A9 BaHo: 1.7 million m³ of earth, 80 per cent recycled
Text Suzanne van Gaale Images JdB Groep

The widening of the A9 Badhoevedorp-Holendrecht requires a lot of sand. To be precise, 1.7 million m³. JdB groep supplied this sand, 80 per cent of which was secondary material. This presents a major logistical challenge: how do you ensure that very large volumes of the right type of sand are delivered and placed in the right location in a short space of time?
The widening and deepening of the A9 is one of the larger projects JdB is involved in. This family-owned company from Hoofddorp is a medium-sized contractor with 160 employees across three locations. It works with sand across the board, from soil and sand remediation and preparing residential areas for construction to landscaping around distribution centres and reinforcing dykes. Example projects include preparing the ‘Kreekrijk’ housing development in Assendelft for construction and occupation, and preparing the Smart Mobility hub in Amsterdam for construction. “Our strength lies in circular, or secondary, sand flows,” says Jan Grisnich, JdB’s operations manager. “Sand we remove from one site can be reused elsewhere. The sand we used on the A9 came from 300 different batches, which we applied in accordance with the applicable quality and environmental standards.”

The right sand in the right place
Commissioned by Rijkswaterstaat, VeenIX is widening and deepening the A9 between Badhoevedorp and Holendrecht. For the widening of the A9, JdB groep supplied a total of 1.7 million m³ of sand on behalf of VeenIX. Of this, 80 per cent was secondary material, equivalent to just under 1.4 million m³. JdB also sourced this secondary sand from within an average radius of 35 kilometres of the A9, in order to achieve the MKI score promised to Rijkswaterstaat. In short, it was a considerable undertaking. “As well as finding the required quantity of sand, we also looked for secondary soil flows with specific qualities. These differences can relate to environmental performance, such as how clean the sand is, or to engineering properties, where the grain size distribution and composition matter. For the temporary bypass at Amstelveen, for example, we used higher-quality sand because it would be recovered later and needed to be easy to reuse elsewhere. It is therefore important for us to know the quality requirements for each specific location, so that we can find the right material for it.”
Challenge
Another challenge was the schedule. Grisnich says: “We had to stick to a fairly tight schedule, which meant sand often had to be delivered at night or at weekends. We had to make sure the required volume was available at those times. For example, not all locations can be loaded at night. That is why we set up several depots specifically for the project. JdB also has a number of its own depots where we store sand temporarily.”
Volumes
Grisnich is proud that JdB was able to work on the A9. “We are based in Hoofddorp and drive along the A9 every day. It is great that, as a medium-sized contractor, we were given the opportunity to contribute to such a large project. We have demonstrated our ability to deliver these volumes to the agreed schedule.”
A business enquiry for JdB groep? Get in touch
Who worked on A9 Badhoevedorp – Holendrecht
- temporary bridges
Janson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility - precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
- foundation specialist
KandtMentioned in Kandt, foundation specialist, delivers quality work on the A9 - welding sheet piles
Marsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling - foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
- foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
- construction cost consultancy
BKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach - UP scaffolding system
PeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen - scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
- Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA9 Badhoevedorp – Holendrecht
- ThemeLower emissions and more reuse
- SubjectRoad construction
- CompanyJdB groep





















