Road construction

Foundation giants join forces

Text Roel van GilsImage TerraFirmA9

Op dit moment is TerraFirmA9 met ruim twintig stellingen actief op het project.
Op dit moment is TerraFirmA9 met ruim twintig stellingen actief op het project.

The widening and below-grade construction of the A9 between Badhoevedorp and Holendrecht, carried out by VeenIX on behalf of Rijkswaterstaat, covers a route of more than 11 kilometres. Given the scale of the project, Gebr. van ’t Hek and Voorbij Funderingstechniek have joined forces. Operating under the name TerraFirmA9, the two foundation giants have been working on the project since 2021, with a ‘large number’ of rigs currently on site.

“We approached each other during the tendering stage to work on the project together,” says Sander Poot, project manager at Gebr. van ’t Hek. “The project is so large that it would be impossible to take it on alone and also serve other clients. No one can do this on their own.” Erik Sandifort, project manager at Voorbij Funderingstechniek, agrees and gives an idea of the enormous quantities involved. “To date, we have installed 20,000 tonnes of sheet piles, 400 tubular piles and 3,300 temporary and permanent anchors.”

The main challenge is the sheer volume of work that needs to be completed in a short time, combined with the logistics involved.

Preparatory works

In 2021-2022, TerraFirmA9 constructed the retaining walls for the bypass, the temporary diversion of the A9. “We spent about a year and a half on that,” says Sandifort. “We installed and anchored various temporary and permanent retaining walls, including carrying out welding on site. We also drilled plenty of piles for a number of temporary bridges, such as the bridge over Keizer Karelplein, currently the longest temporary bridge in the Netherlands. In addition, we extracted old sheet piles and seepage screens and carried out grouting to restore a watertight layer, as well as removing a number of old foundations from demolished structures.” Poot acknowledges that work on the retaining walls for the new A9 only really got under way this year. “And mainly around the centre of Amstelveen, where the road is being built below ground level. VeenIX is building the northern side first, followed by the southern side in two years’ time. That means installing a lot of sheet piles and anchors, both temporary and permanent.”

To date, TerraFirmA9 has installed 20,000 tonnes of sheet piles, 400 tubular piles and 3,300 temporary and permanent anchors.

The Netherlands’ largest foundation project

According to both men, the project is not particularly challenging from a technical point of view. “The main challenge is the sheer volume of work that needs to be completed in a short time, combined with the logistics involved,” says Poot. “In terms of foundation work, this is the largest project currently under way in the Netherlands. On top of that, the project is constantly evolving, which sometimes means the schedule changes. It is our job to manage that by carefully deploying our people and equipment.” The collaboration between the two foundation companies in TerraFirmA9 runs like clockwork. Sandifort says: “It is quite unusual in our line of work to form a consortium with a competitor. There is absolutely no competition within the consortium. The collaboration is excellent. We work together as colleagues on this mega-project.” TerraFirmA9 currently has more than twenty rigs working on the project.  

Een zakelijke vraag aan Voorbij Funderingstechniek? Get in touch

Who worked on A9 Badhoevedorp – Holendrecht

  1. steel producerArcelorMittalMentioned in Steel with a low environmental impact
  2. construction consortiumVeenIXMentioned in Steel with a low environmental impact
  3. design teamKwast ConsultMentioned in EPS structures with a low environmental cost indicator
  4. temporary bridgesJanson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility
  5. clientRijkswaterstaatMentioned in Creative drilling, sawing and demolition
  6. technical designNobleo Bouw & InfraMentioned in The project’s technical conscience
  7. foundation engineering giantVoorbij FunderingstechniekIn this story
  8. radar technologyTerraCartaMentioned in Locating prestressing reinforcement using radar technology
  9. Noise forecastAlcedoMentioned in Managing construction and traffic noise
  10. subcontractorKandt Aannemings- en FunderingsbedrijfMentioned in Specialist contractor and foundation company deploys diverse disciplines on large-scale, complex A9/VeenIX project
  11. precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
  12. foundation specialistKandtMentioned in Kandt, foundation specialist, delivers quality work on the A9
  13. Asset managementINNOCYMentioned in Smart asset management for a safe, high-performing A9
  14. contractorBonneveldMentioned in From cofferdams to reinforced soil
  15. clientFCCMentioned in From cofferdams to reinforced soil
  16. welding sheet pilesMarsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling
  17. foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
  18. foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
  19. construction cost consultancyBKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  20. design teamNobleoMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  21. UP scaffolding systemPeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  22. scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  23. Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA9 Badhoevedorp – Holendrecht
  • ThemeUnderground construction
  • SubjectRoad construction
  • CompanyVoorbij Funderingstechniek
Share this article

Advertisement

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.