Foundation giants join forces
Text Roel van GilsImage TerraFirmA9

The widening and below-grade construction of the A9 between Badhoevedorp and Holendrecht, carried out by VeenIX on behalf of Rijkswaterstaat, covers a route of more than 11 kilometres. Given the scale of the project, Gebr. van ’t Hek and Voorbij Funderingstechniek have joined forces. Operating under the name TerraFirmA9, the two foundation giants have been working on the project since 2021, with a ‘large number’ of rigs currently on site.
“We approached each other during the tendering stage to work on the project together,” says Sander Poot, project manager at Gebr. van ’t Hek. “The project is so large that it would be impossible to take it on alone and also serve other clients. No one can do this on their own.” Erik Sandifort, project manager at Voorbij Funderingstechniek, agrees and gives an idea of the enormous quantities involved. “To date, we have installed 20,000 tonnes of sheet piles, 400 tubular piles and 3,300 temporary and permanent anchors.”

Preparatory works
In 2021-2022, TerraFirmA9 constructed the retaining walls for the bypass, the temporary diversion of the A9. “We spent about a year and a half on that,” says Sandifort. “We installed and anchored various temporary and permanent retaining walls, including carrying out welding on site. We also drilled plenty of piles for a number of temporary bridges, such as the bridge over Keizer Karelplein, currently the longest temporary bridge in the Netherlands. In addition, we extracted old sheet piles and seepage screens and carried out grouting to restore a watertight layer, as well as removing a number of old foundations from demolished structures.” Poot acknowledges that work on the retaining walls for the new A9 only really got under way this year. “And mainly around the centre of Amstelveen, where the road is being built below ground level. VeenIX is building the northern side first, followed by the southern side in two years’ time. That means installing a lot of sheet piles and anchors, both temporary and permanent.”

The Netherlands’ largest foundation project
According to both men, the project is not particularly challenging from a technical point of view. “The main challenge is the sheer volume of work that needs to be completed in a short time, combined with the logistics involved,” says Poot. “In terms of foundation work, this is the largest project currently under way in the Netherlands. On top of that, the project is constantly evolving, which sometimes means the schedule changes. It is our job to manage that by carefully deploying our people and equipment.” The collaboration between the two foundation companies in TerraFirmA9 runs like clockwork. Sandifort says: “It is quite unusual in our line of work to form a consortium with a competitor. There is absolutely no competition within the consortium. The collaboration is excellent. We work together as colleagues on this mega-project.” TerraFirmA9 currently has more than twenty rigs working on the project.
Een zakelijke vraag aan Voorbij Funderingstechniek? Get in touch
Who worked on A9 Badhoevedorp – Holendrecht
- temporary bridges
Janson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility - precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
- foundation specialist
KandtMentioned in Kandt, foundation specialist, delivers quality work on the A9 - welding sheet piles
Marsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling - foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
- foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
- construction cost consultancy
BKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach - UP scaffolding system
PeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen - scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
- Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA9 Badhoevedorp – Holendrecht
- ThemeUnderground construction
- SubjectRoad construction
- CompanyVoorbij Funderingstechniek





















