Smart phasing for the widening and deepening of the A9
Text Suzanne van Gaale Image Novis Roads

For the A9 Badhoevedorp-Holendrecht project, Novis Roads is producing the 3D design for planning and delivering the roadworks phasing. This means determining exactly how the road will be configured during the works. It is a complex task involving many parties.
Jan Roelof Leidekker co-owns Novis Roads with Remco Kluiver and Wouter Bets. The engineering consultancy is part of Novis Group, whose niche is large, multidisciplinary infrastructure projects that it can deliver from start to finish. Leidekker says: “There are six of us, and we have experience on both the contractor and client sides. That means we can respond quickly.” According to Leidekker and Kluiver, their strength lies in working according to the BIM methodology. “By quickly getting a clear understanding of the client’s requirements at the outset, we can think carefully about the desired output, identify the data we need and then present the whole project in 3D. A drawing tells you something, but a 3D image tells you everything.”

BIM methodology
On behalf of Rijkswaterstaat, VeenIX is widening and deepening the A9 between Badhoevedorp and Holendrecht. BIM is an essential tool for designing and coordinating the temporary traffic management phases during the works on the A9. Since traffic must continue to flow on this busy motorway during construction, complex traffic arrangements are introduced in phases. These include temporarily narrowing lanes, reducing the speed limit and shifting the main carriageway to make room for work on bridges, viaducts, the sunken section and the motorway widening. The phasing is fully developed in a 3D BIM model, which also incorporates the road design as a whole. Kluiver says: “The project is divided into three sections, west, central and east, each with its own phasing strategy. This gives us flexibility: a delay in one section does not directly affect another.” The 3D model makes it possible to assess traffic arrangements in advance for buildability, safety and interfaces, both above and below ground. “We identify potential problems during the design phase and can resolve them in good time, ensuring that the design, construction and surrounding area fit together seamlessly.”

The challenges
The project presents particular challenges for Novis Roads. First, the site requires a great deal of careful planning and problem-solving. “We are working in a very confined space, especially on the section near Amstelveen, where we have designed an entire bypass. There, we built a temporary A9 on the south side of the existing motorway. We also have to take account of the interests of various stakeholders, including Schiphol, golfbaan Amsteldijk, Waterschap Rijnland and the various municipalities. There is also considerable pressure to get as much work done as possible in a short time during a closure. All this calls for good collaboration and coordination, not only with colleagues responsible for work preparation and construction, but also with the road authorities, Rijkswaterstaat and the various municipalities.” The coming period will focus on converting the current arrangement into the final configuration. “Normally, you go from phase A to phase B, but here we go from A1, A2, A3 and A4 before eventually reaching B. We want to set up the phases we are putting in place on the road now so that, in the end, everything is permanent and all we have to do is move the white lines. Building this with as little temporary work as possible and with the fewest possible weekend closures is our biggest challenge in the period ahead.”
Pride
Kluiver and Leidekker have been involved in the project since the tender. Asked what they are most proud of, Kluiver replies: “We started sketching on paper during the tender in 2018. Looking at what we have built so far, it still matches what we came up with back then. This was also Novis Roads’ first major infrastructure project. The fact that everything has gone well so far is certainly something we are very proud of.”
Question about this story? Ask your question
Who worked on A9 Badhoevedorp – Holendrecht
- temporary bridges
Janson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility - precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
- foundation specialist
KandtMentioned in Kandt, foundation specialist, delivers quality work on the A9 - welding sheet piles
Marsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling - foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
- foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
- construction cost consultancy
BKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach - UP scaffolding system
PeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen - scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
- Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA9 Badhoevedorp – Holendrecht
- SubjectRoad construction