Managing construction and traffic noise

Text Roel van GilsImage Alcedo

Alcedo berekent voor de A9 per half jaar wat de geluidsimpact is van de werkzaamheden op de omgeving gedurende die periode.
Alcedo berekent voor de A9 per half jaar wat de geluidsimpact is van de werkzaamheden op de omgeving gedurende die periode.

Commissioned by Rijkswaterstaat, construction consortium VeenIX is widening the A9 between the Badhoevedorp and Holendrecht interchanges. Near Amstelveen, the motorway is being lowered over a 1.6-kilometre stretch. For a major infrastructure project like this, it is standard practice to forecast construction noise in advance. VeenIX therefore contacted Alcedo at an early stage to assess and, where possible, minimise potential construction and traffic noise. 

An operation like this on the A9 inevitably generates considerable construction noise. “The Building Decree sets out the rules on construction noise,” says Gertie Spiegelenberg of Alcedo. “VeenIX must comply with these rules and demonstrate, through a noise forecast, that it meets the assessment framework set out in the Building Decree.” 

Construction consortium VeenIX is making a strong commitment to low-noise techniques to minimise disruption to the surrounding area.

Noise model

For the A9, Alcedo calculates the noise impact of the works on the surrounding area for each six-month period. “VeenIX sometimes gives us a list of many hundreds of tasks, which we convert into a noise model and assess against the Building Decree,” Gertie explains. “If a task exceeds the limit value, we assess it against Amstelveen municipality’s assessment framework. The municipality has drawn up a separate exemption scheme, under which an exemption can still be granted. This is subject to conditions, including demonstrable use of the quietest available technique.”

Low-noise techniques

Construction consortium VeenIX is making a strong commitment to low-noise techniques to minimise disruption to the surrounding area. “For example, no piles are being driven for the lowered section in the centre of Amstelveen. Equipment for night-time work is also carefully selected, such as using a grab instead of a breaker. Another advantage is that noise moves around on a project like this. Work is not carried out continuously in the same place. Traffic can also continue to use the A9. Sometimes, you hardly even notice the construction work,” Gertie says. “VeenIX has been working on the project for a few years now, and so far there have been very few noise complaints from the surrounding area.” 

In addition to construction noise, Alcedo also assesses traffic noise from the diversions. The A9 is temporarily rerouted at various locations. “During the various temporary phases, noise from the A9 must not exceed the level in the 2010 Route Decision scenario. Sensors and instruments are used to monitor whether construction and traffic noise remain within acceptable limits. All of this is done remotely,” Gertie concludes.   

A business enquiry for ALCEDO? Get in touch

Who worked on A9 Badhoevedorp – Holendrecht

  1. steel producerArcelorMittalMentioned in Steel with a low environmental impact
  2. construction consortiumVeenIXMentioned in Steel with a low environmental impact
  3. design teamKwast ConsultMentioned in EPS structures with a low environmental cost indicator
  4. temporary bridgesJanson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility
  5. clientRijkswaterstaatMentioned in Creative drilling, sawing and demolition
  6. technical designNobleo Bouw & InfraMentioned in The project’s technical conscience
  7. foundation engineering giantVoorbij FunderingstechniekMentioned in Foundation giants join forces
  8. radar technologyTerraCartaMentioned in Locating prestressing reinforcement using radar technology
  9. Noise forecastAlcedoIn this story
  10. subcontractorKandt Aannemings- en FunderingsbedrijfMentioned in Specialist contractor and foundation company deploys diverse disciplines on large-scale, complex A9/VeenIX project
  11. precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
  12. foundation specialistKandtMentioned in Kandt, foundation specialist, delivers quality work on the A9
  13. Asset managementINNOCYMentioned in Smart asset management for a safe, high-performing A9
  14. contractorBonneveldMentioned in From cofferdams to reinforced soil
  15. clientFCCMentioned in From cofferdams to reinforced soil
  16. welding sheet pilesMarsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling
  17. foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
  18. foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
  19. construction cost consultancyBKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  20. design teamNobleoMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  21. UP scaffolding systemPeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  22. scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  23. Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA9 Badhoevedorp – Holendrecht
  • SubjectNews
  • CompanyALCEDO