Managing construction and traffic noise
Text Roel van GilsImage Alcedo

Commissioned by Rijkswaterstaat, construction consortium VeenIX is widening the A9 between the Badhoevedorp and Holendrecht interchanges. Near Amstelveen, the motorway is being lowered over a 1.6-kilometre stretch. For a major infrastructure project like this, it is standard practice to forecast construction noise in advance. VeenIX therefore contacted Alcedo at an early stage to assess and, where possible, minimise potential construction and traffic noise.
An operation like this on the A9 inevitably generates considerable construction noise. “The Building Decree sets out the rules on construction noise,” says Gertie Spiegelenberg of Alcedo. “VeenIX must comply with these rules and demonstrate, through a noise forecast, that it meets the assessment framework set out in the Building Decree.”

Noise model
For the A9, Alcedo calculates the noise impact of the works on the surrounding area for each six-month period. “VeenIX sometimes gives us a list of many hundreds of tasks, which we convert into a noise model and assess against the Building Decree,” Gertie explains. “If a task exceeds the limit value, we assess it against Amstelveen municipality’s assessment framework. The municipality has drawn up a separate exemption scheme, under which an exemption can still be granted. This is subject to conditions, including demonstrable use of the quietest available technique.”
Low-noise techniques
Construction consortium VeenIX is making a strong commitment to low-noise techniques to minimise disruption to the surrounding area. “For example, no piles are being driven for the lowered section in the centre of Amstelveen. Equipment for night-time work is also carefully selected, such as using a grab instead of a breaker. Another advantage is that noise moves around on a project like this. Work is not carried out continuously in the same place. Traffic can also continue to use the A9. Sometimes, you hardly even notice the construction work,” Gertie says. “VeenIX has been working on the project for a few years now, and so far there have been very few noise complaints from the surrounding area.”
In addition to construction noise, Alcedo also assesses traffic noise from the diversions. The A9 is temporarily rerouted at various locations. “During the various temporary phases, noise from the A9 must not exceed the level in the 2010 Route Decision scenario. Sensors and instruments are used to monitor whether construction and traffic noise remain within acceptable limits. All of this is done remotely,” Gertie concludes.
A business enquiry for ALCEDO? Get in touch
Who worked on A9 Badhoevedorp – Holendrecht
- temporary bridges
Janson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility - precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
- foundation specialist
KandtMentioned in Kandt, foundation specialist, delivers quality work on the A9 - welding sheet piles
Marsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling - foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
- foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
- construction cost consultancy
BKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach - UP scaffolding system
PeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen - scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
- Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA9 Badhoevedorp – Holendrecht
- SubjectNews
- CompanyALCEDO





















