Road construction

Steel with a low environmental impact

Text Roel van GilsImage Rijkswaterstaat

ArcelorMittal is een bekend gezicht op het A9-project.
ArcelorMittal is een bekend gezicht op het A9-project.

ArcelorMittal has supplied steel for various projects in Rijkswaterstaat’s Schiphol, Amsterdam, Almere road expansion programme. The steel producer is also making a substantial contribution to the programme’s fifth and final section, the A9 Badhoevedorp, Holendrecht. ArcelorMittal is expected to supply more than 16,000 tonnes of steel in just four months. And that is not all. We spoke to Roel Bijlard of ArcelorMittal about this huge operation. 

The 20,000 tonnes are exclusively for construction of the sunken section in Amstelveen.

ArcelorMittal is a familiar presence on the project. “Over the course of 2022, we supplied around 4,000 tonnes of steel for various smaller structures,” Bijlard begins. “However, the bulk of our work falls in the first two quarters of 2023. Between February and June, we supplied more than 16,000 tonnes of steel sheet piles to the VeenIX consortium. As well as sheet piles, ArcelorMittal is also supplying the combined wall. “This involves 2,200 tonnes of tubular piles with interlocks (914x16mm and 914x20mm), of which 1,800 tonnes are for temporary use and 400 tonnes for permanent works. We are also producing a further 1,100 tonnes of bored piles, 457 mm in diameter, with wall thicknesses between 10 and 16 mm. This means we are supplying almost the entire range of our products for this project. That has a considerable impact, although we know how to manage it.” 

Sustainable (re)use of steel 

Of the 16,000 tonnes of steel sheet piles, 9,000 tonnes are being used for temporary structures. The remaining 7,000 tonnes of sheet piles will be installed as permanent works. “For temporary structures, we often offer a hire or buy-back contract. This guarantees that we take the materials back into our stock once the project is complete. ArcelorMittal will also buy back the temporary combined wall after the project. All these materials can then be used on future projects. For this project, we are supplying both used and new sheet piles from our stock in the Netherlands. The remainder is being supplied as newly manufactured sheet piles from the factory in Luxembourg. This combination was also chosen because the quantity is so enormous and must be supplied within a short timeframe. It is also a logistical challenge, with deliveries to the site by both inland waterway and road.” 

Of the 16,000 tonnes of steel sheet piles, 9,000 tonnes are being used for temporary structures.

EcoSheetPile™ 

The 20,000 tonnes are exclusively for construction of the sunken section in Amstelveen. “Hopefully that won’t be all, because a substantial number of sheet piles will also be driven into the ground in the final phase of this project,” says Bijlard. ArcelorMittal has also supported the VeenIX consortium by calculating the sustainability and end-of-life scenarios for the sheet piles. “We have drawn up as realistic a picture as possible and presented it to the consortium. Because many of the structures are temporary, a lot of the steel can be reused elsewhere later. This has a major effect on the project’s eventual environmental impact. The sheet piles we supply are also produced from approximately 100% scrap in an electric arc furnace, including the (used) sheet piles from stock. This results in a much lower environmental impact (430 kg CO2 per tonne) than sheet piles produced in a blast furnace (approximately 2,500 kg CO2 per tonne). We can now also supply sheet piles made from scrap using 100% green electricity, reducing the impact further to 360 kg CO2 per tonne. EPDs for both products, EcoSheetPile™ and EcoSheetPile™ Plus (made using 100% green electricity), have recently been published for the Dutch market.”     

Een zakelijke vraag aan ArcelorMittal Projects Europe B.V.? Get in touch

Who worked on A9 Badhoevedorp – Holendrecht

  1. steel producerArcelorMittalIn this story
  2. construction consortiumVeenIXIn this story
  3. design teamKwast ConsultMentioned in EPS structures with a low environmental cost indicator
  4. temporary bridgesJanson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility
  5. clientRijkswaterstaatMentioned in Creative drilling, sawing and demolition
  6. technical designNobleo Bouw & InfraMentioned in The project’s technical conscience
  7. foundation engineering giantVoorbij FunderingstechniekMentioned in Foundation giants join forces
  8. radar technologyTerraCartaMentioned in Locating prestressing reinforcement using radar technology
  9. Noise forecastAlcedoMentioned in Managing construction and traffic noise
  10. subcontractorKandt Aannemings- en FunderingsbedrijfMentioned in Specialist contractor and foundation company deploys diverse disciplines on large-scale, complex A9/VeenIX project
  11. precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
  12. foundation specialistKandtMentioned in Kandt, foundation specialist, delivers quality work on the A9
  13. Asset managementINNOCYMentioned in Smart asset management for a safe, high-performing A9
  14. contractorBonneveldMentioned in From cofferdams to reinforced soil
  15. clientFCCMentioned in From cofferdams to reinforced soil
  16. welding sheet pilesMarsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling
  17. foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
  18. foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
  19. construction cost consultancyBKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  20. design teamNobleoMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach
  21. UP scaffolding systemPeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  22. scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
  23. Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA9 Badhoevedorp – Holendrecht
  • ThemeLower emissions and more reuse
  • SubjectRoad construction
  • CompanyArcelorMittal Projects Europe B.V.
  • CompanyVeenIX
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.