EPS structures with a low environmental cost indicator
Text Roel van GilsImage VeenIX

For the widening and sunken construction of the A9 between Badhoevedorp and Holendrecht, construction consortium VeenIX, working on behalf of Rijkswaterstaat, is making extensive use of EPS as a lightweight fill material. Joosten Groep’s specialists are supporting the consortium with the design, supply and installation of the EPS structures and have already made a number of significant optimisations.
Joosten Groep has specialist expertise and can provide everything related to infrastructure, water management and green spaces in the public realm. “It is on projects of this scale that our strengths really come to the fore. We know that more is required than simply supplying materials,” says Martin Wal, commercial director at Joosten Groep. “Every major project has its own challenges in terms of design, planning and finances. As a group, we can work as a partner to help develop smart solutions that can make a difference to quality, construction time, environmental cost indicator and price. Our team of specialists can support a contractor with the design of a lightweight fill structure, the supply of EPS materials and their installation through our partner Bonneveld. At Joosten, we call this the OLA principle: design, supply and install.”

Project team
Within Joosten Groep, the A9 Badhoevedorp–Holendrecht project is classified as a GP project. “A project of this scale calls for the right people, with the right knowledge and experience,” says Wal. “That is why we formed a project team almost immediately. We take this approach on all major infrastructure projects, and it is appreciated, including by VeenIX.” Joosten has a dedicated team on the project as the point of contact, representing all interests. When VeenIX engaged Joosten Groep, EPS had been specified as lightweight fill material for the construction of many structures. “A large volume of EPS had been budgeted for, using a heavy grade. The project also had an environmental cost indicator requirement. We then put forward Erik Kwast of Kwast Consult to join the design team. Erik is also a partner at Joosten Concepts, part of Joosten Groep. This enabled us to help optimise the heavy EPS grades to a lighter grade. This optimised solution significantly reduced the total environmental impact of the EPS supplied and also delivered a financial benefit. In addition, we can offer a take-back guarantee for the EPS supplied at the end of its service life. Together, these factors result in an exceptionally low environmental cost indicator.”

One thing leads to another
The optimised design, combined with the low environmental cost indicator, meant that Joosten Groep supplied more than 35,000 m3 of EPS for the project last year alone. “We have now won the tender for the next section as well,” says Wal, with justified pride. And there is more. “At Joosten Groep, we always take an integrated approach to structures. A reinforced soil structure is often built on top, or a gabion wall is installed against it. We coordinate these interfaces internally at Joosten and develop the integrated design together with the client. We also deliver such structures according to the OLA principle, carrying out the design, supply and construction as an integrated package with our regular partners. In addition, the consortium can draw on our broad product range for the project. For example, large plastic pipeline routes have also been supplied, along with bespoke PE chambers produced by Joosten Productie en Lastechniek and delivered to site. That is where Joosten Groep’s strength lies. We bring knowledge and expertise to the project from a competitive position. With this approach, the contractor or consortium can address many complex challenges with just one partner on board.”
A business enquiry for Joosten Groep? Get in touch
Who worked on A9 Badhoevedorp – Holendrecht
- design teamKwast ConsultIn this story
- temporary bridges
Janson BridgingMentioned in Temporary bridges on and over the A9 safeguard mobility - precision drilling technologyInterboor MidslandMentioned in Widening the Schipholbrug: precision drilling between parabolic prestressing tendons
- foundation specialist
KandtMentioned in Kandt, foundation specialist, delivers quality work on the A9 - welding sheet piles
Marsé MontageMentioned in Specialist welding on the A9: welding 21 kilometres of sheet piling - foundation contractor consortiumDe Vries TitanMentioned in The Netherlands’ largest anchor pile project
- foundation contractor consortiumBAUER FunderingstechniekMentioned in The Netherlands’ largest anchor pile project
- construction cost consultancy
BKS SchagenMentioned in A9: BKS Schagen demonstrates the value of its expertise and approach - UP scaffolding system
PeriMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen - scaffolding structuresVan der PanneMentioned in Van der Panne installs special viewing tower alongside A9 Amstelveen
- Type C self-drilling anchor pilesHigh 5 SolutionsMentioned in A9: Smart solution for testing anchor piles next to a sheet-pile wall
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA9 Badhoevedorp – Holendrecht
- SubjectRoad construction
- CompanyKwast Consult
- CompanyJoosten Groep
- CompanyBonneveld BV