Water infrastructure

Sewage pumps: bespoke solutions from start to finish

Sewage pumps: bespoke solutions from start to finish

Pentair has been awarded a contract to supply ten Pentair Fairbanks Nijhuis sewage pumps for the renovation and renewal of the wastewater pressure main (AWP) operated by Waterschap Brabantse Delta. Project manager Edwin Wolterink describes it as a bespoke solution from start to finish, with the pumps at the two pumping stations also being fitted with clog-resistant impellers.

Commissioned by GMB Waterkwaliteit & Installaties, Pentair’s Winterswijk branch will supply the pumps for the pumping stations in Roosendaal and Bergen op Zoom, and the effluent pumping station at the Bath wastewater treatment plant. “The project presents us with two major challenges, for which we have found suitable solutions. The first is to tackle clogging at the two pumping stations, and the second is to achieve the high efficiency required to ensure the effluent pumping station operates as efficiently as possible. As the existing pumps are from another supplier, the new pumps have to be custom-made so that they fit directly into the existing installation. It is a great bespoke solution that keeps conversion costs to a minimum.”

Clogging problems

AWP 2.0 is one of the larger wastewater systems in the Netherlands. “Like many other systems, Brabantse Delta’s 60-kilometre AWP also suffers from clogging,” says Ester Reusink, communications manager at Pentair. “The growing amount of non-dissolvable, fibre-rich wipes is becoming an increasingly serious problem in the wastewater sector. The existing pumps are regularly taken out of service by blockages caused, among other things, by these wipes entering the sewer.” According to Wolterink, this is due to the impellers’ incorrect geometry, which causes a great deal of trouble. Pentair’s Winterswijk branch is continually developing its pumps and pumping systems. “The composition of wastewater has changed enormously. For example, the amount of fibre-containing wipes increases every year. Pentair has spent the past few years looking into this problem, and we are responding by continually improving our impellers.”

With its own foundry, machining, assembly and testing facilities, Pentair Fairbanks Nijhuis supports its customers from start to finish.

Scale model test

Another advantage of Pentair’s pumps is their very wide operating range. Wolterink: “The capacity of the pumps we use in West Brabant ranges from 2,000 m3 per hour in dry weather to 20,000 m3 during rainfall. The pumps perform excellently in all conditions, so discharge capacity is always maximised. We designed and calculated the pumps entirely in-house, tailoring them to the specific situation. Our Winterswijk site has its own R&D and engineering department. With our own foundry, machining, assembly and testing facilities, we support our customers from start to finish. All the pumps were successfully tested in our scale model test in December last year.”

The renovation is being carried out in phases, as the sewage pumping stations and the wastewater treatment plant’s effluent pumping station must remain operational throughout the work. The first pump will be replaced in December this year.

Pentair has also signed a multi-year maintenance contract with Waterschap Brabantse Delta. “After the large-scale replacement programme, we will maintain the pumps for fifteen years,” says Reusink. “We support the water authority from start to finish, from design and production through to installation and maintenance.”

Een zakelijke vraag aan Pentair Fairbanks Nijhuis? Get in touch

Who worked on AWP 2.0

  1. construction of the second pipelineGW LeidingtechniekMentioned in Update on the renovation of the Wastewater Rising Main
  2. consultancyKragtenMentioned in Update on the renovation of the Wastewater Rising Main
  3. process automationCroon Wolter en DrosMentioned in Update on the renovation of the Wastewater Rising Main
  4. main contractorGMBMentioned in AWP 2.0: Always in operation
  5. the pumpsPentairMentioned in AWP 2.0: Always in operation
  6. E&PAHoppenbrouwersMentioned in AWP 2.0: Always in operation
  7. clientWaterschap Brabantse DeltaMentioned in AWP 2.0: Always in operation
  8. temporary pumping installationsVan der KampMentioned in AWP 2.0: Always in operation
  9. designRHDHVMentioned in AWP 2.0: Always in operation
  10. BIM coordinatorRoyal HaskoningDHVMentioned in A bird’s-eye view prevents surprises
  11. Pump controlHoppenbrouwers TechniekMentioned in A helicopter view prevents surprises
  12. temporary pumping installationsVan der Kamp PompenMentioned in Temporary pumping installations safeguard AWP continuity

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAWP 2.0
  • SubjectWater infrastructure
  • CompanyPentair Fairbanks Nijhuis
  • CompanyGMB
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.