Specials

AWP 2.0: Always in operation

AWP 2.0: Always in operation

Waterschap Brabantse Delta will spend the coming years renovating and renewing the existing wastewater pressure pipeline (AWP). The pipeline runs from the Moerdijk industrial estate to the wastewater treatment plant in Bath. We talk to project manager Adrie Giljam of integrated main contractor GMB Waterkwaliteit & Installaties about the project and its challenges.

Formally, GMB is the main contractor and the other parties are subcontractors. In practice, there is little sign of this distinction and they are all partners.

Multidisciplinary approach and collaboration

As main contractor, GMB Waterkwaliteit & Installaties is carrying out the work together with its partners: Van der Kamp for the temporary pumping installations, Pentair Nijhuis for the pumps, Hoppenbrouwers for the E&PA and RHDHV for the design, under the name PAUW (Persstations AWP Ultieme Werking). “We were awarded the contract in July 2018 on the basis of EMVI,” says Giljam. “Traditional contract forms are increasingly giving way to agreements tailored to the client’s requirements. As the Netherlands’ leading integrated water quality contractor, we can make full use of our multidisciplinary approach and process engineering expertise. And we have to, because the biggest challenge is ensuring that the work never brings wastewater transport to a halt. Discharge capacity must be maintained. We combine ingenuity with predictability, reliability and safety. The latter is in our DNA.”

PAUW devotes considerable time and attention to building an effective partnership with the client, as this is the foundation of a successful project. The process began with an extensive ProjectSamenwerkingsStartUp (PSSU) in June 2018, followed by quarterly ProjectFollowUp’s (PFU), allowing the project objectives to be regularly reviewed and discussed. At the end of August, the PAUW and Waterschap Brabantse Delta delivery teams held a PSSU-Uitvoering, focusing in depth on working together during the construction phase, with particular attention to safety. A range of topics was discussed. As expected, keeping the AWP in operation was a recurring theme. Investment is also being made in collaboration between the internal teams.  

Formally, GMB is the main contractor and the other parties are subcontractors. “In practice, there is little sign of this distinction and we are all partners,” says Giljam. “We are all working in the interests of the project, and therefore of the client. Central coordination is provided by GMB’s IPM team.” In addition to project management (the IPM organisation), GMB’s scope includes all building renovation work, civil engineering modifications, infrastructure and pipeline work, and mechanical engineering activities. 

Formally, GMB is the main contractor and the other parties are subcontractors.
In practice, there is little sign of this distinction and they are all partners.

Work plan

The pumping stations are being renovated in phases, with GMB scheduling the necessary shutdowns (UBNs). Giljam says: “We have already carried out one UBN for inspection work. A detailed work plan is drawn up for each UBN and agreed with Waterschap Brabantse Delta. It is essential that these shutdowns are carried out safely and predictably, within the specified conditions.” 

At the Bath site, the emergency overflow was modified in June this year. Work is now well under way at the Roosendaal pumping station. Building work has been completed in preparation for installing the new transformers, and modifications have been made to the existing odour control system. The first new pump line at Roosendaal will be ready in March 2020. “Together with the water board, we are on course to deliver a successful project. The entire project will be handed over in September 2022,” Giljam concludes. 

Een zakelijke vraag aan Pentair Fairbanks Nijhuis? Get in touch

Who worked on AWP 2.0

  1. construction of the second pipelineGW LeidingtechniekMentioned in Update on the renovation of the Wastewater Rising Main
  2. consultancyKragtenMentioned in Update on the renovation of the Wastewater Rising Main
  3. process automationCroon Wolter en DrosMentioned in Update on the renovation of the Wastewater Rising Main
  4. main contractorGMBMentioned in AWP 2.0: Always in operation
  5. the pumpsPentairMentioned in AWP 2.0: Always in operation
  6. E&PAHoppenbrouwersMentioned in AWP 2.0: Always in operation
  7. clientWaterschap Brabantse DeltaMentioned in AWP 2.0: Always in operation
  8. temporary pumping installationsVan der KampMentioned in AWP 2.0: Always in operation
  9. designRHDHVMentioned in AWP 2.0: Always in operation
  10. BIM coordinatorRoyal HaskoningDHVMentioned in A bird’s-eye view prevents surprises
  11. Pump controlHoppenbrouwers TechniekMentioned in A helicopter view prevents surprises
  12. temporary pumping installationsVan der Kamp PompenMentioned in Temporary pumping installations safeguard AWP continuity

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAWP 2.0
  • SubjectSpecials
  • CompanyGMB
  • CompanyPentair Fairbanks Nijhuis
  • CompanyHoppenbrouwers Techniek
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.