Robust and sustainable for the future

Robust and sustainable for the future

The West Brabant wastewater pressure pipeline (AWP) is now almost fifty years old, and the associated pumping stations have proved insufficiently reliable. The pumps are reaching the end of their service life and can no longer cope with increased demand. Emergency pumping installations are now in permanent use. This prompted Waterschap Brabantse Delta to renovate and renew the wastewater pressure pipeline, so that capacity and continuity can once again be guaranteed for the next fifty years.

The AWP collects wastewater from households and businesses in 35 villages and towns in West Brabant. All this wastewater is treated in Bath and then returned to nature via the Westerschelde. “The pipeline network is 60 kilometres long and was originally built with a certain amount of spare capacity,” says Frank van Zijl of Waterschap Brabantse Delta. “In the past, when work was being carried out on the installation, we could easily switch off one of the two pumps at the pumping stations in Roosendaal and Bergen op Zoom. That has not been possible for years. In recent years, an emergency pumping installation has been in permanent use, and maintenance work on the installation has become quite costly.”

Two contracts

To make the AWP robust for the future again, the water board issued a tender in 2017 for the large-scale renovation and renewal of the existing installation. “We split the contract into two parts,” says Van Zijl. “Extensive investigations in 2013 showed that the pipeline network is still in excellent condition. However, it needs to be expanded in places to meet the higher capacity requirements. The work therefore also includes laying a second pipeline along a 3.5-kilometre section to handle larger volumes of wastewater. This contract is being carried out by GW Leidingtechniek. The other contract covers the renovation and renewal of the two pumping stations and the effluent pumping station at the wastewater treatment plant in Bath. This is a complex contract known as AWP 2.0. In effect, everything connected by a wire is being replaced,” says Van Zijl.

Route overview

EMVI commitment

Five consortia expressed interest during the tendering phase for AWP 2.0. Van Zijl says: “Two of them ultimately submitted a bid. We selected PAUW (GMB WK&I, Van der Kamp, Pentair Nijhuis, Hoppenbrouwers and RHDHV) because it offered the best quality: an optimal combination of risk management and price. PAUW assures us that continuity of the AWP will be guaranteed at all times. During the construction phase, a pump will always be on standby to take over seamlessly if problems arise. This is an EMVI commitment that we value and which, among other things, helped secure the winning bid. For us as a water board, it is important to complete the construction project without risk and at the most economically attractive price possible. This means maintaining functionality ‘along the way’ and guaranteeing safe processes, both for a safe working environment for our colleagues and for subcontractors, so that the result is operational, manageable and maintainable.”

According to Van Zijl, the renovated and renewed AWP will pump wastewater in the most sustainable way possible, making maximum use of gravity at the pumping stations. “The design incorporates many smart technologies. We are also making huge strides in process automation, with real-time insight into all installations and smart control software. To
further guarantee operational reliability, we have signed a 15-year maintenance contract with a performance guarantee, under which the pumps may be unavailable for their intended function for no more than 20 hours per year. This gives us the assurance of
a robust and reliable system for the future.” 

Een zakelijke vraag aan GW Leidingtechniek BV? Get in touch

Who worked on AWP 2.0

  1. construction of the second pipelineGW LeidingtechniekMentioned in Update on the renovation of the Wastewater Rising Main
  2. consultancyKragtenMentioned in Update on the renovation of the Wastewater Rising Main
  3. process automationCroon Wolter en DrosMentioned in Update on the renovation of the Wastewater Rising Main
  4. main contractorGMBMentioned in AWP 2.0: Always in operation
  5. the pumpsPentairMentioned in AWP 2.0: Always in operation
  6. E&PAHoppenbrouwersMentioned in AWP 2.0: Always in operation
  7. clientWaterschap Brabantse DeltaMentioned in AWP 2.0: Always in operation
  8. temporary pumping installationsVan der KampMentioned in AWP 2.0: Always in operation
  9. designRHDHVMentioned in AWP 2.0: Always in operation
  10. BIM coordinatorRoyal HaskoningDHVMentioned in A bird’s-eye view prevents surprises
  11. Pump controlHoppenbrouwers TechniekMentioned in A helicopter view prevents surprises
  12. temporary pumping installationsVan der Kamp PompenMentioned in Temporary pumping installations safeguard AWP continuity

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAWP 2.0
  • ThemeFlood protection and climate-resilient water management
  • SubjectSpecials
  • CompanyGW Leidingtechniek BV
  • CompanyGMB
  • CompanyPentair Fairbanks Nijhuis
  • CompanyHoppenbrouwers Techniek