Waterschap Brabantse Delta will spend the coming years renovating and renewing the existing wastewater pressure main (AWP). The pipeline runs from the Moerdijk industrial estate to the wastewater treatment plant in Bath. We spoke to project manager Adrie Giljam of integrated main contractor GMB Waterkwaliteit & Installaties about the project and its challenges.

GMB is formally the main contractor, with the other parties acting as subcontractors. In practice, however, there is little sign of this distinction and they are all partners.

Multidisciplinary approach and collaboration

As main contractor, GMB Waterkwaliteit & Installaties is carrying out the work in collaboration with its partners: Van der Kamp for the temporary pumping installations, Pentair Nijhuis for the pumps, Hoppenbrouwers for the E&PA, and RHDHV for the design, under the name PAUW (Persstations AWP Ultieme Werking). “We were awarded the project in July 2018 on the basis of EMVI,” says Giljam. “Traditional forms of contract are increasingly giving way to agreements tailored to the client’s requirements. As the Netherlands’ leading integrated water quality contractor, we can make full use of our multidisciplinary approach and process engineering expertise. We have to, because the biggest challenge is ensuring that the work never brings wastewater transport to a standstill. The flow capacity must be maintained at all times. We combine innovation with predictability, reliability and safety. Safety is in our DNA.”

PAUW devotes considerable time and attention to effective collaboration with the client, as this is the foundation of a successful project. The process began with an extensive ProjectSamenwerkingsStartUp (PSSU) in June 2018, followed by quarterly ProjectFollowUp’s (PFU), enabling the project objectives to be regularly reviewed and discussed. At the end of August, the PAUW and Waterschap Brabantse Delta delivery teams held an extensive PSSU-Uitvoering, focusing on collaboration during the construction phase, with particular attention to safety. A range of topics was discussed. Naturally, the continuity of the AWP was a recurring theme. Investment is also being made in collaboration within the teams.  

GMB is formally the main contractor, with the other parties acting as subcontractors. “In practice, there is little sign of this distinction and we are all partners,” says Giljam. “We are all working in the interests of the project, and therefore of the client. Overall direction is provided by GMB’s IPM team.” In addition to project management through the IPM organisation, GMB’s scope includes all building renovation work, civil engineering modifications, infrastructure and pipeline work, and mechanical engineering activities. 

GMB is formally the main contractor, with the other parties acting as subcontractors.
In practice, however, there is little sign of this distinction and they are all partners.

Work plan

The pumping stations are being renovated in phases, with GMB scheduling the necessary shutdowns (UBN’s). Giljam says: “We have already had one shutdown to carry out inspections. A detailed work plan is drawn up for each shutdown and agreed with Waterschap Brabantse Delta. It is vital that these shutdowns are carried out safely and predictably, within the specified constraints.” 

At the Bath site, the emergency overflow was modified in June this year. Work is now in full swing at the Roosendaal pumping station. Building work has been completed to prepare for the installation of the new transformers, and modifications have been made to the existing odour control system. The first new pump line in Roosendaal will be ready in March 2020. “Together with the water authority, we are on track to deliver a successful project. The entire project will be completed in September 2022,” Giljam concludes. 

Een zakelijke vraag aan Pentair Fairbanks Nijhuis? Get in touch

Who worked on AWP 2.0

  1. construction of the second pipelineGW LeidingtechniekMentioned in Update on the renovation of the Wastewater Rising Main
  2. consultancyKragtenMentioned in Update on the renovation of the Wastewater Rising Main
  3. process automationCroon Wolter en DrosMentioned in Update on the renovation of the Wastewater Rising Main
  4. main contractorGMBIn this story
  5. the pumpsPentairIn this story
  6. E&PAHoppenbrouwersIn this story
  7. clientWaterschap Brabantse DeltaIn this story
  8. temporary pumping installationsVan der KampIn this story
  9. designRHDHVIn this story
  10. BIM coordinatorRoyal HaskoningDHVMentioned in A bird’s-eye view prevents surprises
  11. Pump controlHoppenbrouwers TechniekMentioned in A helicopter view prevents surprises
  12. temporary pumping installationsVan der Kamp PompenMentioned in Temporary pumping installations safeguard AWP continuity

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAWP 2.0
  • SubjectSpecials
  • CompanyGMB
  • CompanyPentair Fairbanks Nijhuis
  • CompanyHoppenbrouwers Techniek
  • CompanyWaterschap Brabantse Delta
  • CompanyVan der Kamp
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.