Reducing failure costs and preventing damage: isn’t that what every company wants? The pump industry is no exception, especially when you consider the consequences of a pump failing to operate. GMB builds and renovates, through its various clusters, dykes, port sites, sewer systems, pumping stations, water treatment plants and sludge processing plants, among other things.

The Water Quality and Installations cluster has a ‘state-of-the-art’ method for reducing the risk of failure in a new pump installation to an absolute minimum. Together with their partners, they create a so-called ‘digital twin’ before the pump is commissioned, and use it to simulate its operation. Marc Vogt, design manager at GMB, takes us through the process.

Dry testing for maximum risk control

“The best way to explain how the digital twin works is to use the AWP 2.0 project for Waterschap Brabantse Delta, which is currently under way,” Vogt begins. . “We are currently renovating three pumping stations, replacing two old pumps with three new ones at each station. The first pump was recently commissioned, and we had already established that it would operate without any problems. Beforehand, together with our partners, we created a digital twin of the discharge station. This means that the pump, pipes and instrumentation were recreated virtually so they could operate in a digital simulation. We then fed the simulation data using software from our partner RHDHV, including data on artificial rainfall, local measurements and all kinds of system influences that affect operation, as well as, importantly, test data for the pump from our partner Pentair. The software from our partner Hoppenbrouwers links everything together. The result is a virtual pump in operation, subject to influences that are certain to occur in real life at some point. A kind of digital baptism of fire…”

But the simulation does not stop there. Vogt explains: “This dry, virtual test also gives us the opportunity to simulate all kinds of operating conditions. You can’t get more certainty in advance. The great thing is that you can fine-tune and adjust things in the simulation, then transfer them directly to the real installation once they have been proven to work. That gives us confidence.”

Overview of the three pump lines.

Enormous time savings

As well as providing certainty about the technology, the digital twin also saves a huge amount of time. “It makes sense, really, because without digital testing we would depend on peak conditions occurring in real life. We would have to wait for severe weather and hope the installation could withstand it. Apart from the time that would take, there would be a real risk of damage. ‘Trial and error’ is not desirable with pump installations of this size. Not only because of the costs of possible damage to the installation, but above all because of the impact on the surrounding area if a pumping station like this fails. Yet another reason to be grateful that virtual testing is possible. Computers are patient. There is no problem running a 24-hour virtual test; we simulate in ‘real time’.”    

The first time leaves you wanting more

This is the first time GMB has worked in this way. “That was possible because this particular project lends itself to it,” Vogt explains. “These pumps are large and powerful. And the discharge must be guaranteed throughout the works. In the virtual environment, we can push things to the absolute limit… The forces involved are so great that doing this in a real-world situation could cause enormous damage. That would cost time and money, and would effectively destroy capital. Now we can test with the shop open, as the saying goes. The old pumps keep running, the new pump is commissioned reliably, and it is simply a matter of replacing the old equipment without unnecessary delays.”

Taking a predictive approach

Vogt concludes: “There is more and more you can do with it. The pump that has now been commissioned is also being monitored. We link that data to the initial test results, and so far everything matches. That gives us a degree of validation. By analysing the data, we will even be able to make predictions. That is the future, and it will be ideal, for example, for further optimising systems.”    

Een zakelijke vraag aan Pentair Fairbanks Nijhuis? Get in touch

Who worked on AWP 2.0

  1. construction of the second pipelineGW LeidingtechniekMentioned in Update on the renovation of the Wastewater Rising Main
  2. consultancyKragtenMentioned in Update on the renovation of the Wastewater Rising Main
  3. process automationCroon Wolter en DrosMentioned in Update on the renovation of the Wastewater Rising Main
  4. main contractorGMBMentioned in AWP 2.0: Always in operation
  5. the pumpsPentairMentioned in AWP 2.0: Always in operation
  6. E&PAHoppenbrouwersMentioned in AWP 2.0: Always in operation
  7. clientWaterschap Brabantse DeltaMentioned in AWP 2.0: Always in operation
  8. temporary pumping installationsVan der KampMentioned in AWP 2.0: Always in operation
  9. designRHDHVMentioned in AWP 2.0: Always in operation
  10. BIM coordinatorRoyal HaskoningDHVMentioned in A bird’s-eye view prevents surprises
  11. Pump controlHoppenbrouwers TechniekMentioned in A helicopter view prevents surprises
  12. temporary pumping installationsVan der Kamp PompenMentioned in Temporary pumping installations safeguard AWP continuity

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAWP 2.0
  • ThemeDigitalisation from design to construction
  • SubjectBouwMat
  • CompanyGMB
  • CompanyPentair Fairbanks Nijhuis
  • CompanyHoppenbrouwers Techniek
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.