BouwMat

A robust, sustainable system for the future

A robust, sustainable system for the future

The wastewater rising main (AWP) in West Brabant is now almost fifty years old, and the associated pumping stations have proved insufficiently reliable. Pumps are reaching the end of their service life and can no longer meet increased demand. Emergency pumping systems are now in permanent use. This prompted Waterschap Brabantse Delta to renovate and upgrade the wastewater rising main, so that its capacity and continuity can once again be guaranteed for the next fifty years. 

The AWP collects wastewater from households and businesses in 35 villages and towns in West Brabant. All this wastewater is treated in Bath and then returned to nature via the Westerschelde. “The pipeline network is 60 kilometres long and was originally built with a certain amount of spare capacity,” says Frank van Zijl of Waterschap Brabantse Delta. “In the past, when work was being carried out on the system, we could easily switch off one of the two pumps at the pumping stations in Roosendaal and Bergen op Zoom. That has not been possible for years. In recent years, an emergency pumping system has been in permanent use, and maintenance work on the system has become quite costly.”

Two contracts

To make the AWP robust enough for the future, the water authority invited tenders in 2017 for a major renovation and upgrade of the existing system. “We split the contract into two parts,” says Van Zijl. “An extensive survey in 2013 showed that the pipeline network is still in excellent condition. However, it needs to be expanded in some places to meet the higher capacity requirement. The work therefore also includes installing a second pipeline along a 3.5-kilometre section, to handle larger volumes of wastewater. This contract is being delivered by GW Leidingtechniek. The other contract covers the renovation and upgrade of the two pumping stations and the effluent pumping station at the wastewater treatment plant in Bath. This is a complex project known as AWP 2.0. In effect, everything connected by a wire is being replaced,” says Van Zijl.

Route overview

EMVI commitment

Five consortia came forward during the tender process for AWP 2.0. Van Zijl: “Two of them ultimately submitted a bid. We chose PAUW (GMB WK&I, Van der Kamp, Pentair Nijhuis, Hoppenbrouwers and RHDHV) because it offered the best quality, combining optimal risk management with price. PAUW assures us that continuity of the AWP will be guaranteed at all times. During the construction phase, a pump will always be on standby to take over seamlessly if problems arise and capacity is affected. This EMVI commitment was something we valued and was one of the factors that led to the winning bid. As a water authority, it is important for us to complete the construction project without risk and at the most economically attractive price possible. That means maintaining functionality ‘along the way’ and guaranteeing safe processes, both for a safe working environment for our colleagues and for subcontractors, in order to deliver a result that is easy to operate, manage and maintain.”

According to Van Zijl, the renovated and upgraded AWP will pump wastewater in the most sustainable way possible, making maximum use of gravity at the pumping stations. “The design incorporates many smart technologies. We are also making huge strides in process automation, with real-time insight into all installations and smart control software. To
further guarantee operational reliability, we have signed a fifteen-year maintenance contract with a performance guarantee, under which the pumps may be out of service for no more than 20 hours a year. This gives us the assurance of
a robust and reliable system for the future.” 

Een zakelijke vraag aan GW Leidingtechniek BV? Get in touch

Who worked on AWP 2.0

  1. construction of the second pipelineGW LeidingtechniekMentioned in Update on the renovation of the Wastewater Rising Main
  2. consultancyKragtenMentioned in Update on the renovation of the Wastewater Rising Main
  3. process automationCroon Wolter en DrosMentioned in Update on the renovation of the Wastewater Rising Main
  4. main contractorGMBMentioned in AWP 2.0: Always in operation
  5. the pumpsPentairMentioned in AWP 2.0: Always in operation
  6. E&PAHoppenbrouwersMentioned in AWP 2.0: Always in operation
  7. clientWaterschap Brabantse DeltaMentioned in AWP 2.0: Always in operation
  8. temporary pumping installationsVan der KampMentioned in AWP 2.0: Always in operation
  9. designRHDHVMentioned in AWP 2.0: Always in operation
  10. BIM coordinatorRoyal HaskoningDHVMentioned in A bird’s-eye view prevents surprises
  11. Pump controlHoppenbrouwers TechniekMentioned in A helicopter view prevents surprises
  12. temporary pumping installationsVan der Kamp PompenMentioned in Temporary pumping installations safeguard AWP continuity

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAWP 2.0
  • ThemeFlood protection and climate-resilient water management
  • SubjectBouwMat
  • CompanyGW Leidingtechniek BV
  • CompanyGMB
  • CompanyPentair Fairbanks Nijhuis
  • CompanyHoppenbrouwers Techniek