No surprises with new pump installations thanks to a ‘digital twin’

Reducing failure costs and preventing damage: isn’t that what every company wants? The pump industry is no exception, particularly when we consider the consequences of a pump failing to operate. GMB constructs and renovates, across several divisions, dykes, port areas, sewer systems, pumping stations, water treatment plants and sludge processing plants, among other things.
GMB’s Water Quality and Installations division has a state-of-the-art method for reducing the risk of failure in a new pump installation to an absolute minimum. Together with their partners, they create a ‘digital twin’ before the pump is commissioned and use it to simulate its operation. Marc Vogt, design manager at GMB, takes us through the process.
Dry testing for maximum risk control
“The best way to explain how the digital twin works is to use the AWP 2.0 project for Waterschap Brabantse Delta, which is currently under way,” Vogt begins. “We are currently renovating three pumping stations, replacing two old pumps with three new ones at each station. The first pump was recently commissioned, and we knew in advance that it would operate without any problems. Beforehand, together with our partners, we created a digital twin of the discharge station. This means the pump, pipework and instrumentation were recreated virtually so that they could operate in a digital simulation. We then used calculation software from our partner RHDHV to feed data into the simulation, including artificial rainfall events, data from local measurements, all kinds of system influences that affect operation and, last but not least, test data for the pump supplied by our partner Pentair. Our partner Hoppenbrouwers’ software links everything together, resulting in a virtual pump in operation, subject to influences that are certain to occur at some point in real life. A kind of digital baptism of fire…”
But the simulation does not stop there. Vogt explains: “This dry, virtual test also lets us simulate all kinds of operating scenarios. You can’t get greater certainty in advance. The great thing is that you can fine-tune and adjust things in the simulation, then transfer them directly to the real installation if the results prove successful. That inspires confidence.”

An overview of the three pump lines.
Huge time savings
As well as providing certainty about the technology, the digital twin also saves a great deal of time. “It makes sense, really. Without digital testing, we would depend on peaks occurring in real life. We would have to wait for severe weather and hope the installation could withstand it. Besides the time this takes, there is a real risk of damage. ‘Trial and error’ is not desirable with pump installations of this size. Not only because of the costs of possible damage to the installation, but above all because of the impact on the surrounding area if a pumping station like this fails. Once again, it proves how fortunate we are to have the option of virtual testing. The computer is patient. Running a 24-hour virtual test is no problem, as we simulate in real time.”
The first time leaves us wanting more
This is the first time GMB has worked this way. “That was possible because this particular project is ideally suited to it,” Vogt explains. “These pumps are large and powerful. And the discharge must be guaranteed throughout the construction work. In the virtual environment, we can push things right to the limit… The forces involved are so great that doing this in real-world conditions could cause enormous damage. That would cost time and money and, in effect, destroy capital. Now we can test while keeping the operation running, as the saying goes. The old pumps are still running, the new pump can be brought into reliable operation, and it is simply a matter of replacing them without unnecessary disruption.”
Taking a predictive approach
Vogt concludes: “There is more and more you can do with it. The pump that has now been commissioned is also being monitored. We link that data to the initial test results, and everything is matching so far. That gives us a way to validate the results. By analysing the data, we will even be able to make predictions in future. That is where things are heading, and it will be ideal for further optimising systems, for example.”
Een zakelijke vraag aan Pentair Fairbanks Nijhuis? Get in touch
Who worked on AWP 2.0
- construction of the second pipeline
GW LeidingtechniekMentioned in Update on the renovation of the Wastewater Rising Main - process automationCroon Wolter en DrosMentioned in Update on the renovation of the Wastewater Rising Main
- temporary pumping installationsVan der Kamp PompenMentioned in Temporary pumping installations safeguard AWP continuity
Keep following this
Get an email when a new story is published. No account needed.
- ProjectAWP 2.0
- ThemeDigitalisation from design to construction
- SubjectBouwMat