A great challenge on the Afsluitdijk: pouring concrete on a 10% slope
Text Suzanne van Gaale Beeld Disa/Levvel/Rijkswaterstaat

As a specialist in underwater civil engineering, the team at DISA International works below the waterline on the construction, maintenance and repair of major civil engineering infrastructure projects. They are also involved in strengthening and renovating the Afsluitdijk. “A wonderful project that brings together every aspect of our work.”
DISA likes to get involved as early as the design stage of a project. “Because,” says site manager Marc Veldhuizen, “we like to contribute to preparations by helping find solutions for work underwater. We are increasingly finding that many companies lack the knowledge and experience in this specialist field. Underwater civil engineering is our specialism, so we are brought in to help develop solutions. We have worked on the Maasdeltatunnel and the Hollandtunnel, De Groene Boog and OPENIJ, among other projects. On all our projects, including the strengthening and renovation of the Afsluitdijk, our clients value our innovative, safe and reliable approach. This year, we have also achieved level 4 on the Safety Culture Ladder.”

Underwater solutions
One of the solutions proposed by DISA was how to pour underwater concrete on a 10% slope. Senior site manager Cecil de Groot explains: “There is a 10% slope in two cofferdams on the Wadden Sea side of the pumping station at Den Oever. A slope like that is quite unusual. You can imagine that if you pour concrete here, it will quickly flow away. We solved this by installing reinforcement cages fitted with stop-end steel. Mesh was placed on these cages to maintain the slope of the concrete and prevent it from slipping. We also made the concrete mix slightly stiffer. We prepared all the reinforcement drawings for construction consortium Levvel (BAM, Van Oord, Rebel and Invesis), which is carrying out the work on the Afsluitdijk on behalf of Rijkswaterstaat, and also handled the installation and execution. We also fitted the sheet-pile wall with a special sealing joint to accommodate any movement in the wall. We worked all this out in advance with Levvel.” In addition to pouring underwater concrete, DISA’s diving teams carried out work including cutting off sheet piles, welding and various underwater construction tasks in preparation for the concrete pour. On average, four diving teams are at work, carrying out the various activities.

Depth sensor
Underwater measurements are accurate to the nearest centimetre thanks to depth sensors. In the past, someone on the surface would walk alongside the diver with a weighted steel line. Now, depth sensors do the job. Marc explains: “All our diving teams are equipped with one of these sensors. As well as measuring depth, it can check whether an object is level. The sensor works quickly and efficiently. We use it for everything that needs to be measured. What might once have taken two days can now be done in a few hours. We are one of the few companies to use this technology.”
Weekly meetings
To ensure everything runs smoothly and according to plan, meetings are held on site every week. “The collaboration is very good. Discussing things on site every week helps us keep our finger on the pulse and quickly adjust course when needed.”
Have a business enquiry for DISA International? Get in touch
Who worked on Afsluitdijk
- clientRijkswaterstaatMentioned in Greater discharge capacity through specialist, bespoke pump design
- central control
Croonwolter&drosMentioned in Afsluitdijk system integration: invisible and indispensable - supplierSaferoadMentioned in “Alternative systems are permitted, provided they comply with the rules”
- underwater construction
DISA InternationalMentioned in ‘Placing underwater concrete is all about good planning’ - underwater excavation
BonneveldMentioned in A sheet pile structure with anchoring has been installed at the Lely monument, halfway along the dyke. - technical integrator
Batenburg Industrial AutomationMentioned in A complex IT puzzle on the Afsluitdijk - contractorBoskalisMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
- Levvel construction consortiumInvesisMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
- contractors' joint ventureIJsselmeerwerken VOFMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
- clientProvince of FrieslandMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
- fire alarm and evacuation systems
Unica Fire SafetyMentioned in Optimal fire safety for the Afsluitdijk - Levvel construction consortiumAberdeenMentioned in Afsluitdijk reinforcement complete: pumping station and new sluices officially opened
Keep following this
Get an email when a new story is published. No account needed.
- ProjectAfsluitdijk
- ThemeMaterials and techniques for infrastructure
- SubjectWater infrastructure
- CompanyDISA International
- CompanyVeldhuizen b.v.
- CompanyVan Oord


















