‘Placing underwater concrete is all about good planning’

As a specialist in civil underwater construction, the people at DISA International dive beneath the water to build, maintain and repair major civil infrastructure projects. They have already done so on projects such as the Maasdelta and Hollandtunnel, De Groene Boog and OPENIJ, and are now working on the Afsluitdijk too. The company is known as the world’s underwater specialist.
1,675 m3 of underwater concrete

“If you calculate the amount of underwater concrete we place over a period of about 5 years, it works out at an average of 100,000 cubic metres a year,” says Cecil de Groot, Afsluitdijk site manager at DISA. “That is a huge amount, and few companies can match it. We do this for structures including tunnels, car parks and locks. A single pour can sometimes involve as much as 10,000 cubic metres, the equivalent of around a thousand lorry loads. For the Afsluitdijk project, 1,675 m3 of underwater concrete was placed in the deepest cofferdam at Den Oever, a cofferdam about 20 metres deep. We also placed underwater concrete at the existing sluices on the Wadden Sea side, a total of 2,000 m3. Placing underwater concrete is always a matter of good planning. The pour has to continue without interruption, you cannot stop halfway through. On all our projects, including the Afsluitdijk renewal, our clients value our innovative, safe and reliable approach.”
Divers lend a hand
DISA began underwater work on the existing discharge structures at Den Oever in 2018. This immediately presented a welcome challenge when it came to placing underwater concrete. “Space was so limited that there was virtually nowhere to position the concrete pump. In the end, we placed a 63-metre pump with a boom on the closed carriageway, extending over the carriageway that remained open to traffic. Additional pipelines carried the concrete to a second concrete pump on a pontoon.”
This year, DISA faced another welcome challenge, once again at Den Oever. Two cofferdams on the Wadden Sea side have a slope of 10 per cent. Concrete will not stay in place on a slope like that. “We solved the problem by installing reinforcement cages to keep the concrete slope in place. We also made the concrete mix slightly stiffer. Divers had to lend a hand in a number of the cofferdams. During excavation, there were many places the excavator could not reach. Divers then use low-pressure water jets and a pump to suction out the material.”
Have a business enquiry for DISA International? Get in touch
Who worked on Afsluitdijk
- clientRijkswaterstaatMentioned in Greater discharge capacity through specialist, bespoke pump design
- central control
Croonwolter&drosMentioned in Afsluitdijk system integration: invisible and indispensable - supplierSaferoadMentioned in “Alternative systems are permitted, provided they comply with the rules”
- underwater excavation
BonneveldMentioned in A sheet pile structure with anchoring has been installed at the Lely monument, halfway along the dyke. - technical integrator
Batenburg Industrial AutomationMentioned in A complex IT puzzle on the Afsluitdijk - contractorBoskalisMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
- Levvel construction consortiumInvesisMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
- contractors' joint ventureIJsselmeerwerken VOFMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
- clientProvince of FrieslandMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
- fire alarm and evacuation systems
Unica Fire SafetyMentioned in Optimal fire safety for the Afsluitdijk - Levvel construction consortiumAberdeenMentioned in Afsluitdijk reinforcement complete: pumping station and new sluices officially opened
Keep following this
Get an email when a new story is published. No account needed.
- ProjectAfsluitdijk
- SubjectNews
- CompanyDISA International