‘Placing underwater concrete is all about good planning’

Project manager Cecil de Groot.
Project manager Cecil de Groot.

As a specialist in civil underwater construction, the people at DISA International dive beneath the water to build, maintain and repair major civil infrastructure projects. They have already done so on projects such as the Maasdelta and Hollandtunnel, De Groene Boog and OPENIJ, and are now working on the Afsluitdijk too. The company is known as the world’s underwater specialist.

1,675 m3 of underwater concrete

DISA began underwater work on the existing discharge structures at Den Oever in 2018.

“If you calculate the amount of underwater concrete we place over a period of about 5 years, it works out at an average of 100,000 cubic metres a year,” says Cecil de Groot, Afsluitdijk site manager at DISA. “That is a huge amount, and few companies can match it. We do this for structures including tunnels, car parks and locks. A single pour can sometimes involve as much as 10,000 cubic metres, the equivalent of around a thousand lorry loads. For the Afsluitdijk project, 1,675 m3 of underwater concrete was placed in the deepest cofferdam at Den Oever, a cofferdam about 20 metres deep. We also placed underwater concrete at the existing sluices on the Wadden Sea side, a total of 2,000 m3. Placing underwater concrete is always a matter of good planning. The pour has to continue without interruption, you cannot stop halfway through. On all our projects, including the Afsluitdijk renewal, our clients value our innovative, safe and reliable approach.”

Divers lend a hand

DISA began underwater work on the existing discharge structures at Den Oever in 2018. This immediately presented a welcome challenge when it came to placing underwater concrete. “Space was so limited that there was virtually nowhere to position the concrete pump. In the end, we placed a 63-metre pump with a boom on the closed carriageway, extending over the carriageway that remained open to traffic. Additional pipelines carried the concrete to a second concrete pump on a pontoon.”

This year, DISA faced another welcome challenge, once again at Den Oever. Two cofferdams on the Wadden Sea side have a slope of 10 per cent. Concrete will not stay in place on a slope like that. “We solved the problem by installing reinforcement cages to keep the concrete slope in place. We also made the concrete mix slightly stiffer. Divers had to lend a hand in a number of the cofferdams. During excavation, there were many places the excavator could not reach. Divers then use low-pressure water jets and a pump to suction out the material.” 

Have a business enquiry for DISA International? Get in touch

Who worked on Afsluitdijk

  1. Levvel construction consortiumVan OordMentioned in Afsluitdijk reinforcement gets under way
  2. Levvel construction consortiumBAMMentioned in Afsluitdijk reinforcement gets under way
  3. Levvel construction consortiumRebelMentioned in Afsluitdijk reinforcement gets under way
  4. maintenanceLevvel BVMentioned in Afsluitdijk reinforcement gets under way
  5. six pumpsFlowserveMentioned in Greater discharge capacity through specialist, bespoke pump design
  6. clientRijkswaterstaatMentioned in Greater discharge capacity through specialist, bespoke pump design
  7. central controlCroonwolter&drosMentioned in Afsluitdijk system integration: invisible and indispensable
  8. hydraulicsHycomMentioned in E-engineering: power and data for the renovated Afsluitdijk
  9. supplierSaferoadMentioned in “Alternative systems are permitted, provided they comply with the rules”
  10. sealsTrelleborg RidderkerkMentioned in Trelleborg Ridderkerk designs and manufactures seals for the Afsluitdijk
  11. underwater constructionDISA InternationalIn this story
  12. electrical controlsELMAMentioned in Hydraulic systems must perform at 100% at all times
  13. Basalton QuattroblocksHolcim CoastalMentioned in The most stable revetment of its kind
  14. technical integratorBatenburg Industrial AutomationMentioned in A complex IT puzzle on the Afsluitdijk
  15. Levvel construction consortiumInvesisMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
  16. contractors' joint ventureIJsselmeerwerken VOFMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
  17. clientProvince of FrieslandMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
  18. fire alarm and evacuation systemsUnica Fire SafetyMentioned in Optimal fire safety for the Afsluitdijk
  19. Levvel construction consortiumAberdeenMentioned in Afsluitdijk reinforcement complete: pumping station and new sluices officially opened

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAfsluitdijk
  • SubjectNews
  • CompanyDISA International
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.