Water infrastructure

A sheet pile structure with anchoring has been installed at the Lely monument, halfway along the dyke.

Er moest secuur gewerkt wordt tussen de funderingspalen.
Er moest secuur gewerkt wordt tussen de funderingspalen.

Excavating sheet pile cofferdams is quite a job

Underwater excavation is a specialised skill, and one the team at Bonneveld knows well. At the Afsluitdijk near Kornwerderzand, they excavated a total of three sheet pile cofferdams, as well as the passage for the Vismigratierivier, on behalf of construction consortium Levvel. “In total, we excavated and suctioned away 26,000 m3 of clay and sand underwater,” says project manager Stefan Albers.

The Afsluitdijk is a fantastic Rijkswaterstaat project to work on, says Albers. “This is where our experience and expertise in wet excavation really come into their own. For the underwater work at Kornwerderzand, we delivered the complete package: excavating the wet cofferdams, carrying out the diving work and placing underwater concrete. One advantage is that we have all the equipment and resources needed for underwater excavation. This includes polymer plants, pontoons, silt skips, clamshell buckets and specially developed pumping systems for excavating cofferdams.”

After the sheet pile cofferdams had been pumped dry, the entire area was cleaned and handed over to Levvel in a clean condition.

At great depth

The three sheet pile cofferdams at the Kornwerderzand storm surge barrier naturally presented a number of challenges. The deepest sheet pile wall extends down 16 metres. The largest cofferdam will house the enormous rolling gate, weighing 950,000 kilograms, 56 metres wide and 15 metres high. It will be slid shut when water levels are very high. “We had to work very precisely here because we had to excavate between the foundation piles, which meant space was limited. The sheet pile walls were also coated and could not be damaged under any circumstances. That is why, among other things, we used GPS for the excavation.” Another major challenge was that the sheet pile walls had been installed at a higher level to account for possible extreme water levels. “We excavated to a depth of 16 metres below the top of the sheet pile wall. In total, we excavated more than 8,000 m3 of soil and suctioned away 6,000 m3 of sand. We were also working on a protected waterbed, which naturally called for the necessary precautions.” In addition to the excavation, Bonneveld cleaned the sheet pile walls underwater, laid a gravel layer, installed pressure relief wells and placed underwater concrete. After the sheet pile cofferdams had been pumped dry, the entire area was cleaned and handed over to Levvel in a clean condition. 

Sustainable reuse of sand

Bonneveld was also responsible for excavating one of the sheet pile cofferdams for the Vismigratierivier, including the diving work, placing underwater concrete and cleaning the cofferdam. Albers says: “During the work, road traffic continued to pass over one part of the cofferdam. That too required meticulous working. The sand and clay excavated here were sustainably reused elsewhere on the project. In total, we excavated 9,000 m3 and suctioned away 3,000 m3.”

Tight timeframe

Albers looks back with pride on Bonneveld’s contribution. “Thanks to good cooperation with all the parties involved, and with the flexibility and creativity required, we completed everything within the set timeframe.”     

A business enquiry for Bonneveld BV? Get in touch

Who worked on Afsluitdijk

  1. Levvel construction consortiumVan OordMentioned in Afsluitdijk reinforcement gets under way
  2. Levvel construction consortiumBAMMentioned in Afsluitdijk reinforcement gets under way
  3. Levvel construction consortiumRebelMentioned in Afsluitdijk reinforcement gets under way
  4. maintenanceLevvel BVMentioned in Afsluitdijk reinforcement gets under way
  5. six pumpsFlowserveMentioned in Greater discharge capacity through specialist, bespoke pump design
  6. clientRijkswaterstaatMentioned in Greater discharge capacity through specialist, bespoke pump design
  7. central controlCroonwolter&drosMentioned in Afsluitdijk system integration: invisible and indispensable
  8. hydraulicsHycomMentioned in E-engineering: power and data for the renovated Afsluitdijk
  9. supplierSaferoadMentioned in “Alternative systems are permitted, provided they comply with the rules”
  10. sealsTrelleborg RidderkerkMentioned in Trelleborg Ridderkerk designs and manufactures seals for the Afsluitdijk
  11. underwater constructionDISA InternationalMentioned in ‘Placing underwater concrete is all about good planning’
  12. electrical controlsELMAMentioned in Hydraulic systems must perform at 100% at all times
  13. Basalton QuattroblocksHolcim CoastalMentioned in The most stable revetment of its kind
  14. underwater excavationBonneveldIn this story
  15. technical integratorBatenburg Industrial AutomationMentioned in A complex IT puzzle on the Afsluitdijk
  16. Levvel construction consortiumInvesisMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
  17. contractors' joint ventureIJsselmeerwerken VOFMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
  18. clientProvince of FrieslandMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
  19. fire alarm and evacuation systemsUnica Fire SafetyMentioned in Optimal fire safety for the Afsluitdijk
  20. Levvel construction consortiumAberdeenMentioned in Afsluitdijk reinforcement complete: pumping station and new sluices officially opened

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAfsluitdijk
  • ThemeUnderground construction
  • SubjectWater infrastructure
  • CompanyBonneveld BV
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.