Let it flow when you can, pump when you must!

Let it flow when you can, pump when you must!

The Afsluitdijk renovation puts water discharge centre stage alongside flood protection. Construction consortium Levvel (BAM,…

Alongside flood protection, water discharge is a key focus of the Afsluitdijk renovation. Construction consortium Levvel (BAM, Van Oord and Rebel) has included additional sluice gates in its plans for Den Oever, as well as two pumping stations with six pumps in total. These are essential to making the Afsluitdijk fit for the future, as Piet Zuidgeest, New Discharge Facility Project Manager at Levvel, explains.

We talk to Zuidgeest about his area of work: increasing the capacity to discharge water from the IJsselmeer into the Wadden Sea. “Rijkswaterstaat’s brief was clear: the Afsluitdijk needed greater discharge capacity and had to be energy-neutral. A minimum pumping capacity was specified. Levvel stood out in the tender by also offering additional groups of sluices to provide the required discharge capacity. This concept significantly reduces energy consumption,” Zuidgeest begins.

Construction consortium Levvel (BAM, Van Oord and Rebel) has included additional sluice gates in its plans for Den Oever, as well as two pumping stations with six pumps in total.

Construction is now under way

“We have now started work on the northern cofferdams, based on the principal dimensions of the pump structures. At the same time, all the components of the pumping installations are still being worked up in detail,” says Zuidgeest. Asked to describe the situation before the works, he replies: “On the Den Oever side, there are currently three groups of sluices, each with five discharge culverts. When the water level on the Wadden Sea side is lower than on the IJsselmeer side, the gates are opened so water can discharge by gravity, making use of the tidal window. This is a major concern under the current conditions. The time available for discharge is getting shorter because climate change is gradually raising the average water level on the Wadden Sea side. That is the first constraint. The second is that climate change is causing more peak flows into the IJsselmeer. We can anticipate that sluicing alone will no longer be enough, even with the additional sluice capacity we are building. That is why the pumps are important too.”

Piet Zuidgeest, New Discharge Facility Project Manager at Levvel.

Sluice gates and pumping stations working in tandem

To meet changing conditions, Levvel has planned two new groups of sluices at Den Oever, on the intermediate islands between the existing groups. “Each new group has four discharge culverts, giving us eight in total. This represents a 75% increase in sluice area at Den Oever compared with the current situation. The Afsluitdijk’s overall sluice system also includes the capacity of the existing groups at Kornwerderzand, two groups of five discharge culverts each. The two pumping stations we are building, with six pumps in total, can together provide the specified discharge rate of 235 cubic metres of water per second. The pumps will only be used when needed, hence ‘let it flow when you can, pump when you must’. This approach actively helps reduce energy consumption. The pumps themselves have also been selected for their energy efficiency.”

Levvel has chosen a vertically suctioning pump, with discharge at a 90˚ angle. Zuidgeest explains: “We chose this pump to achieve the shortest possible pump channel. It has the smallest installation dimensions we could accommodate. A useful feature is that, thanks to their size and the position of the impellers, the pumps are ‘fish-friendly’ and therefore will not affect fish stocks.” In addition to saving energy through the choice of pump and using the pumps only when needed, solar panels will help make the Afsluitdijk energy-neutral. A solar farm covering 3 hectares will be built on the site of Levvel’s current temporary office in Den Oever. Solar power will offset the energy used by both the pumps and the other infrastructure.

“We have now started work on the northern cofferdams, based on the principal dimensions of the pump structures.” (Image: Pieter Klein)

A stand-alone project

“The new sluice gates and pumping stations can be seen as a stand-alone sub-project within the Afsluitdijk renovation works. However, the schedule is linked to other activities, such as closing one lane of the A7 and refurbishing the decks of the existing sluice groups, among other works, in the same phases,” Zuidgeest concludes.    

Have a business enquiry for Van Oord? Get in touch

Who worked on Afsluitdijk

  1. Levvel construction consortiumVan OordMentioned in Afsluitdijk reinforcement gets under way
  2. Levvel construction consortiumBAMMentioned in Afsluitdijk reinforcement gets under way
  3. Levvel construction consortiumRebelMentioned in Afsluitdijk reinforcement gets under way
  4. maintenanceLevvel BVMentioned in Afsluitdijk reinforcement gets under way
  5. six pumpsFlowserveMentioned in Greater discharge capacity through specialist, bespoke pump design
  6. clientRijkswaterstaatMentioned in Greater discharge capacity through specialist, bespoke pump design
  7. central controlCroonwolter&drosMentioned in Afsluitdijk system integration: invisible and indispensable
  8. hydraulicsHycomMentioned in E-engineering: power and data for the renovated Afsluitdijk
  9. supplierSaferoadMentioned in “Alternative systems are permitted, provided they comply with the rules”
  10. sealsTrelleborg RidderkerkMentioned in Trelleborg Ridderkerk designs and manufactures seals for the Afsluitdijk
  11. underwater constructionDISA InternationalMentioned in ‘Placing underwater concrete is all about good planning’
  12. electrical controlsELMAMentioned in Hydraulic systems must perform at 100% at all times
  13. Basalton QuattroblocksHolcim CoastalMentioned in The most stable revetment of its kind
  14. technical integratorBatenburg Industrial AutomationMentioned in A complex IT puzzle on the Afsluitdijk
  15. Levvel construction consortiumInvesisMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
  16. contractors' joint ventureIJsselmeerwerken VOFMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
  17. clientProvince of FrieslandMentioned in ‘You can’t see from the outside how much work is being done on the Afsluitdijk’
  18. brandmeld- en ontruimingsinstallatiesUnica Fire SafetyMentioned in Optimal fire safety for the Afsluitdijk
  19. Levvel construction consortiumAberdeenMentioned in Afsluitdijk reinforcement complete: pumping station and new sluices officially opened

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAfsluitdijk
  • ThemeFlood protection and climate-resilient water management
  • SubjectWater infrastructure
  • CompanyVan Oord
Share this article

Advertisement

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.