Risk management and environmental monitoring are essential to strengthening the Markermeerdijken. The aim is to deliver a safe dike, work practically and make damage prevention a top priority. AMMD’s Integrated Monitoring Team (IMT) is responsible for planning and supports, among others, the environmental managers, site engineers and construction teams.

Dike reinforcement, the surrounding area and active monitoring

It is important that the built environment remains stable throughout the work. Should damage occur despite all precautions, it must be possible to establish what has happened quickly. Imre van Hal, adviser at Aveco de Bondt, says: “The tension lies in deciding what is best for the project and what is best for the surrounding area. This is a healthy tension. The only way to manage it is through active environmental monitoring and good plans. The aim is not to tick boxes and put a report away in a desk drawer, but to monitor the surroundings and take preventive action.”

Plaxis pore water pressure calculations, Alliantie Markermeerdijken.

Preparatory work and construction

There is always a risk of damage caused by raising ground levels, excavation and vibration. The challenging subsoil is at the heart of the issue. How can you carry out the work while managing these risks? Rick Oosterhoff, senior adviser at Aveco de Bondt, says: “The IMT has drawn up policy and integrated plans that clearly set out the ‘ground rules’ for damage prevention. What makes this major project unique is that the impact on the surrounding area is assessed in detail at any locations where risks may arise.” Imre adds: “The complexity of the project requires geotechnical engineers and other experts to switch between detailed analysis and an overview of the project as a whole. We assess the risks to the surrounding area in advance using the latest models and technical insights. We also carry out fieldwork and make ‘old-fashioned’ visits to archives to find foundation data. Clear plans and agreements are in place beforehand. These set carefully considered threshold values for each phase, linked to approval points before the next phases can proceed. By working in stages and taking measurements at the right times, you can respond immediately and reduce the risk of damage. Close communication with site engineers, construction teams and environmental managers is also essential to ensure the right control measures can be taken.”

Environmental monitoring and damage prevention take centre stage

The project involves risks that make a wide range of measurements necessary. In addition to the usual pre-construction building surveys and benchmarks for measuring levels, various instruments are being used, including prisms and inclinometer tubes to measure horizontal displacement, phenomarkers to monitor ground settlement, crack gauges, vibration monitors and piezometers. These are installed at numerous locations along the 33-kilometre route. Imre says: “What stood out was that the planning and follow-up of environmental monitoring made us realise that damage prevention was becoming part of the organisation’s culture and rightly taking centre stage. People across all levels of the organisation are working together and making adjustments to prevent damage during construction.”

Geoweb environment, Alliantie Markermeerdijken.

What has it achieved?

Environmental monitoring backed by clear action plans has enabled Alliantie Markermeerdijken to manage the risks. Naturally, local residents who experience vibration and disruption may see things differently. The IMT gives environmental managers the knowledge to explain the difference between perceived nuisance and actual damage. So far, the tension has been managed successfully at the Markermeerdijken. Environmental monitoring, combined with an action plan, provides clarity and reassurance for both local residents and the alliance as a whole.     

Question about this story? Ask your question

Who worked on Markermeerdijken

  1. led consortiumBoskalis NederlandMentioned in Broad foundation expertise for the Markermeerdijken project
  2. All-round foundation specialistGebr. van ’t HekMentioned in Broad foundation expertise for the Markermeerdijken project
  3. welding and fabricationLinden StaalbouwMentioned in Broad foundation expertise for the Markermeerdijken project
  4. engineering consultancyHektecMentioned in Broad foundation expertise for the Markermeerdijken project
  5. clientHoogheemraadschap Hollands NoorderkwartierMentioned in A complex technical challenge calls for a unique partnership
  6. Brushwood mattressesVan AalsburgMentioned in Protecting soil and banks in a natural way
  7. maritime service providerK&W TransMentioned in On the front line of dike reinforcement
  8. clientAlliantie MarkermeerdijkenMentioned in Monitoring transport by water
  9. Integrated monitoring team (IMT)AMMDIn this story
  10. adviserAveco de BondtIn this story
  11. clientAllianceMentioned in Responding to changing circumstances throughout
  12. environmental consultancyATKBMentioned in Responding to changing circumstances throughout
  13. earthmoving machinery with operatorHuiberts BVMentioned in Cumela contractor at the heart of the dike reinforcement project
  14. contractorDe Vries & van de WielMentioned in Hopper suction dredger TEXEL unloads more than 3.5 million m3 of sand
  15. traffic management measuresBUKO InfrasupportMentioned in Working together towards a safe future
  16. leading hydraulic engineering contractorBoskalisMentioned in Experienced dike builders
  17. maritime service providerKapitein MaritiemMentioned in Specialist fleet for shallow waters
  18. fencingQ-FenceMentioned in Special settlement gauges and fencing
  19. settlement markers and other temporary worksWelding and assembly work (LMW)Mentioned in Special settlement gauges and fencing
  20. sealing panelsSamson AppendagesMentioned in ‘Specials’ for water engineering
  21. reinforcement supplierSpanberg WapeningMentioned in Integrated design and installation of reinforcing steel
  22. integrated designStaalis EngineeringMentioned in Integrated design and installation of reinforcing steel
  23. framework contractorABC Hekwerk Noord-WestMentioned in High-quality perimeter fencing
  24. Site engineering teamBT GeoconsultMentioned in Safely raising the Markermeerdijken

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectMarkermeerdijken
  • ThemeFlood protection and climate-resilient water management
  • SubjectWater infrastructure
  • CompanyAMMD
  • CompanyAveco de Bondt
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.