Water infrastructure

Integrated design and installation of reinforcing steel

Foundation for combined culvert structure 03.
Foundation for combined culvert structure 03.

The reinforcement of the Markermeerdijken involves the construction of six civil engineering structures, including inlet and outlet chambers, suspended culverts and capping beams. On behalf of the Alliantie, Spanberg Wapening and Staalis Engineering are responsible for the integrated design of the reinforcing steel for the structures. The latter is a joint venture between engineering consultancy Clafis and reinforcement supplier Spanberg. According to Dennis Knaap, director of Spanberg and Staalis, this brings significant benefits during construction, particularly on a project such as this.

Staalis produced a complete 3D drawing of the reinforcement for the structures on the Markermeerdijken.

“Staalis aims to optimise the process from design through to installation of concrete reinforcement by designing it as an integrated whole and modelling it pragmatically,” says Knaap. “We factor in the most practical construction method at the design stage, often opting for prefabricated components to limit production time on site. Our clients particularly value our input at an early stage. Staalis’s modellers are based at our reinforcement and bending centre in Uitgeest, which means feedback from the factory can be dealt with quickly.”

Outlet chamber, structure 01.

160 tonnes of reinforcement

Staalis produced a complete 3D drawing of the reinforcement for the structures on the Markermeerdijken. “The work comprises two inlet and outlet chambers, two suspended culverts and various capping beams on a sheet pile wall,” says Stijn Springer, project manager at Staalis. “At 160 tonnes of reinforcement, it is not a particularly large project for us in terms of quantity, but it is the details that make it a little different. The unusual shapes and angles make the reinforcement design somewhat more complex. We also have to allow for the tolerances of components, such as sheet piles, that have to be driven into the ground. Our task is to design the reinforcement so that it can be adjusted relatively easily on site. The 2D reinforcement drawings for the site teams are then generated from the 3D model.” Knaap adds that the reinforcement drawings are similar to the instructions for an Ikea product: “They explain step by step to the site teams how the reinforcement should be installed.”

According to Knaap, the first discussions about the project took place as early as 2018. “We began the drawing work in 2019 and installed the reinforcement for the first structure in 2020, around 30 tonnes of reinforcing steel for the Westerkogge structure. We will remain involved in the project until the end of 2022, albeit in phases, following the Alliantie’s schedule. As mentioned, it is not a particularly complex project for us, but if you do not approach it in a practical and integrated way, it is the kind of project that can easily catch you out.”   

Question about this story? Ask your question

Who worked on Markermeerdijken

  1. led consortiumBoskalis NederlandMentioned in Broad foundation expertise for the Markermeerdijken project
  2. All-round foundation specialistGebr. van ’t HekMentioned in Broad foundation expertise for the Markermeerdijken project
  3. welding and fabricationLinden StaalbouwMentioned in Broad foundation expertise for the Markermeerdijken project
  4. engineering consultancyHektecMentioned in Broad foundation expertise for the Markermeerdijken project
  5. clientHoogheemraadschap Hollands NoorderkwartierMentioned in A complex technical challenge calls for a unique partnership
  6. Brushwood mattressesVan AalsburgMentioned in Protecting soil and banks in a natural way
  7. maritime service providerK&W TransMentioned in On the front line of dike reinforcement
  8. clientAlliantie MarkermeerdijkenMentioned in Monitoring transport by water
  9. Integrated monitoring team (IMT)AMMDMentioned in Managing the risk of damage at the Markermeerdijken
  10. adviserAveco de BondtMentioned in Managing the risk of damage at the Markermeerdijken
  11. clientAllianceMentioned in Responding to changing circumstances throughout
  12. environmental consultancyATKBMentioned in Responding to changing circumstances throughout
  13. earthmoving machinery with operatorHuiberts BVMentioned in Cumela contractor at the heart of the dike reinforcement project
  14. contractorDe Vries & van de WielMentioned in Hopper suction dredger TEXEL unloads more than 3.5 million m3 of sand
  15. traffic management measuresBUKO InfrasupportMentioned in Working together towards a safe future
  16. leading hydraulic engineering contractorBoskalisMentioned in Experienced dike builders
  17. maritime service providerKapitein MaritiemMentioned in Specialist fleet for shallow waters
  18. fencingQ-FenceMentioned in Special settlement gauges and fencing
  19. settlement markers and other temporary worksWelding and assembly work (LMW)Mentioned in Special settlement gauges and fencing
  20. sealing panelsSamson AppendagesMentioned in ‘Specials’ for water engineering
  21. reinforcement supplierSpanberg WapeningIn this story
  22. integrated designStaalis EngineeringIn this story
  23. framework contractorABC Hekwerk Noord-WestMentioned in High-quality perimeter fencing
  24. Site engineering teamBT GeoconsultMentioned in Safely raising the Markermeerdijken

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectMarkermeerdijken
  • ThemeMaterials and techniques for infrastructure
  • SubjectWater infrastructure
  • CompanySpanberg Wapening
  • CompanyStaalis Engineering
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.