Local knowledge crucial to dike reinforcement project

KWS, a VolkerWessels company, is best known in the Netherlands as a market leader in road construction and an asphalt producer. The company now generates a substantial share of its revenue from dike reinforcement projects. On the Markermeerdijken project, KWS’s local knowledge is proving invaluable, thanks to its decentralised organisational structure and regional offices. An interview with Pieter Kaars, Integrated Delivery Manager representing KWS in the Alliantie Markermeerdijken.
“Back in 2015, we submitted a tender for the Markermeerdijken dike reinforcement project together with Boskalis and fellow VolkerWessels company Van Hattum en Blankevoort,” Kaars begins. “Our consortium submitted the winning bid. A unique partnership was then established to tackle this complex project effectively. Hoogheemraadschap Hollands Noorderkwartier is not only the Alliantie’s client, but also works closely with us as a public-sector partner within the Alliantie.”

KWS has built up considerable experience in dike reinforcement projects. “Together with Boskalis, we previously completed the dike reinforcement on Texel for HHNK, as well as the Ommelanderdiek for Waterschap Noorderzijlvest, reinforcing the almost 12-kilometre-long sea dike between Eemshaven and Delfzijl. We are also currently involved in several design and construction teams. For example, we are working with Waterschap Scheldestromen to reinforce 5.2 kilometres of dike near Hansweert in Zeeland, and with Waterschap Vallei en Veluwe to reinforce the Noordelijke Randmeerdijk.”

Local knowledge
KWS is increasingly focusing on dike reinforcement projects. Kaars: “We are involved in a growing number of HWBP projects nationwide, and through our subsidiaries HollandScherm and Aquavia we have strong capabilities in delivering and maintaining both large and small-scale water infrastructure. This includes repairing, renovating and replacing locks, fender structures, bridges and quays.
So we are no longer just a road builder, but we do benefit from our decentralised organisational structure, with regional offices across the country. Most of the work on the Markermeerdijken is being handled by our Amsterdam-Utrecht office. This is paying dividends in both design and construction, because we approach the project with people who know the area and often come from the region. From the project manager to the excavator operator out on site. That is a definite advantage on this project, given the poor ground conditions. Building on peat requires a fundamentally different approach from building on sandy soil. We can also draw on the network of VolkerWessels companies for a range of specialist expertise, and of course we rely on our own engineering consultancies, KWS@vice and Aveco de Bondt, which have extensive expertise in water engineering projects.”
A logistical puzzle
The project presents a host of challenges. “Aside from the design challenges, on site it is above all a major logistical puzzle,” says Kaars. “To minimise the impact on the surrounding area, with its small villages, dike roads and polder roads, we have chosen to carry out most of the work from the water. A number of navigation channels and unloading areas have been set up along the entire route. They are effectively the project’s arteries, enabling us to handle the huge volumes of materials and transfer equipment.” To give an idea of the scale: a total of 8,000,000 m3 of sand will be delivered, along with 300,000 tonnes of rock armour, almost 1,000,000 m³ of clay, 170,000 m2 of concrete columns and 115,000 m2 of permanent surfacing, excluding opportunities to combine works. “Thanks to our good contacts in the industry, Boskalis and we are well placed to handle these huge volumes. As well as the floating plant required for this type of work, now that we are above water, our own conventional earthmoving equipment is proving useful. We work with great care. Fill layers are placed very evenly and are often monitored in real time using pore pressure sensors, inclinometer tubes and settlement plates.”

Digitalisation
“At KWS, we are used to organising and managing major infrastructure projects in an integrated way,” Kaars concludes. “We demonstrated this on SAAone, among other projects, and now on the Markermeerdijken. We use VolkerWessels’ own digital systems for systems engineering and digital inspections, and all our employees, from groundworkers to project directors, use our WAVE app for safety. Combined with the local knowledge that has proved so valuable on this project and the specialists at KWS@vice and Aveco de Bondt, we were also well placed to address the challenges at the outset. In practice, that is now paying off handsomely.”
Have a business enquiry for KWS? Get in touch
Who worked on Markermeerdijken
- led consortiumBoskalis NederlandMentioned in Broad foundation expertise for the Markermeerdijken project
- All-round foundation specialistGebr. van ’t HekMentioned in Broad foundation expertise for the Markermeerdijken project
- welding and fabricationLinden StaalbouwMentioned in Broad foundation expertise for the Markermeerdijken project
- engineering consultancyHektecMentioned in Broad foundation expertise for the Markermeerdijken project
- clientHoogheemraadschap Hollands NoorderkwartierMentioned in A complex technical challenge calls for a unique partnership
- Integrated monitoring team (IMT)AMMDMentioned in Managing the risk of damage at the Markermeerdijken
- earthmoving machinery with operatorHuiberts BVMentioned in Cumela contractor at the heart of the dike reinforcement project
- contractorDe Vries & van de WielMentioned in Hopper suction dredger TEXEL unloads more than 3.5 million m3 of sand
- settlement markers and other temporary worksWelding and assembly work (LMW)Mentioned in Special settlement gauges and fencing
- reinforcement supplierSpanberg WapeningMentioned in Integrated design and installation of reinforcing steel
- integrated designStaalis EngineeringMentioned in Integrated design and installation of reinforcing steel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectMarkermeerdijken
- ThemeFlood protection and climate-resilient water management
- SubjectWater infrastructure
- CompanyKWS
- CompanyBoskalis Nederland