200,000 tonnes of rock armour to strengthen the Markermeer dikes

Despite the many innovative methods being used to strengthen the Markermeer dikes, traditional rock armour is still being used extensively. Given the huge quantities involved, the Alliance has called on Combinatie Rotim & de Beijer VOF (CR&B) to supply the material. The joint venture was established by the two companies in 2013 to ensure continuity on major hydraulic engineering projects of this kind and limit risks.
“Combinatie CR&B is anything but a one-off joint venture,” says Edo Heslinga of Rotim. “We join forces on major projects because individually we cannot supply the quantities required, or meet the tight delivery schedules. Together, we can. So on smaller projects we compete with each other, while on others we work shoulder to shoulder. This is common practice among contractors, and it has proved beneficial for us as suppliers too.”
Three sections
Combinatie CR&B is no stranger to the Alliance. “We also supplied the rock armour for Marker Wadden, another Boskalis project,” Heslinga continues. The Marker Wadden nature islands recently won the prof.dr.ir. J.F. Agemaprijs at Waterbouwdag 2021. Awarded once every five years, the prize recognises the best and most innovative hydraulic engineering project of recent years. “It’s great to be able to build on that partnership by supplying more than 200,000 tonnes of rock armour for the Markermeer dikes.” Rob Ebergen of De Beijer Bouwgrondstoffen adds: “For our supplies, the project is divided into three sections: north, central and south. In some cases, we have to supply all three at the same time. That has a considerable impact on logistics and the quarries. By tackling a project of this scale as a joint venture, we can offer guarantees that are very reassuring for the Alliance, because continuity is vital on a project like this.”

Managing supply imbalances
200,000 tonnes of rock armour is a huge quantity. Heslinga explains: “The main requirement here is 40/200 kg graded riprap, which means producing a lot of material and also generating a lot of by-products at the quarry. So we need to strike a balance. The aim is to use these by-products on other projects wherever possible. That is precisely what makes the joint venture strong. Rotim mainly relies on quarries in Belgium, while De Beijer focuses primarily on quarries in Germany. This enables us to manage this kind of imbalance.” Ebergen adds: “And the logistics are quite a puzzle too. It is not so much a question of accessibility, but of weekly volumes, which range from 2,000 to as much as 10,000 tonnes. That means we need to be able to source supplies from several locations. During the preparatory phase, we worked with the Alliance to map out the logistics as effectively as possible. We enjoy contributing ideas. Sometimes we share ideas and a competitor runs with them, but that’s how it goes. We believe in sharing knowledge and getting involved. As a joint venture, we have twice the knowledge to develop the best possible plan. Our collaboration with the Alliance has been extremely positive and constructive.”
Both Rotim and De Beijer are independent family-owned businesses. “Between us, we have a huge range of solutions, with a wide variety of stone types and properties. That makes us particularly valuable as a joint venture when supplying major projects. We have supplied rock armour for the Beatrixsluis, the widening of the Twentekanaal, the Afsluitdijk and Flevokust, as well as more than a million tonnes for the excavation pits along the Spui,” Heslinga concludes.
A business enquiry for Rotim? Get in touch
Who worked on Markermeerdijken
- led consortiumBoskalis NederlandMentioned in Broad foundation expertise for the Markermeerdijken project
- All-round foundation specialistGebr. van ’t HekMentioned in Broad foundation expertise for the Markermeerdijken project
- welding and fabricationLinden StaalbouwMentioned in Broad foundation expertise for the Markermeerdijken project
- engineering consultancyHektecMentioned in Broad foundation expertise for the Markermeerdijken project
- clientHoogheemraadschap Hollands NoorderkwartierMentioned in A complex technical challenge calls for a unique partnership
- Integrated monitoring team (IMT)AMMDMentioned in Managing the risk of damage at the Markermeerdijken
- earthmoving machinery with operatorHuiberts BVMentioned in Cumela contractor at the heart of the dike reinforcement project
- contractorDe Vries & van de WielMentioned in Hopper suction dredger TEXEL unloads more than 3.5 million m3 of sand
- settlement markers and other temporary worksWelding and assembly work (LMW)Mentioned in Special settlement gauges and fencing
- reinforcement supplierSpanberg WapeningMentioned in Integrated design and installation of reinforcing steel
- integrated designStaalis EngineeringMentioned in Integrated design and installation of reinforcing steel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectMarkermeerdijken
- ThemeFlood protection and climate-resilient water management
- SubjectWater infrastructure
- CompanyRotim