Weaving diamond interchange tested virtually in advance

To improve traffic flow on the N206 during work on the RijnlandRoute, the traffic layout at the Leiden-West interchange has been changed since 27 May. The COMOL5 construction consortium has used what is known as a “weaving diamond interchange”. This traffic solution has been used in the United States for some time, but this is the first time it has been applied in the Netherlands.
For a period of 2.5 years, traffic will travel on the left-hand side of the road over a short stretch. Traffic is guided safely by traffic lights, road markings, signs, barriers and screens between the lanes. There are fewer crossing movements, allowing traffic to continue flowing safely and efficiently while work on the RijnlandRoute is under way. The A44 will remain open during the works.
Aiming for maximum certainty
In theory, the weaving diamond interchange should work well. To be on the safe side, the team called on Soltegro for help. The brief was: “Create a simulation of the proposed weaving diamond interchange to support the decision-making process.” We spoke to Soltegro employees Franc Fouchier, manager systems engineering & innovation, and Alexander van der Kolk, technical innovation lead, about this special simulation and its results.

The weaving diamond interchange from above.
“It is indeed very difficult to assess the situation from a static 2D design on paper,” Fouchier begins. “Soltegro specialises, among other things, in creating 3D traffic simulations, which are ideal for this situation.” Van der Kolk adds: “The process with the stakeholder was guided by traffic solutions manager Angelo van Turenhout. The DDI (Diverging Diamond Interchange) principle, the weaving diamond interchange, had to demonstrate in the simulation that it would actually reduce disruption to traffic. Soltegro chose a straightforward solution: transferring the road model from BIM into the 3D simulation, and adding the traffic layout based on a traffic model. The traffic flow simulated, in which drivers could also take part, was a forecast of conditions in 2030.”
A sharp focus on what is needed
Van der Kolk: “We set up the simulation in less than 12 weeks, focusing closely on what was needed. Soltegro developed an application that uses BIM. Following the simulation, COMOL5 made improvements to the road design. All the changes were ultimately incorporated into the BIM model.” Fouchier adds: “Less information makes the situation easier to understand, while of course taking account of the relevant laws and regulations.”
The simulation was tested by ‘special groups’. “These included a group comprising the competent authority and the police, as well as a test group of ordinary road users from the immediate area.
We looked at what would best support optimum safety. The tests were carried out in highly realistic conditions, either in a driver’s seat with three screens or using a 360˚ VR headset,” Fouchier explains. “Digitally demonstrating how things work prevents costs arising from errors later on, even if the improvements identified were incidental benefits. The tests proved beyond doubt that everyone automatically drove in the right direction in the simulation. This temporary solution by COMOL5 was therefore tested virtually in advance.”
A business enquiry for Soltegro? Get in touch
Who worked on RijnlandRoute
- technical modules
Croonwolter&drosMentioned in RijnlandRoute tunnel technology: a report from the heart of the operation - construction consortiumCOMOL5In this story
- anchor plates and plates for shoring supportsDe Boer StaalMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- custom-cut steel componentsDe Boer SnijbedrijfMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- clientProvince of South HollandMentioned in World first: sunlight in the tunnel delivers major energy savings
- contractors' joint ventureVINCI Construction Grands ProjetsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- contractors' joint ventureDEME Infra Marine ContractorsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- compressed air systemBOGE KompressorenMentioned in Energy-efficient compressed air system keeps tunnel bore under pressure
- temporary traffic measuresTraffic & MoreMentioned in Driving the right way is less straightforward than many people think
- traffic engineering expertMAP Traffic ManagementMentioned in Diverging Diamond Interchange: een stukje Amerikaans verkeersinzicht op Nederlandse bodem
- international contractor consortiumDIMCOMentioned in RijnlandRoute: The tunnel on the N434 is named Corbulotunnel
- pile breaker combinations
van der JagtMentioned in More than 60 years of expertise provide a solid foundation for structures on the RijnlandRoute
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRijnlandRoute
- SubjectSpecials
- CompanySoltegro
- CompanyCOMOL5