Energy-efficient compressed air system keeps tunnel bore under pressure

The RijnlandRoute, the new road link between Katwijk and Leiden, is taking shape. The project includes construction of a 2.25-kilometre bored tunnel. To maintain air pressure in the tunnel while boring, the COMOL5 contractor consortium is using the most energy-efficient compressed air system currently available on the market. It was designed by BOGE Kompressoren.
The most energy-efficient solution available today
As a long-standing supplier to several members of COMOL5, BOGE was asked to help design a compressed air system to maintain air pressure in the tunnel bore during construction. “The technical and financial aspects of the proposal were satisfactory and convincing enough for COMOL5 to choose BOGE,” says Olivier Matheron, procurement officer for the contractor consortium. Ronald Engberts of BOGE adds: “During the engineering phase, we are happy to work with clients to configure our compressors as efficiently as possible, based on their needs and requirements. For COMOL5, this resulted in the most energy-efficient solution currently available on the market.”

BOGE commissioned and fine-tuned the system at the end of 2019, ensuring that the compressors operate within the correct range. (Image: Guus Schoonewille)
Optimal air pressure at all times
The system BOGE developed for the RijnlandRoute comprises three S-4 series screw compressors and two DS350 compressed air refrigerated dryers. “This setup enables us to maintain optimal air pressure throughout tunnel boring,” says Engberts. “COMOL5 is also assured of a highly efficient system, with a backup always available thanks to this configuration. As a 112-year-young German family business, we place great value on high quality and are committed to saving energy.” The S-4 screw compressors feature an innovative design that delivers major advances in noise reduction, ease of maintenance and power consumption. Engberts says: “All the soundproofing panels can be removed, and all maintenance work can be carried out from either side. The oil separator tank, drive motor and compressor block are all elastically mounted on the base frame, effectively isolating them from vibration.”
Substantial savings
The refrigerated dryers downstream of the S-4 compressors also support BOGE’s mission to save as much energy as possible. “The effective controls on our DS350 refrigerated dryers ensure a highly energy-efficient compressed air drying process. Pressure loss is no longer an issue. This means we can save up to 6% for every bar of air pressure,” explains Engberts. “We commissioned and fine-tuned the system at the end of 2019, ensuring that the compressors operate within the correct range. We can also monitor the system remotely. Any faults can be dealt with remotely too. Since we have installed an extra backup on the RijnlandRoute, remote fault monitoring is less critical for this project. The system is currently operating to the client’s full satisfaction, which naturally makes us happy too. In any case, this is a special project for us as a company, because tunnels are not built very often in the Netherlands,” Engberts concludes enthusiastically.
Question about this story? Ask your question
Who worked on RijnlandRoute
- technical modules
Croonwolter&drosMentioned in RijnlandRoute tunnel technology: a report from the heart of the operation - anchor plates and plates for shoring supportsDe Boer StaalMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- custom-cut steel componentsDe Boer SnijbedrijfMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- clientProvince of South HollandMentioned in World first: sunlight in the tunnel delivers major energy savings
- contractors' joint ventureVINCI Construction Grands ProjetsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- contractors' joint ventureDEME Infra Marine ContractorsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- compressed air systemBOGE KompressorenIn this story
- temporary traffic measuresTraffic & MoreMentioned in Driving the right way is less straightforward than many people think
- traffic engineering expertMAP Traffic ManagementMentioned in Diverging Diamond Interchange: een stukje Amerikaans verkeersinzicht op Nederlandse bodem
- international contractor consortiumDIMCOMentioned in RijnlandRoute: The tunnel on the N434 is named Corbulotunnel
- pile breaker combinations
van der JagtMentioned in More than 60 years of expertise provide a solid foundation for structures on the RijnlandRoute