The A44 in the RijnlandRoute project: a complex phasing plan

To widen the A44 and renew five structures near Leiden, construction consortium COMOL5 devised a plan to carry out the work while keeping the A44 open.
The range of work and the large number of structures involved in the project call for a highly detailed phasing plan to address complex challenges. We sit down with Wim Guis, project manager at COMOL5, Robert Englebert, structures site manager, and Joey Lalloesingh of the Province of South Holland, project leader for structures.

The five phases around the A44
“The work is divided into five phases, designed to ensure that traffic on the A44 experiences little or no disruption,” says Guis. “We have to deal with the motorway and the local road network, work with many different disciplines, coordinate with several municipalities and water authorities, and there are major businesses in the area, including Janssen Biologics in Leiden and Airbus. In the first phase, we diverted the A44 to make room for construction of the new Ommedijk interchange, which will connect to the sunken section of the new N434,” says Guis. “The second phase involved building a diverging diamond interchange (DDI) at Leiden-West, a type of junction that takes up less space, freeing up room for construction without restricting traffic flow. In the third phase, we shifted the A44 westwards and are moving on to the fourth phase, in which we are building the eastern side of the flyovers. In the fifth phase, we will ensure that everything around the A44 can be brought into service and the final layout completed. After that, it will be ‘business as usual’ for road users.”
The five structures on the A44
Englebert describes the structures on the A44: “The northernmost structure is the flyover over Robert Boyleweg. Further south is the flyover over the N206, Plesmanlaan, which incorporates the cycle tunnel running parallel to the N206. Next comes the bridge over the Oude Rijn.” Lalloesingh adds: “The Oude Rijn bridge will combine the existing and new bridges. Unlike the other structures, where a new structure is built alongside the old one before the old one is demolished, the Oude Rijn bridge will be retained.” Guis explains: “The existing bridge over the Oude Rijn has been strengthened to extend its service life. The old bridge was a bascule bridge, which has been fixed in place during the work. The new bridge is a fixed bridge.”
Englebert continues his list: “Finally, there is the flyover over Ommedijkseweg and the Ommedijk interchange, which is integrated into the sunken section. Throughout the phasing, the eastbound carriageway is dealt with first, followed later by the westbound carriageway. Traffic can continue to use the A44 at all times.” Guis notes that each flyover will be demolished over a single weekend.

Current progress
The four northernmost structures are ready for the traffic switch. This summer, the A44 will be diverted to its new alignment, after which the old structures can be demolished. Lalloesingh says: “We are now entering an important new phase and expect to have the final layout of the A44 in place by summer 2021, although work on the N434 will still be under way and the Ommedijk interchange will not yet be open. Englebert concludes: “Together, we will then have completed a major project in a series of complex phases, all while traffic was able to continue on its way without disruption. It has been a fine collaboration between the design, planning and delivery teams, made possible only by the integration of the various disciplines.”
RijnlandRoute
The RijnlandRoute is a project by the Province of South Holland and comprises a new road link between Katwijk, via the A44, and the A4 near Leiden. The road will resolve existing bottlenecks and ensure traffic flows smoothly across the Holland Rijnland region, particularly around Leiden and Katwijk.
Two of the RijnlandRoute’s three projects are now under way. The N434/A44/A4 project, which includes the bored tunnel, is being delivered by contractor consortium Comol5. Comol5 is an international consortium comprising TBI companies Mobilis and Croonwolter&dros, VINCI Construction Grands Projets and DEME Infra Marine Contractors. The N206 ir.G. Tjalmaweg project is being delivered by Boskalis. The third RijnlandRoute project, the N206 Europaweg, is still in preparation.
Have a business enquiry for Mobilis? Get in touch
Who worked on RijnlandRoute
- technical modules
Croonwolter&drosMentioned in RijnlandRoute tunnel technology: a report from the heart of the operation - anchor plates and plates for shoring supportsDe Boer StaalMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- custom-cut steel componentsDe Boer SnijbedrijfMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- clientProvince of South HollandMentioned in World first: sunlight in the tunnel delivers major energy savings
- contractors' joint ventureVINCI Construction Grands ProjetsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- contractors' joint ventureDEME Infra Marine ContractorsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- compressed air systemBOGE KompressorenMentioned in Energy-efficient compressed air system keeps tunnel bore under pressure
- temporary traffic measuresTraffic & MoreMentioned in Driving the right way is less straightforward than many people think
- traffic engineering expertMAP Traffic ManagementMentioned in Diverging Diamond Interchange: een stukje Amerikaans verkeersinzicht op Nederlandse bodem
- international contractor consortiumDIMCOMentioned in RijnlandRoute: The tunnel on the N434 is named Corbulotunnel
- pile breaker combinations
van der JagtMentioned in More than 60 years of expertise provide a solid foundation for structures on the RijnlandRoute
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRijnlandRoute
- SubjectNews
- CompanyMobilis
- CompanyCroonwolter&dros