RijnlandRoute tunnel technology: a report from the heart of the operation

At the heart of the RijnlandRoute is the N434, the future link between the A4 and A44 near Leiden. Almost 2.5 kilometres of the N434 will run through a bored tunnel. The contract to build the tunnel was awarded to the COMOL5 consortium, formed by Croonwolter&dros, Mobilis, Vinci and Dimco.
The Province of South Holland awarded this part of the RijnlandRoute project to COMOL5 under the MEAT (most economically advantageous tender) criteria. COMOL5 committed to having everything ready for IFAT (Integral Fabrication Acceptance Test) two years before opening. The team is now working flat out at a dedicated test centre in Eindhoven. GWW magazine was given the unique opportunity to take a look around.
Welcome to the world of tomorrow
The old industrial buildings housing COMOL5 blend into the streetscape of an old Eindhoven neighbourhood. From the outside, there is no hint of what is going on inside. The surprise is all the greater when Jan Witte, project manager at Croonwolter&dros and assistant project manager at COMOL5, shows us in. It is a completely different world, packed with technology and innovation. As we take in the scene, Witte begins to explain: “At this test facility in Eindhoven, we are building modular units for all the tunnel’s technical systems. The advantage is that we can carry out our tests in fully controlled conditions. Everything involved in the technical work is within walking distance. We build, simulate, test, solve problems and ultimately produce ready-to-install modules that will be sent to the tunnel on a plug-and-play basis.
Any problems we encounter can be dealt with straight away and very efficiently. This will help us avoid rework costs, delays and other unpleasant surprises later on. Another advantage is that the number of interfaces with the civil works has fallen considerably.”

Simulation of the tunnel entrance. Traffic light, matrix sign and LED luminaire.
Working quite literally in the future
“It is quite something to be able to drive through the tunnel virtually already,” says Witte. “Everything is in our integrated 3D model/BIM. Even more remarkable is that the test site in Eindhoven is already connected remotely to the traffic control centre in Rhoon. The tunnel will be operated from there, but for the team there, the tunnel already exists, in a sense. We have a live connection with Rhoon, and have already had audio contact. Bear in mind that the tunnel boring machine will not start excavating the first tunnel bore in Leiden until July this year. We are quite literally working in the future here.”

This is what the local control unit looks like.
The test centre is a stone’s throw from the Croonwolter&dros office in Eindhoven. Is that a coincidence? “No coincidence,” Witte replies. “Our Technical Automation department is based there. It works very well to be so close together. Short distances, both within the company and with external parties, make a substantial contribution to an efficient workflow.”
It all started with a sketch
Witte smiles as he shares an anecdote with us: “The idea of modular construction in the early stages literally began as a sketch. That same sketch, developed into a finished concept, won us the TBI Innovation Award in 2017, so I treasure the drawing. It showed us that this approach gives us a real advantage. The method has now also been adopted within the organisation as an established formula in other disciplines.” The construction drawings on the walls of the test centre show clearly how everything will be built. COMOL5 is building no fewer than 24 technical modules in total, to be distributed between the East and West service buildings on either side of the tunnel. There will also be modules for various technical systems inside the tunnel itself. “Lego-style construction is a good way to describe the approach. All the components are delivered to Leiden ready to plug and play, and all that remains is to connect the cables. If something does not work after connection, we can be 99% sure it is down to the cabling, because everything leaves Eindhoven fully operational.”

Emergency telephone/intercom test set-up.
Packed with innovation
The array of technical wizardry is impressive. Everything is there and working, from a long line of CCTV cameras and the ICT network to a full complement of operational emergency telephones/intercoms, a complete field of fire detectors connected to the fire alarm system (BMI), and the SOS (speed undercutting system) linked to the MTM (motorway traffic management). There is no shortage of innovation, and everything is designed with sustainability in mind. “One exciting development is the Solar Optic Fiber sunlight system. GPS-controlled lenses on the tunnel track the sun, focusing the light and transmitting it via fibre-optic cables for up to 100 metres to daylight luminaires at the tunnel entrances. This drastically reduces the energy needed to light the tunnel portals. The light is needed to make the transition between the tunnel and the outside world as easy as possible on drivers’ eyes,” Witte explains.

Artist’s impression of the East service building.
Delivery of the first modules is scheduled for the second half of 2020. “The units have been specially designed to measure 3 x 3 x 9 metres. That is the maximum size permitted for standard road transport. However, we are currently looking at the possibility of transporting them by water for sustainability reasons. That would make a significant contribution to reducing CO2 emissions,” says Witte.
A business enquiry for Croonwolter&dros? Get in touch
Who worked on RijnlandRoute
- anchor plates and plates for shoring supportsDe Boer StaalMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- custom-cut steel componentsDe Boer SnijbedrijfMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- clientProvince of South HollandMentioned in World first: sunlight in the tunnel delivers major energy savings
- contractors' joint ventureVINCI Construction Grands ProjetsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- contractors' joint ventureDEME Infra Marine ContractorsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- compressed air systemBOGE KompressorenMentioned in Energy-efficient compressed air system keeps tunnel bore under pressure
- temporary traffic measuresTraffic & MoreMentioned in Driving the right way is less straightforward than many people think
- traffic engineering expertMAP Traffic ManagementMentioned in Diverging Diamond Interchange: een stukje Amerikaans verkeersinzicht op Nederlandse bodem
- international contractor consortiumDIMCOMentioned in RijnlandRoute: The tunnel on the N434 is named Corbulotunnel
- pile breaker combinations
van der JagtMentioned in More than 60 years of expertise provide a solid foundation for structures on the RijnlandRoute
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRijnlandRoute
- ThemeUnderground construction
- SubjectBridge construction
- CompanyCroonwolter&dros
- CompanyMobilis