Standing out by not rising above ground level

Perhaps a somewhat cryptic headline, but it is certainly true. Within the RijnlandRoute project, the sunken section of the N434 has a special place.
The N434 is the new east-west link between the A44 and the A4 near Leiden. Alongside the construction of the 2.5 km-long tunnel, construction consortium Comol5 is building a sunken section approximately 1.4 km long. We talk to Sjoukje van Heesch, landscape architect at the Province of Zuid-Holland, Timo de Goede, design lead at Comol5, and Hugo Jacobs, construction manager at Comol5, about this cleverly designed sunken section, which takes the N434 below ground level where needed.
“The sunken section serves two purposes,” Timo begins. “At the eastern end, it bridges the difference in elevation between the bored tunnel and the flyover. At the western end, it is purely a landscaping measure.”

Traffic passes unseen through a valuable nature reserve
Sjoukje: “The Province of Zuid-Holland has designated the polder on the western side as a protected meadow bird area and a cultural heritage asset of outstanding value. It is therefore important to preserve the polder intact. The fact that a road has been built through it at all is remarkable.” The aqueduct is mentioned in the same breath as the sunken section. “The Veenwatering flows through it,” Timo explains. “It is not very deep, but it is wide and important to the landscape.”
Sjoukje was involved in the decision to build an aqueduct in 2012: “Integrating the sunken section into the landscape requires careful attention. We promised local residents that nothing would protrude above ground level. I am personally committed to honouring that promise. The landscape architects at wUrck have come up with a very attractive solution. Of course, compromises have to be made here and there, there is no getting around that. We could not avoid having a C2000 mast and a barrier. Overall, however, the sunken section has been very successfully kept out of sight.”

A unique use of traffic signs
“We had extensive discussions within Comol5, because challenges arose right down to the details. Under the guidelines for signs above roads, it would not have been possible to keep the signs below ground level. The solution is both effective and creative: we were allowed to use signs designed for tunnels. They are a smaller version, but fully approved. This is a unique application for a sunken section.”
6,000 foundation piles
The sunken section is a cut-and-cover structure. This means working with groundwater, so the surrounding area has to be carefully monitored. Timo explains: “The top layer, which is 5 to 8 metres thick, is very poor. That is why the entire sunken section is ‘suspended’ from around 6,000 anchor piles, which keep the structure in place.”

Veenwatering temporarily diverted
Hugo explains how the aqueduct was built: “The sunken section crosses the Veenwatering, passing underneath it. To build the aqueduct, the Veenwatering was first diverted using sheet pile walls. The first cofferdam could then be built, with an underwater concrete base. Once complete, it was dewatered so construction of the aqueduct could continue. The floors, walls and central pier supporting the aqueduct were then built. Beneath the aqueduct, the sunken section contains a water reservoir with a pumping installation to drain rainwater.”
Once the aqueduct was commissioned, the Veenwatering could return to its normal course. “The diversion was closed off and backfilled with sand,” says Hugo. “The aqueduct is 14 metres wide and 1.5 metres deep.”
Clever solutions
The sunken section’s design is not only considerate of local residents, it also takes road users into account. “It was quite a challenge, particularly at the western end, at the Ommedijk interchange where it connects to the A44. In the original design, drivers heading west were faced with a pointed projection several metres high. To make the route more comfortable visually, the wall alongside the exit towards Amsterdam was replaced with a slope in the cut-and-cover section. This means the excavation has to be wider.” Sjoukje adds: “This slope was specifically designed to improve the driving experience.”
The wildlife crossing and cycle path beneath the A44 are also notable features. “They have been combined with the sunken section,” Timo concludes. “It was quite a puzzle to fit them in with the road alignment. The crossing was built using a membrane structure, rather than the heavy concrete box used for the sunken section. It consists of an open, U-shaped slope with a membrane in the ground, forming a funnel that invites all kinds of wildlife to cross.”
RijnlandRoute
The RijnlandRoute is a project by the Province of Zuid-Holland and comprises a new road link between Katwijk, via the A44, and the A4 near Leiden. The road will address existing bottlenecks and ensure traffic continues to flow smoothly across the Holland Rijnland region, particularly around Leiden and Katwijk.
Two of the three RijnlandRoute projects are now under way. The N434/A44/A4 project, which includes the bored tunnel, is being delivered by contractor consortium Comol5. Comol5 is an international consortium comprising TBI companies Mobilis and Croonwolter&dros, VINCI Construction Grands Projets and DEME Infra Marine Contractors. The N206 ir.G. Tjalmaweg project is being delivered by Boskalis. The third RijnlandRoute project, the N206 Europaweg, is still in preparation. www.rijnlandroute.nl
Have a business enquiry for Mobilis? Get in touch
Who worked on RijnlandRoute
- technical modules
Croonwolter&drosMentioned in RijnlandRoute tunnel technology: a report from the heart of the operation - anchor plates and plates for shoring supportsDe Boer StaalMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- custom-cut steel componentsDe Boer SnijbedrijfMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- clientProvince of South HollandMentioned in World first: sunlight in the tunnel delivers major energy savings
- contractors' joint ventureVINCI Construction Grands ProjetsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- contractors' joint ventureDEME Infra Marine ContractorsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- compressed air systemBOGE KompressorenMentioned in Energy-efficient compressed air system keeps tunnel bore under pressure
- temporary traffic measuresTraffic & MoreMentioned in Driving the right way is less straightforward than many people think
- traffic engineering expertMAP Traffic ManagementMentioned in Diverging Diamond Interchange: een stukje Amerikaans verkeersinzicht op Nederlandse bodem
- international contractor consortiumDIMCOMentioned in RijnlandRoute: The tunnel on the N434 is named Corbulotunnel
- pile breaker combinations
van der JagtMentioned in More than 60 years of expertise provide a solid foundation for structures on the RijnlandRoute
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRijnlandRoute
- SubjectRoad construction
- CompanywUrck architectuur stedenbouw landschap
- CompanyMobilis
- CompanyCroonwolter&dros