Made-to-measure steel for the RijnlandRoute bored tunnel

After years of preparation and debate, construction of the RijnlandRoute finally got under way in August 2017. The RijnlandRoute is intended to improve accessibility and quality of life in the Leiden region and is expected to be completed in 2022. A key part of the project is the construction of a 2.5-kilometre bored tunnel (N434). De Boer Staal and De Boer Snijbedrijf are suppliers to the RijnlandRoute.
A challenging megaproject
Before tunnel boring can begin, a range of preliminary foundation works must first be carried out. Sheet piles have been installed at the tunnel shafts, for example, and anchor piles have been driven into the ground.
“The anchor piles secure the base slab of the construction pit, while bracing frames have been installed to hold the sheet piles in place. These frames consist of tubes, sections, tie bars and various made-to-measure steel components (temporary steelwork),” says René Wentzel, commercial manager at De Boer Staal and De Boer Snijbedrijf.
Steel anchor plates and support stools
“We specialise in cutting and processing steel and hold ample stocks of plate and sections in a range of sizes, grades and thicknesses. We are flexible and can deliver quickly. For the RijnlandRoute, we cut 60 tonnes of anchor plates and plates for support stools to size from S355J2+N steel.”
Special tunnel boring machine
Construction of the tunnel began in June 2019. The tunnel boring machine (TBM) has a cutterhead almost 11 metres in diameter and excavates and builds the tunnel at the same time. After around 6 months, the first tunnel bore will be complete and boring will begin on the second. The slogan ‘YOU BUILD WE SUPPLY’ applies to civil engineering too.
Question about this story? Ask your question
Who worked on RijnlandRoute
- technical modules
Croonwolter&drosMentioned in RijnlandRoute tunnel technology: a report from the heart of the operation - anchor plates and plates for shoring supportsDe Boer StaalIn this story
- custom-cut steel componentsDe Boer SnijbedrijfIn this story
- clientProvince of South HollandMentioned in World first: sunlight in the tunnel delivers major energy savings
- contractors' joint ventureVINCI Construction Grands ProjetsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- contractors' joint ventureDEME Infra Marine ContractorsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- compressed air systemBOGE KompressorenMentioned in Energy-efficient compressed air system keeps tunnel bore under pressure
- temporary traffic measuresTraffic & MoreMentioned in Driving the right way is less straightforward than many people think
- traffic engineering expertMAP Traffic ManagementMentioned in Diverging Diamond Interchange: een stukje Amerikaans verkeersinzicht op Nederlandse bodem
- international contractor consortiumDIMCOMentioned in RijnlandRoute: The tunnel on the N434 is named Corbulotunnel
- pile breaker combinations
van der JagtMentioned in More than 60 years of expertise provide a solid foundation for structures on the RijnlandRoute
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRijnlandRoute
- ThemeUnderground construction
- SubjectBridge construction
- CompanyDe Boer Staal
- CompanyDe Boer Snijbedrijf