Braided diamond interchange tested virtually in advance

Braided diamond interchange tested virtually in advance

To improve traffic flow on the N206 during work on the RijnlandRoute, the traffic layout at the Leiden-West interchange has been changed since 27 May. Construction consortium COMOL5 has introduced the so-called “braided diamond interchange”. This traffic solution has been used in the United States for some time, but this is the first time it has been used in the Netherlands.

For a period of 2.5 years, traffic will travel on the left-hand side of the road for a short distance. It will be guided safely by traffic lights, road markings, signs, barriers and screens between the lanes. There are fewer crossing movements, allowing traffic to continue flowing safely and smoothly while work on the RijnlandRoute is under way. The A44 will remain open during the works.

Aiming for maximum certainty

In theory, the braided diamond interchange should work perfectly. To be absolutely sure, the team called on Soltegro for help. The brief was: “Create a simulation of the proposed braided diamond interchange to support the decision-making process.” We speak to Soltegro employees Franc Fouchier, manager systems engineering & innovation, and Alexander van der Kolk, technical innovation lead, about this unusual simulation and its results.

De state-of-the-art-fabriek van Bosch Beton in Barneveld.

An aerial view of the braided diamond interchange.

“It is indeed very difficult to assess the situation from a static, paper-based 2D design,” Fouchier begins. “Soltegro specialises, among other things, in creating 3D traffic simulations, which are ideal for this situation.” Van der Kolk adds: “The process with the stakeholder was facilitated by traffic solutions manager Angelo van Turenhout. The DDI (Diverging Diamond Interchange) principle, the braided diamond interchange, had to demonstrate in the simulation that it would actually reduce disruption to traffic. Soltegro opted for a straightforward solution: transferring the road model from BIM into the 3D simulation, with the traffic layout added in accordance with a traffic model. The traffic flow that was simulated, and which the driver could experience from behind the wheel, was a forecast of what traffic would be like in 2030.”

A sharp focus on what is needed

Van der Kolk: “We set up the simulation in less than 12 weeks and focused closely on what was needed. Soltegro developed an application that uses BIM. Following the simulation, COMOL5 made improvements to the road design. All the changes were ultimately incorporated into the BIM model.” Fouchier adds: “Less information makes the situation easier to understand, while of course taking account of laws and regulations.”

The simulation was tested by ‘special groups’. “These included a group comprising the competent authority and police, as well as a test group of regular road users from the immediate area.

We looked at what would deliver optimum safety. The tests were carried out in highly realistic conditions, either in a driver’s seat with three screens or wearing a 360˚ VR headset,” Fouchier explains. “By digitally demonstrating how things work, we can prevent rework costs later on, even if the improvements identified are incidental findings. The tests proved beyond doubt that everyone in the simulation automatically drove in the right direction. COMOL5’s temporary solution was therefore tested virtually in advance.”   

A business enquiry for Soltegro? Get in touch

Who worked on RijnlandRoute

  1. technical modulesCroonwolter&drosMentioned in RijnlandRoute tunnel technology: a report from the heart of the operation
  2. simulationSoltegroMentioned in Weaving diamond interchange tested virtually in advance
  3. construction consortiumCOMOL5Mentioned in Weaving diamond interchange tested virtually in advance
  4. anchor plates and plates for shoring supportsDe Boer StaalMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
  5. custom-cut steel componentsDe Boer SnijbedrijfMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
  6. clientProvince of South HollandMentioned in World first: sunlight in the tunnel delivers major energy savings
  7. contractors' joint ventureMobilisMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
  8. contractors' joint ventureVINCI Construction Grands ProjetsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
  9. contractors' joint ventureDEME Infra Marine ContractorsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
  10. compressed air systemBOGE KompressorenMentioned in Energy-efficient compressed air system keeps tunnel bore under pressure
  11. temporary traffic measuresTraffic & MoreMentioned in Driving the right way is less straightforward than many people think
  12. traffic engineering expertMAP Traffic ManagementMentioned in Diverging Diamond Interchange: een stukje Amerikaans verkeersinzicht op Nederlandse bodem
  13. international contractor consortiumDIMCOMentioned in RijnlandRoute: The tunnel on the N434 is named Corbulotunnel
  14. pile breaker combinationsvan der JagtMentioned in More than 60 years of expertise provide a solid foundation for structures on the RijnlandRoute
  15. precast beamsHaitsma BetonMentioned in Improving access to Holland-Rijnland
  16. architectural practicewUrckMentioned in Standing out by not rising above ground level
  17. setting outIv-InfraMentioned in From setting out to monitoring

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectRijnlandRoute
  • SubjectBouwMat
  • CompanySoltegro
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.