Specials

More than 60 years of expertise provide a solid foundation for structures on the RijnlandRoute

More than 60 years of expertise provide a solid foundation for structures on the RijnlandRoute

The work is officially known as ‘pile cropping’. More than 60 years ago, the family business removed pile heads by hand. Adriaan van der Jagt, director and owner of the Van der Jagt Groep, is the third generation to run the family business.

“My grandfather started it, and back then everything was indeed done by hand. Today, we have developed machines for the job, the so-called ‘pile-cracking rigs’.”

The Van der Jagt Groep is working in stages to prepare the driven and bored piles for a number of structures on the RijnlandRoute. “We’re talking about more than 1,200 piles in total,” says Van der Jagt. “We started a year and a half ago. We’re working alongside the A4 near Leiden, where the flyovers for the new Hofvliet interchange are located.”

Exposing the reinforcement starters

The Van der Jagt Groep completes between 30 and 50 piles a day. “The piling rig installs the piles, after which we remove the concrete pile heads in stages. This exposes the reinforcement starters so they can be incorporated into the structure. The work requires a considerable level of commitment. We sometimes use two pile-cracking rigs to meet the required schedule.” 

As well as cropping around 1,200 piles with diameters of 500 and 600 mm, Van der Jagt does much more for construction consortium COMOL5. “We have expertise across all disciplines, including drilling and sawing,” explains Van der Jagt. “We’re therefore regularly called on to carry out various tasks on the project.”

A bird’s-eye view

Van der Jagt gives us a quick tour of the structures where his company is working. “Near the A44, that includes the Robert Boyleviaduct, the Plesmanlaan viaduct, the Oude Rijnbrug, where a new bridge is being built, and the Ommedijkseweg viaduct. We’re also working at the future Ommedijk interchange, partly on the sunken section of the new N434, where we demolished the pile heads for the diaphragm walls, and at the bored tunnel. In addition, we’re working at the tunnel entrance on the A4 side.” As mentioned, the work is being carried out in stages, and the Van der Jagt Groep will remain firmly on site until it is complete.

Van der Jagt concludes: “We are, and will remain, a true family business. That means we are all very proud of our work. When traffic is using the RijnlandRoute, nobody will see the work we’ve done there. But knowing that we have literally helped lay the foundations for all this is a great feeling!”

A business enquiry for Van der Jagt Groep? Get in touch

Who worked on RijnlandRoute

  1. technical modulesCroonwolter&drosMentioned in RijnlandRoute tunnel technology: a report from the heart of the operation
  2. simulationSoltegroMentioned in Weaving diamond interchange tested virtually in advance
  3. construction consortiumCOMOL5Mentioned in Weaving diamond interchange tested virtually in advance
  4. anchor plates and plates for shoring supportsDe Boer StaalMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
  5. custom-cut steel componentsDe Boer SnijbedrijfMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
  6. clientProvince of South HollandMentioned in World first: sunlight in the tunnel delivers major energy savings
  7. contractors' joint ventureMobilisMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
  8. contractors' joint ventureVINCI Construction Grands ProjetsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
  9. contractors' joint ventureDEME Infra Marine ContractorsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
  10. compressed air systemBOGE KompressorenMentioned in Energy-efficient compressed air system keeps tunnel bore under pressure
  11. temporary traffic measuresTraffic & MoreMentioned in Driving the right way is less straightforward than many people think
  12. traffic engineering expertMAP Traffic ManagementMentioned in Diverging Diamond Interchange: een stukje Amerikaans verkeersinzicht op Nederlandse bodem
  13. international contractor consortiumDIMCOMentioned in RijnlandRoute: The tunnel on the N434 is named Corbulotunnel
  14. pile breaker combinationsvan der JagtIn this story
  15. precast beamsHaitsma BetonMentioned in Improving access to Holland-Rijnland
  16. architectural practicewUrckMentioned in Standing out by not rising above ground level
  17. setting outIv-InfraMentioned in From setting out to monitoring

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectRijnlandRoute
  • SubjectSpecials
  • CompanyVan der Jagt Groep
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.