Braided diamond interchange tested virtually in advance

To keep traffic moving on the N206 during work on the RijnlandRoute, a new traffic arrangement has been in place at the Leiden-West interchange since 27 May…
To keep traffic moving on the N206 during work on the RijnlandRoute, the traffic arrangement at the Leiden-West interchange changed on 27 May. Construction consortium COMOL5 used what is known as a “braided diamond interchange”. This traffic solution has been used in the United States for some time, but this is the first time it has been applied in the Netherlands.
For a period of 2.5 years, traffic will travel on the left-hand side of the road for a short distance. Traffic lights, road markings, signs, barriers and screens between the lanes will guide vehicles safely. There are fewer crossings, allowing traffic to continue flowing safely and smoothly during work on the RijnlandRoute. The A44 will remain open during the works.
Aiming for maximum certainty
In theory, the braided diamond interchange should work perfectly well. To be on the safe side, COMOL5 called on Soltegro for help. The brief was: “Create a simulation of the proposed braided diamond interchange to support the decision-making process.” We spoke to Soltegro employees Franc Fouchier, manager systems engineering & innovation, and Alexander van der Kolk, technical innovation lead, about this innovative simulation and its results.

An aerial view of the braided diamond interchange.
“It is indeed very difficult to assess the situation from a static 2D design on paper,” Fouchier begins. “Soltegro specialises, among other things, in creating 3D traffic simulations, which are ideal for this situation.” Van der Kolk adds: “The process with the stakeholder was facilitated by traffic solutions manager Angelo van Turenhout. The DDI (Diverging Diamond Interchange) principle, or braided diamond interchange, had to demonstrate in the simulation that it would actually reduce disruption to traffic. Soltegro opted for a straightforward solution: transferring the road model from BIM into the 3D simulation, then adding the traffic situation based on a traffic model. The simulated traffic flow, which drivers could experience from behind the wheel, was based on a forecast of what traffic would be like in 2030.”
A sharp focus on what is needed
Van der Kolk: “We set up the simulation in less than 12 weeks, focusing closely on what was needed. Soltegro developed an application that uses BIM. Following the simulation, COMOL5 made improvements to the road design. All the changes were then incorporated into the BIM model.” Fouchier adds: “Less information makes the situation easier to understand, while of course taking account of the relevant laws and regulations.”
The simulation was tested by ‘special groups’. “One of these was a group comprising the competent authority and police, as well as a test group of regular road users from the immediate area.
The tests looked at what would ensure optimum safety. They were conducted in highly realistic conditions, either in a driver’s seat with three screens or using a 360˚ VR headset,” Fouchier explains. “Digitally demonstrating how things work helps prevent rework costs later on, even if the improvements are ‘incidental benefits’. The tests provided conclusive proof that everyone automatically drives in the right direction in the simulation. COMOL5’s temporary solution was therefore tested virtually in advance.”
A business enquiry for Soltegro? Get in touch
Who worked on RijnlandRoute
- technical modules
Croonwolter&drosMentioned in RijnlandRoute tunnel technology: a report from the heart of the operation - anchor plates and plates for shoring supportsDe Boer StaalMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- custom-cut steel componentsDe Boer SnijbedrijfMentioned in Made-to-measure steel for the RijnlandRoute bored tunnel
- clientProvince of South HollandMentioned in World first: sunlight in the tunnel delivers major energy savings
- contractors' joint ventureVINCI Construction Grands ProjetsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- contractors' joint ventureDEME Infra Marine ContractorsMentioned in Er wordt hard gewerkt aan het “nieuw Leids Ontzet”
- compressed air systemBOGE KompressorenMentioned in Energy-efficient compressed air system keeps tunnel bore under pressure
- temporary traffic measuresTraffic & MoreMentioned in Driving the right way is less straightforward than many people think
- traffic engineering expertMAP Traffic ManagementMentioned in Diverging Diamond Interchange: een stukje Amerikaans verkeersinzicht op Nederlandse bodem
- international contractor consortiumDIMCOMentioned in RijnlandRoute: The tunnel on the N434 is named Corbulotunnel
- pile breaker combinations
van der JagtMentioned in More than 60 years of expertise provide a solid foundation for structures on the RijnlandRoute
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRijnlandRoute
- SubjectBouwMat
- CompanySoltegro