Underground infrastructure

Slipformed barrier improves safety in Rottemerentunnel

Text Roel van GilsImage De Groene Boog

De Wirtgen SP25i slipformpaver van BKB Infra draait momenteel op volle toeren.
De Wirtgen SP25i slipformpaver van BKB Infra draait momenteel op volle toeren.

As on many other tunnel projects, construction consortium De Groene Boog has opted for a slipformed barrier rather than a precast one at Rottemerentunnel. This technique makes it possible to create a smoother line, resulting in a calmer view for road users. BKB Infra is regarded as the leading specialist in constructing slipformed barriers and has even developed a bespoke mould and a fire-retardant concrete mix for this project. 

Since its first project in the combined road and rail tunnel in Nijverdal in 2012, BKB Infra’s slipformed barrier concept has taken off. The Sluiskiltunnel, the RijnlandRoute, the Victory Boogie Woogietunnel and the tunnels on the Blankenburgverbinding are just a few of the many projects where BKB Infra has cast vehicle restraint systems in situ. “What we do is a bit like large-scale 3D printing,” says Laurens Bogerd, commercial manager at BKB Infra. “Using our slipform paver, we form a concrete barrier from ready-mixed concrete in a single pass, following a smooth line.”

A further boost to fire resistance

BKB Infra is a familiar presence in tunnels across the Netherlands and knows better than anyone how to turn the constraints and requirements into a ready-to-use solution. “The same applies here on the A16 Rotterdam,” says Laurens, continuing: “Rijkswaterstaat, for example, has specific fire-safety requirements. The mix we are using here for the slipformed barrier has been modified and tested to further improve the tunnel’s fire resistance. It is the same mix we previously used on the Blankenburgverbinding.” The mix flows through a mould in the slipform paver to achieve the required end result. “A machine like this comes from the manufacturer with a standard mould. We have modified and further developed it in-house, however, so we can work much more efficiently and finish the barrier to the level normally specified by CUR100 standard B9.”

BKB Infra is installing a total of 11,258 metres of slipformed barrier on the A16 Rotterdam.

Barrier with a free-standing end

BKB Infra is installing a total of 11,258 metres of slipformed barrier on the A16 Rotterdam, most of it in the enclosed tunnel section (8,950 metres), where it is 80 centimetres high. The barrier will be 90 centimetres high on the tunnel approaches. “In preparation for this work, we completed an initial phase of several hundred metres last year using our Wirtgen SP25i slipform paver on a connecting ramp between the A16 and the A13,” says Laurens. “Here, in-situ casting was the only option, as the 90-centimetre-high barrier was positioned against an existing wall with a noise barrier above it. There was not enough room to place the barrier fully flush against the wall. With no restraint on one side, we developed a bespoke slipform mould so we could form the final 30 centimetres of the barrier with a free-standing end. Custom structures like this are well within our capabilities.” 

Expansion joints and saw cuts

BKB Infra’s Wirtgen SP25i slipform paver is equipped with a GPS unit. “This means we can use De Groene Boog’s 3D design to set the barrier’s design level directly and cast it along the road in a smooth line,” Laurens explains. “Structurally, the tunnel is divided into 25-metre sections. We therefore install an expansion joint in the barrier every 25 metres, allowing the sections to expand and preventing the barrier from being crushed. We also cut a contraction joint every 3.10 metres, a 5-centimetre-deep saw cut over the full height of the barrier.” 

Forming recesses mechanically

Unevenness in the base course can easily be accommodated when installing a slipformed barrier. BKB Infra has also devised a solution for the emergency telephone cabinets and escape doors required in the tunnel. “We have modified the mould so we can work around them without moving the machine away from the wall. Of course, you can also form and cast such recesses by hand afterwards, but that takes a great deal of time and money. We would rather invest the latter in a modified mould, so we can do everything mechanically to the highest possible quality, and in less time. We also have our parent company VolkerWessels to thank: it is a large, financially sound organisation that helps make investment in new moulds and techniques possible.”

Roundabout kerbs and concrete pavements

The original plan was to slipform the barrier first and lay the asphalt afterwards. The first asphalt layers have already been laid, however, and only the surface course remains. “That works in our favour,” says Laurens. BKB Infra’s slipform paver is currently running at full capacity. “We are on schedule to finish by the end of February 2024. We are not on the project continuously, incidentally. We coordinate the schedule with De Groene Boog and complete the work one tunnel tube at a time. In between, we can easily move on to other projects elsewhere in the country. The slipform paver is versatile and can be deployed flexibly. We also use it to cast flat surfaces, such as cycle paths between 2 and 4.5 metres wide. We have several other machines too, both smaller and larger. With our SP1600, we can lay a 10-metre-wide concrete pavement in a single pass. Our smaller SP15i is also used for roundabout kerbs and all kinds of linear structures. Our pavers are ideal for casting linear features in situ.” 

A business enquiry for BKB Infra? Get in touch

Who worked on Rottemerentunnel

  1. construction consortiumDe Groene BoogMentioned in Reinforcement steel for the Rottemeren Tunnel’s underwater concrete floor
  2. reinforcing steelBCS (Buig Centrale Steenbergen)Mentioned in Reinforcement steel for the Rottemeren Tunnel’s underwater concrete floor
  3. construction consortiumBESIXMentioned in ‘Berend Botje’ can keep sailing as usual
  4. supportSafeMentioned in ‘Berend Botje’ can keep sailing as usual
  5. fire-resistant doorsKeersMentioned in Fire-resistant sliding doors for Rottemeren Tunnel
  6. fire-resistant boardsPromatMentioned in Fire-resistant boards offer the new Rottemerentunnel optimal protection
  7. De Groene Boog construction consortiumMobilisMentioned in Focus on fit-out works in the Rottemeren Tunnel
  8. tunnel systemsCroonwolter&drosMentioned in Focus on fit-out works in the Rottemeren Tunnel
  9. lining walls and slatted claddingAldowaMentioned in Concrete structure ‘wrapped’ in aluminium acoustic screens and louvre cladding
  10. architectQWA-architectenMentioned in Concrete structure ‘wrapped’ in aluminium acoustic screens and louvre cladding
  11. installationKaeferMentioned in Rottemerentunnel concrete structure protected with fire-resistant cladding
  12. fire protection applicationsVan der Aa Brandwerende applicatiesMentioned in Flame barriers protect underside of service walkway in the event of a fire
  13. Slipformed barrierBKB InfraIn this story
  14. clientRijkswaterstaatMentioned in DC power in tunnels is worth considering

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectRottemerentunnel
  • ThemeUnderground construction
  • SubjectUnderground infrastructure
  • CompanyBKB Infra
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.