Concrete structure ‘wrapped’ in aluminium acoustic screens and louvre cladding
Text Roel van GilsImage Aldowa

The concrete structure of the approach ramps to the Rottemerentunnel will be completely concealed by specially formed acoustic screens with aluminium panels, made by Aldowa. The anti-glare louvres in the approach ramps will also be clad with unique diamond-pattern folded sheet metal. A huge job for the metal and composite cladding specialist, which is also taking care of some of the cladding inside the tunnel and on the central tunnel duct.
Aldowa regularly provides cladding for tunnels and other civil engineering structures. Thanks to its experience, construction consortium De Groene Boog asked the company to submit a price for the acoustic screens, louvre cladding and part of the cladding in the Rottemerentunnel. “We ultimately won the tender, mainly because we had a good feeling about it,” says Martien Trouborst, project manager at Aldowa. “Given the tight timescale for getting everything under way, we took the initiative to organise a series of scrum sessions, or intensive design workshops, together with the consortium’s technical staff and the architect. This allowed us to work through the design process very efficiently and find a suitable solution to every challenge.”

Many thousands of panels
Martien says all the parties found the scrum process very positive. “Because you’re sitting together in person, you can discuss every challenge openly and honestly, and you see that, in practice, anything is possible. As a result, we were able to set the standard panel dimensions for the acoustic screens at 1375 by 833 millimetres and start production fairly quickly. That was necessary, too, because this project involves many thousands of perforated panels. And when you know that each panel spends 15 minutes on the punch press, you can imagine how long production takes. We therefore significantly increased production capacity to make the panels.” They are far from standard panels. “A diagonal fold across the panel means that, in plan view, not all the corners are at 90 degrees. The bottom-left and top-right corners effectively point away from each other. So the panel is not square on the punch press, making this a bespoke solution for the project, with no fewer than 15,000 holes in each panel.”

Ready-to-install elements
Aldowa then set up an assembly line to produce elements three panels wide (2.50 metres) and ranging in height from 2.50 metres to 8.50 metres, with acoustic insulation behind them to absorb traffic noise. Martien says: “This allowed us to build up a large buffer and prevent delays during installation. The elements were turned a quarter turn and loaded onto flatbed trailers. One truck served every three trailers, shuttling between our temporary storage facility and the construction site. So the project is also a logistical challenge.” Aldowa is installing around 600 elements in total, with the company handling the engineering, production, assembly and installation itself. “The approach ramp on the south side is now fully clad, and we’ve just started work on the north side.”

Diamond-pattern folded sheet metal
Each of the two approach ramps to the Rottemerentunnel has 24 anti-glare louvres to soften the transition from daylight into the dark tunnel. “They are substantial concrete beams spanning the road. The aluminium cladding around the beams follows the road downwards. The first louvre is the smallest, at 1.7 metres high, while the one closest to the tunnel is no less than 2.7 metres high,” Martien explains. “We are also engineering, supplying and installing the folded aluminium sheet metal for these, in a diamond pattern designed by QWA-architecten. Because there are homes next to the road on the south side, the louvre cladding there is also perforated and fitted with acoustic insulation. On the north side, all the louvres are solid.” Aldowa has now started installing these as well, along with the tunnel cladding for the first 40 metres of the tunnel on both sides.
Question about this story? Ask your question
Who worked on Rottemerentunnel
- construction consortiumDe Groene BoogMentioned in Reinforcement steel for the Rottemeren Tunnel’s underwater concrete floor
- reinforcing steelBCS (Buig Centrale Steenbergen)Mentioned in Reinforcement steel for the Rottemeren Tunnel’s underwater concrete floor
- fire-resistant boardsPromatMentioned in Fire-resistant boards offer the new Rottemerentunnel optimal protection
- De Groene Boog construction consortium
MobilisMentioned in Focus on fit-out works in the Rottemeren Tunnel - lining walls and slatted claddingAldowaIn this story
- architectQWA-architectenIn this story
- installationKaeferMentioned in Rottemerentunnel concrete structure protected with fire-resistant cladding
- fire protection applicationsVan der Aa Brandwerende applicatiesMentioned in Flame barriers protect underside of service walkway in the event of a fire
Keep following this
Get an email when a new story is published. No account needed.
- ProjectRottemerentunnel
- ThemeMaterials and techniques for infrastructure
- SubjectUnderground infrastructure
- CompanyAldowa
- CompanyQWA-architecten



















