Water infrastructure

Wider, deeper and more attractive

De verdiepte ligging is opgesplitst in dertien compartimenten waarin telkens negentien activiteiten in een treintje achter elkaar worden uitgevoerd.
De verdiepte ligging is opgesplitst in dertien compartimenten waarin telkens negentien activiteiten in een treintje achter elkaar worden uitgevoerd.

To accommodate increasing traffic and provide better access to the new and planned residential area, the N206 ir. G. Tjalmaweg between Leiden and Katwijk is being widened and upgraded. Several new structures are also being built. Boskalis Nederland is responsible for designing and constructing the new Tjalmaweg, including ten years of maintenance. Together with Geri de Bijl, project director at Boskalis Nederland, we take a look at this technically challenging project.

The complex interfaces within a very limited footprint make the project particularly challenging.

As part of the RijnlandRoute, the N206 ir. G. Tjalmaweg is a key arterial road for the region, particularly for access to Katwijk. “The existing single-carriageway road could no longer cope with the higher traffic volumes or meet noise standards. In 2019, Zuid-Holland province therefore put out to tender a project to lower the road and double the number of lanes. Boskalis won the contract with the highest MEAT score, particularly for its approach to landscape integration, delivery with local communities in mind and sustainable construction methods,” says De Bijl. “We are building two grade-separated junctions above the sunken road. There will also be a fast cycle route and a green park strip in the so-called Parkzone. In addition, we are building a new bridge alongside the existing Torenvlietbrug and fully upgrading the old bridge over the Oude Rijn. This will also significantly improve traffic flow here, with 2×2 lanes, including a cycle and footpath.”

Sub-projects

Boskalis Nederland has divided the project into four sub-projects. “Sub-project 1 covers upgrading the existing Torenvlietbrug and building a new bridge alongside it,” explains De Bijl. “We are currently building the new bridge, which is structurally similar to the existing Torenvlietbrug but will have a fixed deck. Around the summer construction holiday this year, traffic will be switched to the new bridge, allowing us to upgrade the existing bridge to meet the new standards. The main change is that its movable section will be replaced with a fixed deck. According to the schedule, both bridges will be open to traffic in the first quarter of 2023.” 

Sub-project 2 involved all the preparatory work required before construction of the sunken road could begin. De Bijl: “We installed the necessary surcharge embankments and put in place everything needed to divert existing traffic onto the temporary N206. This included diverting cables and pipes, installing complete siphons, building roundabouts to provide access to the residential area and constructing the temporary provincial road itself. During this phase, the Achterwegviaduct was also demolished and replaced with a temporary 60-metre cycle and pedestrian bridge over both the temporary road and the road under construction. The switch to the temporary N206 went extremely smoothly, and we opened it a month ahead of schedule, at the beginning of August last year.”

19 steps

The most extensive phase is sub-project 3, which involves constructing the new Tjalmaweg below ground level. This work is now in full swing. “We have divided the sunken road into thirteen sections, each involving nineteen activities carried out in sequence. We are working from east (Leiden) to west (Katwijk),” De Bijl explains. “The sunken road is 1,900 metres long, 30 to 50 metres wide and reaches 7 metres below N.A.P. Rather than building a conventional concrete trough, we are using a membrane structure installed in a dry excavation. To create this dry excavation, we drive sheet piles into the ground and install a temporary injection layer down to a depth of 17 metres below ground level.

It is a proven method, although it has never before been used on this scale in the Netherlands. By also making as much use as possible of existing and recycled materials, we can build a highly sustainable structure with a much lower environmental cost indicator (MKI) value.”

Battling the water

Boskalis Nederland expects traffic to be able to use the sunken road by mid-2023. The surrounding road network will then be upgraded and the Parkzone laid out (sub-project 4). Local residents will then experience virtually no disruption from this busy arterial road. In return, they will gain a beautiful natural corridor in the Parkzone, featuring a range of
historical anecdotes, including the ancient Limes Road from Roman times. 

There is still plenty to do before then. “In some places, it really is a battle against the water,” says De Bijl. “There is a great deal of variation in the ground conditions. In two sections, we even had to completely change our working method because of the high water pressure from underlying layers, which disrupts the gel injection layer. This caused water to seep into the excavation. The advantage of working in sections is that this phasing gives us the flexibility to devise appropriate solutions during construction.”

The new Tjalmaweg is therefore a technically very challenging project. “The complex interfaces within a very limited footprint make it particularly challenging, quite apart from the scale of the ground injection works, the high standard of finish, the need to preserve flora and fauna, and the attention we pay to the local community. By keeping stakeholders informed on a regular basis, we reduce the element of surprise and have earned a great deal of goodwill from the local community.” The new N206 ir. G. Tjalmaweg is scheduled for completion in 2023. “This is a fantastic project for Boskalis Nederland, with many challenges, and one we are enjoying working on. Everyone who visits the project can sense the passion and pride we share as we get the job done!” 

Part of the RijnlandRoute

The RijnlandRoute is a new road connection between Katwijk and the A4 near Leiden, via the A44. It includes a new road with a bored tunnel, the N434, and upgrades to sections of the N206 in Leiden and Katwijk. Zuid-Holland province is the client for the RijnlandRoute. The N206 ir. G. Tjalmaweg is one of the RijnlandRoute’s three project sections. www.rijnlandroute.nl

Have a business enquiry for Boskalis Nederland? Get in touch

Who worked on N206 ir. G. Tjalmaweg

  1. clientProvince of South HollandIn this story
  2. membrane structureCofraMentioned in Innovative sealing system offers a high degree of flexibility
  3. main contractorBoskalis NederlandMentioned in Innovative sealing system offers a high degree of flexibility
  4. water-resistant gel layerBE InjectMentioned in Innovative sealing system offers a high degree of flexibility
  5. process controlEnviro Quality ControlMentioned in Innovative sealing system offers a high degree of flexibility
  6. landscaping contractorGako GroenvoorzieningMentioned in A ‘home game’ for landscaping contractor
  7. landscape architectsBoschSlabbersMentioned in A continuous park landscape
  8. supplierPlatowoodMentioned in Seven kilometres of louvred wall
  9. specialist foundation contractorFranki GrondtechniekenMentioned in The Netherlands’ largest ground injection project
  10. road infrastructure designGeoniusMentioned in Creative design within the constraints
  11. specialist foundation contractorVoorbij FunderingstechniekMentioned in A solid foundation for the N206
  12. constructionVoets Gewapende GrondconstructiesMentioned in N206 cutting: pushing the boundaries of reinforced soil
  13. Reinforced earth structureHUESKER NederlandMentioned in N206 cutting: pushing the boundaries of reinforced soil
  14. temporary infrastructureBouwtech BPIMentioned in Temporary medium- and low-voltage infrastructure for the N206

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectN206 ir. G. Tjalmaweg
  • SubjectWater infrastructure
  • CompanyProvince of South Holland
  • CompanyBoskalis Nederland
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.