News

A solid foundation for the N206

Press-in rig with Quattro piler.
Press-in rig with Quattro piler.

As a specialist in the design and execution of all types of foundation work, Voorbij Funderingstechniek is effectively providing the entire load-bearing capacity for the new N206 ir. G. Tjalmaweg. According to Erik Sandifort, project manager at Voorbij Funderingstechniek, a wide range of techniques are being brought together on this project, and in considerable quantities too. 

Sheet piles being installed by vibration using a vibratory hammer.

Boskalis has subcontracted the entire foundation package for the N206 to us, Sandifort begins. “We are carrying out all the foundation work required, both for structures such as the Torenvlietbrug and for the entire sunken section and all the temporary works. The scope ranges from installing precast piles and bored casing piles to combined piles and a huge quantity of sheet piles, including their anchoring. We are also installing some of the injection tubes for Franki Grondtechnieken, for the soil injection work.” 

Noise mitigation measures

All in all, a substantial undertaking, even for a specialist foundation contractor such as Voorbij Funderingstechniek. “We started work on site last November, having begun preparations six months earlier. We were also involved in calculating the detailed design for the sheet piles and anchoring for the sunken section. Without our input, there would have been no structure or sunken section,” Sandifort says jokingly. The foundations for the new Torenvlietbrug over the Oude Rijn were Voorbij Funderingstechniek’s first task on the project. This involved fairly heavy piling with 450 mm square precast piles, some of them installed from a pontoon. However, implementing the noise mitigation measures proved an even greater challenge. “Among other things, we used a large mobile acoustic screen mounted on an auxiliary crane alongside the piling rig.”

The anchor drilling rig on the right and the HSP rig on the left, for installing the injection tubes.

Removing the steel

Voorbij Funderingstechniek then began installing sheet piles in the thirteen compartments of the sunken section. Sandifort: “We started at the Torenvlietbrug end and installed a total of 10,000 tonnes of sheet piles, equivalent to 3,900 pairs of piles and 71,000 m2. To reduce noise, as many of the sheet piles as possible were installed by pressing them in (3,000 tonnes), particularly on the north side of the excavation. Some of them were then vibrated further into the ground because of the high penetration resistance encountered there. We also drilled 1,507 grout anchors, installed the same number of anchor chairs and fitted more than 2,700 linear metres of walings to the sheet piles to keep everything in place after excavation. The good thing is that the steel is being ‘recovered’ too. We have now reached the stage where we are extracting the steel by sonic vibration, apart from the partition walls.”

The first two compartments are already ‘steel-free’. “We are now working in compartments 4 and 5, extracting the sheet piles and removing the anchors. According to the schedule, everything will be out by October and the steel can be used elsewhere. The project is progressing well,” says Sandifort. “We have been able to deploy many of our techniques and build the necessary certified temporary works in our own welding shop. Our welders are also regularly active on site. At peak times, we had as many as 18 welders working at once, along with ten foundation rigs and auxiliary cranes. Even so, we have been able to manage everything with a small project team, thanks in part to the positive collaboration with Boskalis and the lean planning reviewed each week.”   

Een zakelijke vraag aan Voorbij Funderingstechniek? Get in touch

Who worked on N206 ir. G. Tjalmaweg

  1. clientProvince of South HollandMentioned in Wider, deeper and more attractive
  2. membrane structureCofraMentioned in Innovative sealing system offers a high degree of flexibility
  3. main contractorBoskalis NederlandMentioned in Innovative sealing system offers a high degree of flexibility
  4. water-resistant gel layerBE InjectMentioned in Innovative sealing system offers a high degree of flexibility
  5. process controlEnviro Quality ControlMentioned in Innovative sealing system offers a high degree of flexibility
  6. landscaping contractorGako GroenvoorzieningMentioned in A ‘home game’ for landscaping contractor
  7. landscape architectsBoschSlabbersMentioned in A continuous park landscape
  8. supplierPlatowoodMentioned in Seven kilometres of louvred wall
  9. specialist foundation contractorFranki GrondtechniekenMentioned in The Netherlands’ largest ground injection project
  10. road infrastructure designGeoniusMentioned in Creative design within the constraints
  11. specialist foundation contractorVoorbij FunderingstechniekIn this story
  12. constructionVoets Gewapende GrondconstructiesMentioned in N206 cutting: pushing the boundaries of reinforced soil
  13. Reinforced earth structureHUESKER NederlandMentioned in N206 cutting: pushing the boundaries of reinforced soil
  14. temporary infrastructureBouwtech BPIMentioned in Temporary medium- and low-voltage infrastructure for the N206

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectN206 ir. G. Tjalmaweg
  • ThemeUnderground construction
  • SubjectNews
  • CompanyVoorbij Funderingstechniek
Share this article

Advertisement

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.