Trelleborg devises ingenious solution for Selective Extraction IJmuiden Sea Lock walls
Text Suzanne van Gaale Beeld Trelleborg / Rijkswaterstaat

Selective Extraction IJmuiden Sea Lock is a special project that also called on the problem-solving skills of the Design Engineers at Trelleborg Marine & Infrastructure. It was a leap into the unknown that involved a great deal of calculation. Olivier Schuringa, Design Engineer, and Bob Rijnders, Global Sales Manager Water Infrastructure at Trelleborg, explain why their solution is crucial to how the salt barrier works.
The more complex, the better. That is what they like at Trelleborg. “Because,” Olivier explains, “our strength lies in devising solutions to polymer-related problems and challenges.” A good example is a request from Van Hattum en Blankevoort, main contractor for the IJmuiden Salt Barrier: could Trelleborg develop a solution that can accommodate the required forces and rotations, preventing the salt barrier walls from moving in their slots during their service life, while also allowing for the installation and construction tolerances of the screens?

Pushing the limits
“To meet these two requirements, we ultimately came up with a combination of a lifting cushion and a bearing,” Olivier explains. “The bearing accommodates the forces caused by any rotation, for example due to water flow. The lifting cushion bridges the gaps so that the bearing block makes contact.” Throughout the design process, we had to keep pushing the limits of what was both possible to manufacture and practical to use. For example, the lifting cushion and bearing combination had to be as thin as possible, leaving maximum clearance to lower the wall into its slot during installation. At the same time, to accommodate all the forces once the walls were installed, the combination had to be capable of maximum inflation, ensuring that the bearing block makes contact everywhere if all the tolerances build up on one side. In effect, these were two conflicting requirements that we had to find a solution for. The combination we ultimately devised was therefore extensively tested, partly because we wanted to establish exactly which filling compound would be most suitable for the lifting cushion. It had to be possible to inflate it in a controlled way, even underwater, and it had to cure relatively quickly, but not too quickly. It was also essential that the solution worked first time. Once the walls are installed, there is no going back. It also has to last throughout the salt barrier’s service life.”
Collaboration and trust
Looking back on the design process as a whole, Olivier and Bob are proud to have developed a solution to a particularly complex challenge. “Our success was thanks to the good collaboration and the trust Van Hattum en Blankevoort placed in us. The solution is so unique that we have even named it the Van Hattum en Blankevoort bearing.”
Een zakelijke vraag aan Trelleborg Ridderkerk B.V.? Get in touch
Who worked on Selectieve Onttrekking
- construction companyVan Hattum en BlankevoortMentioned in An innovative project for water quality and safety
- main contractorVan Hattum BlankevoortMentioned in Offshore diving experience proves invaluable on Selective Extraction project
- temporary steel structures
Marsé MontageMentioned in Versatile specialist in steel temporary works presses ahead on the Selective Withdrawal