De loopbruggen zijn intussen al een klein jaar in gebruik, de steiger wordt volgens planning eind dit jaar opgeleverd door Beens Groep.
De loopbruggen zijn intussen al een klein jaar in gebruik, de steiger wordt volgens planning eind dit jaar opgeleverd door Beens Groep.

Construction is under way in the Binnenspuikanaal, part of the IJmuiden lock complex, on the Selectieve Onttrekking, an innovative structure that returns salt water to the sea. The project requires existing mooring facilities and waiting berths to be relocated to the southern side of the North Sea Canal. To this end, Beens Groep is building three footbridges and a new jetty structure for Van Hattum en Blankevoort, to high quality standards. 

“We were initially asked to submit a proposal for the jetty,” says Peter Melis, business unit manager at Beens Groep. “Shortly after the contract was awarded, we received a follow-on order to build and install three footbridges. There was also some urgency, as the work had to fit in with the project phasing.” The footbridges connect the new berths for commercial vessels to the mainland, while the jetty will serve as a mooring location for Rijksrederij’s workboats, part of Rijkswaterstaat. These vessels are currently moored at a temporary location.

Thanks to this thorough preparation, installing the footbridges took just three weeks.

From design to construction

Beens Groep is responsible for the design, manufacture and installation of the steel marine structures. “A preliminary design was already available for the footbridges, while for the jetty we had only the functional requirements,” says Maarten Vos, work planner at Beens Groep. “Given the demanding requirements, we paid close attention to the design, planning the work so that on-site activities would be kept to a minimum. This is why we are doing so much prefabrication. The footbridges, each 25 metres long and 1.5 metres wide, have already been assembled and coated in the factory. They were delivered to the site ready for installation and could therefore be fitted straight onto the tubular piles and substructure we had installed earlier. Thanks to this thorough preparation, installation took just three weeks.”

The jetty structure is an impressive feat in terms of its configuration and dimensions, particularly as it is also being built to be fully demountable.

Demountable

The jetty structure is considerably more complex. It is 100 metres long and 4 metres wide, and includes a platform where a lorry-mounted crane can deploy its outriggers. “It is an impressive feat in terms of its configuration and dimensions, particularly as the structure is also being built to be fully demountable,” says Peter. “That was an additional requirement from Rijkswaterstaat, both in the interests of circularity and to ensure that, in the event of a collision, only one section would need to be replaced.” Because the structure is demountable, Beens Groep has kept the number of welded connections to a minimum. Maarten explains: “We will still be doing some welding on site, mainly to accommodate tolerances in the 33 tubular piles we installed earlier. We will do this using an oversized flange, which will be welded in place on site.”

Beens Groep is using its largest pontoon, fitted with a 110-tonne crane, and its largest workboat to build the jetty.

High quality 

The jetty has a particularly slender profile. “That is thanks to the unique substructure,” says Peter. “Normally, you stack the transverse and longitudinal beams on top of each other; here, they are integrated.” Maarten adds: “We are also using special 10-centimetre-high ‘open grating’ in the area where the lorry-mounted crane needs to deploy its outriggers. The longitudinal section, where the crane will not be operating, will have 5-centimetre grating, but even that can easily support the weight of a car.” The entire structure, including both the jetty and the footbridges, is subject to high quality standards, including level 1.4 of the Richtlijnen Ontwerp Kunstwerken (ROK).

The jetty was delivered to IJmuiden as a kit of parts in fifteen numbered sections. “The installation may look like a simple job, but it is anything but,” says Richard de Boer, site supervisor at Beens Groep. “We are using our largest pontoon, fitted with a 110-tonne crane, and our largest workboat. It takes a carefully coordinated effort between people and machinery. Once the sections have been installed, we will fit all the utility services on the jetty and build a small storage room and workshop for Rijkswaterstaat’s workboats.” The footbridges have now been in use for almost a year. Beens Groep is on schedule to complete the jetty by the end of this year.   

Question about this story? Ask your question

Who worked on Selectieve Onttrekking

  1. construction companyVan Hattum en BlankevoortMentioned in An innovative project for water quality and safety
  2. dredgingVan den HerikMentioned in A feat of civil engineering by concrete specialist
  3. main contractorVan Hattum BlankevoortMentioned in Offshore diving experience proves invaluable on Selective Extraction project
  4. steel suppliesArcelorMittalMentioned in Sustainable steel
  5. supply of skilled workersEmployMentioned in A strong shared commitment to safety
  6. clientRijkswaterstaatMentioned in A strong shared commitment to safety
  7. temporary steel structuresMarsé MontageMentioned in Versatile specialist in steel temporary works presses ahead on the Selective Withdrawal
  8. lifting cushion and bearingTrelleborgMentioned in Trelleborg devises ingenious solution for Selective Extraction IJmuiden Sea Lock walls

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectSelectieve Onttrekking
  • SubjectWater infrastructure
Share this article

Advertisement

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.