High-quality marine structures
Text Roel van GilsImage Beens Groep

Construction is under way in the Binnenspuikanaal, part of the IJmuiden lock complex, on the Selectieve Onttrekking, an innovative structure that returns salt water to the sea. The project requires existing mooring facilities and waiting berths to be relocated to the southern side of the North Sea Canal. To this end, Beens Groep is building three footbridges and a new jetty structure for Van Hattum en Blankevoort, to high quality standards.
“We were initially asked to submit a proposal for the jetty,” says Peter Melis, business unit manager at Beens Groep. “Shortly after the contract was awarded, we received a follow-on order to build and install three footbridges. There was also some urgency, as the work had to fit in with the project phasing.” The footbridges connect the new berths for commercial vessels to the mainland, while the jetty will serve as a mooring location for Rijksrederij’s workboats, part of Rijkswaterstaat. These vessels are currently moored at a temporary location.

From design to construction
Beens Groep is responsible for the design, manufacture and installation of the steel marine structures. “A preliminary design was already available for the footbridges, while for the jetty we had only the functional requirements,” says Maarten Vos, work planner at Beens Groep. “Given the demanding requirements, we paid close attention to the design, planning the work so that on-site activities would be kept to a minimum. This is why we are doing so much prefabrication. The footbridges, each 25 metres long and 1.5 metres wide, have already been assembled and coated in the factory. They were delivered to the site ready for installation and could therefore be fitted straight onto the tubular piles and substructure we had installed earlier. Thanks to this thorough preparation, installation took just three weeks.”

Demountable
The jetty structure is considerably more complex. It is 100 metres long and 4 metres wide, and includes a platform where a lorry-mounted crane can deploy its outriggers. “It is an impressive feat in terms of its configuration and dimensions, particularly as the structure is also being built to be fully demountable,” says Peter. “That was an additional requirement from Rijkswaterstaat, both in the interests of circularity and to ensure that, in the event of a collision, only one section would need to be replaced.” Because the structure is demountable, Beens Groep has kept the number of welded connections to a minimum. Maarten explains: “We will still be doing some welding on site, mainly to accommodate tolerances in the 33 tubular piles we installed earlier. We will do this using an oversized flange, which will be welded in place on site.”

High quality
The jetty has a particularly slender profile. “That is thanks to the unique substructure,” says Peter. “Normally, you stack the transverse and longitudinal beams on top of each other; here, they are integrated.” Maarten adds: “We are also using special 10-centimetre-high ‘open grating’ in the area where the lorry-mounted crane needs to deploy its outriggers. The longitudinal section, where the crane will not be operating, will have 5-centimetre grating, but even that can easily support the weight of a car.” The entire structure, including both the jetty and the footbridges, is subject to high quality standards, including level 1.4 of the Richtlijnen Ontwerp Kunstwerken (ROK).
The jetty was delivered to IJmuiden as a kit of parts in fifteen numbered sections. “The installation may look like a simple job, but it is anything but,” says Richard de Boer, site supervisor at Beens Groep. “We are using our largest pontoon, fitted with a 110-tonne crane, and our largest workboat. It takes a carefully coordinated effort between people and machinery. Once the sections have been installed, we will fit all the utility services on the jetty and build a small storage room and workshop for Rijkswaterstaat’s workboats.” The footbridges have now been in use for almost a year. Beens Groep is on schedule to complete the jetty by the end of this year.
Question about this story? Ask your question
Who worked on Selectieve Onttrekking
- construction companyVan Hattum en BlankevoortMentioned in An innovative project for water quality and safety
- main contractorVan Hattum BlankevoortMentioned in Offshore diving experience proves invaluable on Selective Extraction project
- temporary steel structures
Marsé MontageMentioned in Versatile specialist in steel temporary works presses ahead on the Selective Withdrawal - lifting cushion and bearing
TrelleborgMentioned in Trelleborg devises ingenious solution for Selective Extraction IJmuiden Sea Lock walls
Keep following this
Get an email when a new story is published. No account needed.
- ProjectSelectieve Onttrekking
- SubjectWater infrastructure