Water infrastructure

Waaldijk fails flood safety standards

Om overstromingen in Nederland te voorkomen, worden tot 2050 in heel Nederland ruim 1.500 kilometer aan dijken en 500 sluizen en gemalen versterkt.
Om overstromingen in Nederland te voorkomen, worden tot 2050 in heel Nederland ruim 1.500 kilometer aan dijken en 500 sluizen en gemalen versterkt.

The Waaldijk between Wolferen (Overbetuwe) and Sprok (Nijmegen) no longer meets the statutory standards for flood safety. The 2016 assessment found that only part of the dike failed to meet the standards, but the introduction of the new standards in 2017 substantially increased the scale of the task. Waterschap Rivierenland is responsible for making the entire dike between Wolferen and Sprok safe against flooding again by 2026.

The 2016 assessment found that only part of the dike failed to meet the standards, but the introduction of the new standards in 2017 substantially increased the scale of the task.

Managers of the Netherlands’ primary flood defences must report to the minister every twelve years on the general condition of these defences. “As a water authority, we are responsible for the flood safety of the dikes in our area, which are assessed once every twelve years,” says Bram de Fockert, project manager at Waterschap Rivierenland. “The Waaldijk between Wolferen and Sprok is one of them, and the 2016 assessment found that it was not entirely safe. ‘Not safe’ means not safe in the longer term. The assessment therefore looks ahead. If high water occurs now, it will not pose an immediate problem.”

Flood Protection Programme 

The 2016 assessment was still based on the standards in force at the time. “It showed that ‘only’ just under three kilometres of the 13-kilometre dike section would need to be strengthened,” De Fockert explains. “During the planning process, we had to deal with stricter standards for primary flood defences, which came into force on 1 January 2017. Naturally, we anticipated this as a water authority. Under the new standards, the entire section between Wolferen and Sprok failed on several failure mechanisms. This has a considerable impact, including on all the other primary flood defences in our area.” The Wolferen to Sprok dike reinforcement is part of the Flood Protection Programme. To prevent flooding in the Netherlands, more than 1,500 kilometres of dikes and 500 locks and pumping stations are to be strengthened across the country by 2050. This is a major undertaking, including for Waterschap Rivierenland, which must strengthen more than 400 kilometres of dikes by 2050, including around 70 kilometres of the northern Waaldijk. “The section between Wolferen and Sprok must be brought up to standard by 2026.” 

Sustainability

The entire length of the dike section between Wolferen and Sprok is being upgraded for height and stability. Measures are also being taken to prevent piping. De Fockert says: “We started the exploration phase in early 2016 to identify a preferred option. We then moved into the planning phase, deliberately bringing a contractor on board at an early stage to draw on its construction expertise as soon as possible. The intention was also to proceed to construction with that consortium.” Sustainability was an important consideration in developing the plan. “For example, extensive trials were carried out with plastic piping screens, which we are now actually using. Research was also conducted into an emissions-free construction site. During the planning phase, we examined hypothetically what it would entail to deliver a project of this kind entirely emissions-free. A detailed report was produced, which the Flood Protection Programme is now using to establish a framework for, among other things, subsidising emissions-free equipment. What is encouraging is that the construction consortium is already willing to invest in advance, for example in using an electric excavator.”

“As a water authority, we were very pleased with this kind of process involving an integrated design team. We worked together as partners, with openness and transparency, to develop a sound plan and a construction contract in which the risks were properly managed.” Since construction began in the summer of 2021, however, the relationship has once again been that of client and contractor, according to De Fockert. “That is almost inevitable. As the client, we have an oversight role. Even so, we have agreed to maintain our collaborative and transparent approach throughout construction. That means keeping each other well informed, identifying potential issues early and addressing them so that escalation can be avoided. So far, that approach is paying off.” 

Question about this story? Ask your question

Who worked on Dijkversterking Wolferen Sprok

  1. contractorCombinationMentioned in What lies beneath the ground we build on?
  2. clientWaterschap RivierenlandMentioned in What lies beneath the ground we build on?
  3. contractorPloegamMentioned in What lies beneath the ground we build on?
  4. contractorDura VermeerMentioned in What lies beneath the ground we build on?
  5. geo-data specialistFugroMentioned in Fugro expertise helps put dikes on a firm footing
  6. construction consortiumGMBMentioned in Fugro expertise helps put dikes on a firm footing
  7. adviserDeltaresMentioned in Fugro expertise helps put dikes on a firm footing
  8. sheet pile supplierArcelorMittalMentioned in Sustainable steel sheet piles made from scrap
  9. construction consortiumDe Betuwse Waard construction consortiumMentioned in A modern take on a proven concept
  10. anchoring of the steel sheet pile wallDe Vries TitanMentioned in Expertise required to install grout injection anchors

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDijkversterking Wolferen Sprok
  • SubjectWater infrastructure
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.