Multifunctional, sustainable steel sheet piles
Text Roel Bijlard Image Dijkalliantie Neder-Betuwe

The Neder-Betuwe dike reinforcement project is a major water safety initiative along the north bank of the Waal, from Tiel to Wely. This 20.2-kilometre stretch lies between earlier dike reinforcement projects, including Tiel-Waardenburg, Stad Tiel and Wolferen-Sprok, which have already been successfully reinforced with steel sheet piles in recent years. Steel once again plays a key role in the current project: almost 11 kilometres of the dike will be reinforced with sheet piles, across several dike sections and in three sub-projects over a five-year period.
The work is being carried out by Dijkalliantie Neder-Betuwe, a partnership between GMB, Ploegam and Dura Vermeer. The project is characterised by a strong focus on tailored solutions, as conventional approaches alone, such as large-scale dike reinforcement using soil, are often not feasible. Steel sheet piles provide an efficient, space-saving solution.

The essential role of steel sheet piles
Sheet piles serve a dual purpose in dike reinforcement. They protect the dike against two critical failure mechanisms: piping and macro-stability failure. Piping occurs when water flows beneath the dike and carries sand with it, potentially weakening the flood defence. The sheet pile lengthens or interrupts the flow path, preventing sand-carrying boils from forming. At the same time, the sheet pile contributes to stability by acting as a robust structure that withstands forces within the dike. In some locations, it also serves directly as a measure to prevent burrowing damage by beavers. This means a single measure can address the entire reinforcement challenge within the existing dike profile, without significant impact on homes, infrastructure or the surrounding area.
The project requires a substantial quantity of steel, more than 30,000 tonnes, in several steel sheet pile sections. The mix comprises AZ18-700, AZ24-700 and AZ26-700 sections, ranging in length from 8 to 16 metres. Depending on the location, the sheet piles are installed by vibration or pressing. Around 50% are installed using low-vibration methods, with a silent piler or leader-guided pressing technique. This is important close to buildings, where limiting vibration is essential, and also more broadly from an ecological perspective.
Logistics and phasing
The work is divided into three sub-projects, with deliveries by ship for each. This ensures that the large quantities of steel are transported to the project area efficiently and sustainably. The first delivery for sub-project 1 took place in December 2025, using three inland vessels, followed by a second delivery of three vessels in July 2026. A third delivery will follow at a later stage. By taking sheet piles into storage early, the consortium gains flexibility in carrying out the work and effectively limits risks in a volatile market.

Sustainability as a core principle
Sustainability is a key principle of the project. Emissions from installation on site are reduced by using electric equipment. Together with the choice of EcoSheetPile™ steel sheet piles and transport to the site by inland vessel, this contributes to the project’s overall sustainability. The sheet piles are produced in Luxembourg using an electric arc furnace and approximately 100% recycled steel. This results in a substantial reduction in CO2 emissions: 423 kg CO2 per tonne of steel, compared with 2,200-2,500 kg CO2/t for blast furnace steel. This footprint is documented in the updated EcoSheetPile™ EPD.
The Neder-Betuwe dike reinforcement project demonstrates the key role steel sheet piles play in modern water engineering projects. Their ability to address piping and macro-stability failure at the same time, their efficient use in confined spaces and their favourable sustainability profile make them a robust, future-proof solution. Combined with smart logistics and low-emission construction, Dijkalliantie is delivering a dike ready to meet the challenges of climate change and increasing river flows.
A business enquiry for GMB? Get in touch
Who worked on Dijkversterking Neder-Betuwe
- contractorconstruction company J. den BoerMentioned in Strategic clay extraction speeds up sustainable dike reinforcement
- constructionPloegamIn this story
- constructionDura VermeerIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectNeder-Betuwe dyke reinforcement
- ThemeFlood protection and climate-resilient water management
- SubjectWater infrastructure
- CompanyGMB
- CompanyPloegam
- CompanyDura Vermeer