Three ‘foundation projects’ to build a single pumping station

During the tender, Gebr. van ’t Hek was approached by the Van Hattum en Blankevoort and Friso Civiel construction consortium to help plan how to execute the foundation design for the Monnickendam pumping station. The foundation specialist is based in the region and knows the local ground conditions extremely well. This has proved a definite advantage on this unusual project, which is characterised by numerous challenges and three different cofferdams.
Gebr. van ’t Hek is responsible for the complete foundation package for the new pumping station. “We started designing the three cofferdams back in late 2019: the outlet side, the inlet side and the road cofferdam,” says project manager Dennis Jonges. “The road cofferdam is directly beneath the N247, while the inlet and outlet sides are on either side of the provincial road. Each cofferdam is formed by driving precast concrete piles and installing a sheet-pile enclosure with a two-tier bracing frame. However, we began by installing temporary sheet piles to provide surcharge loading on the outlet and inlet sides. Some of this work was carried out from a pontoon.”

Major weekend works
To build the road cofferdam, a large number of cables and pipes first had to be relocated. Gebr. van ’t Hek installed 2 x 2 double sheet piles on either side of the N247 for this purpose. “A cable duct has since been installed on these, carrying the relocated cables and pipes,” Jonges explains. “We then drove the piles and sheet piles for the outlet-side cofferdam. Next came the road cofferdam. Over two weekends, while the N247 was closed, we drove the sheet piles and piles, installed the first tier of the bracing frame, and fitted the edge walings, which are now beneath the road cofferdam’s temporary steel support bridge. After these major works, which went very smoothly, we continued without interruption on the inlet side, driving the concrete piles and sheet piles. The second tier of the bracing frame in
the three cofferdams was initially scheduled for late 2021, but was significantly delayed by an archaeological find in the embankment. Remains of an old sea lock were found, pierced by the ‘newly’ installed concrete piles.”

Complex work
The archaeological find is currently being carefully surveyed and documented. Gebr. van ‘t Hek expects to resume work at the end of February. “We will then continue installing the bracing frames, in close consultation and coordination with all the parties involved, including the archaeologists and earthworks teams,” Jonges explains. “It makes the work more involved than originally envisaged, but we are finding a way to accommodate that too. Once the bracing frames are in place, the cofferdams can be excavated to depth and the consortium can start the concrete work. Once the concrete floor has cured, we will return to remove the bracing frames and extract the sheet piles.” For Gebr. van ‘t Hek, the project as a whole involves around 1,400 tonnes of sheet piling, from AZ 18700 to AZ 36700, in pile lengths of 18 to 22 metres, as well as more than 130 square 45 and square 40 concrete piles in lengths ranging from 18 to 20 metres. “All in all, it is a great project with plenty of challenges, and it is right here in our neighbourhood. That makes it extra special.”
A business enquiry for Friso Civiel? Get in touch
Who worked on Gemaal Monnickendam
- contractors' joint venture
Friso CivielMentioned in Monnickendam pumping station: A remarkable feat beneath the surface - contractors' joint ventureVan Hattum en BlankevoortMentioned in Monnickendam pumping station: A remarkable feat beneath the surface
- clientHoogheemraadschap Hollands NoorderkwartierMentioned in Monnickendam pumping station: A remarkable feat beneath the surface
- NoNOx filtersVolkerWesselsMentioned in Monnickendam pumping station: A remarkable feat beneath the surface
- fish-friendly pumping station pumps
Pentair Fairbanks NijhuisMentioned in Fish-friendly pumping station pumps - gate valves and non-return valvesHC Waterbeheersing BVMentioned in Large spindle-operated penstocks and flap valves
- foundation specialistGebr. van ’t HekIn this story
- research agencyVestigia Archeologie & CultuurhistorieMentioned in Uncovering the layers of a centuries-old dam
Keep following this
Get an email when a new story is published. No account needed.
- ProjectMonnickendam pumping station
- ThemeFlood protection and climate-resilient water management
- SubjectWater infrastructure
- CompanyGebr. van ’t Hek
- CompanyFriso Civiel