Building and installing the rolling gate for the Kornwerderzand storm surge barrier

Designing and building the 60-metre-long rolling gate for the storm surge barrier at Kornwerderzand takes more than precision work. How do you allow for tolerances? And how do you position a 950-tonne gate on the rails to the nearest centimetre? Project engineer Pieter Woudenberg and project manager Edwin Schepers explain how they went about it.

Two completely new storm surge barriers are being built at Den Oever and Kornwerderzand. They will protect the hinterland against extreme high water. The storm surge barrier at Kornwerderzand consists of a rolling gate that can be moved across a sill in the navigation channel. HSM Steel Structures was appointed to build and install the rolling gate at Kornwerderzand. Woudenberg explains how the rolling gate works: “When a storm is forecast, the rolling gate is moved into the navigation channel. During a storm, high water on the Wadden Sea side will press the gate against the concrete under the force of the water, allowing it to hold back the water completely.”

The enormous structure weighs 950,000 kilograms, is 56 metres wide and 15 metres high.

In-house yard

The rolling gate weighs 950,000 kilograms, is 56 metres wide and 15 metres high. HSM Steel Structures built the enormous structure at its own yard in Schiedam. Woudenberg says: “We specialise in large civil engineering projects. Our site is fully equipped for them, and we have access to open water. We therefore always try to make the components as large as possible, so that they can be installed efficiently at their final destination in a single operation, with as little disruption as possible. HSM has already built several bridges over 200 metres long in their entirety at our site, then installed them at their full length at the project location.”

Millimetre precision

The challenge in the design was achieving accuracy. “We are dealing with a large structure where tolerances have to be measured in millimetres. The interfaces are the most important part. The steel gate must fit seamlessly against the concrete and hold back the water completely when closed. There is a lot of welding involved. The heat from welding causes the material to deform. We took this into account from the design stage and throughout the construction process. For example, you have to take measurements continuously during construction and build in pre-formed moulds. In the design, welds are kept as small as possible, which reduces heat input and therefore deformation.”

HSM Steel Structures built the enormous structure at its own yard in Schiedam.

Winch system

According to Schepers, the design is unique. “The rolling gate rests on two bottom roller carriages and is moved by a winch system. The sheave beam is connected to the rolling gate, and the winch cables are reeved through it to move the gate. The winch system consists of two cables: a closing cable to pull the rolling gate into the navigation channel, and an opening cable to pull it into the gate chamber. The bottom roller carriages run on rails embedded in the concrete. The rolling gate is fitted with a jet system that sprays the rails clean to remove mud and other large objects.”

The tension mounts

The complete structures, including the rolling gate and its operating machinery, have been thoroughly tested and are ready for transport. The rolling gate has been built in its entirety and will be transported by sea on a heavy-lift barge to the Afsluitdijk. Schepers says: “We’ll have everything we need on hand to lift the gate into position. This has to be done within two days, because the navigation channel will need to be closed.” The lifting operation is another tense moment. It has to be accurate to the centimetre. “The gate has to sit exactly on the bottom roller carriages, each weighing 40 tonnes. We’re already preparing for that. Because we’ve fully planned, tested and prepared everything at our yard, we expect to carry out the installation smoothly on site in March 2023. Then we just need the weather to cooperate.”     

Een zakelijke vraag aan HSM Steel Structures BV? Get in touch

Who worked on Keersluis Den Oever

  1. construction consortiumLevvelMentioned in Guide structures must prevent collisions with ships
  2. main driveDemakoMentioned in Rail-wheel design for the main drive of the navigation lock
  3. design teamHSMMentioned in Rail-wheel design for the main drive of the navigation lock

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectKeersluis Den Oever
  • SubjectWater infrastructure
  • CompanyHSM Steel Structures BV
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.