ArcelorMittal optimises sheet pile use on the Tiel-Waardenburg dike reinforcement project
Text Roel van GilsImage Paul Poels fotografie

Under the motto ‘working together, smartly and to strengthen’, construction consortium Mekante Diek is reinforcing the dike between Tiel and Waardenburg over a length of approximately 19 kilometres. The approach centres on working together to find sustainable solutions. ArcelorMittal was therefore brought on board at an early stage to identify ways to optimise sheet pile use, with great success. It is also the first project in the Netherlands to use EcoSheetPile™ Plus, a sheet pile product made from scrap steel using 100% green electricity.
“We joined Mekante Diek’s design team quite soon after the contract was awarded, to look at ways of optimising sheet pile use at a high level,” says Roel Bijlard of ArcelorMittal. Steel sheet piles are ideally suited to this type of dike reinforcement project, as they eliminate two failure mechanisms in one go: piping and macro-instability. “The main aim of this early collaboration is to reduce the total weight of the sheet pile solution. Using less steel in the ground not only saves costs, but also delivers substantial savings in terms of sustainability and CO2 emissions.”

Much lower environmental impact
The greatest gains in optimising sheet pile use were achieved by using stepped lengths. “In other words, combining a long pile, say 16 metres, with a shorter one of 12 metres, and alternating between them,” Roel explains. “The longer sheet pile provides the required stability, while the shorter one creates a continuous wall. We can apply this optimisation at various locations on the Tiel-Waardenburg project. It delivers substantial savings.” In addition to optimising the weight, ArcelorMittal is making another important contribution to the project’s sustainability. “For the first time in the Netherlands, we are producing and supplying our EcoSheetPile™ Plus sheet piles here. As with the standard EcoSheetPile™, the steel in the Plus version is produced in an electric arc furnace using around 100% scrap. This alone results in a much lower environmental impact of 427 kg CO2 per tonne, compared with steel from a blast furnace, which accounts for around 2,000-2,500 kg CO2 per tonne. With the EcoSheetPile™ Plus version, we also guarantee that the steel is made using 100% green electricity, reducing the impact further to 359 kg CO2 per tonne.”

EPDs
New EPDs for both versions of EcoSheetPile™ have been available since April 2023. “Because we were part of Mekante Diek’s design team, we were able to offer EcoSheetPile™ Plus ahead of their publication. This meant Mekante Diek could work with very favourable figures of +/-50 kg CO2 per m2 of wall. That really does make a difference,” says Roel with justified pride. “We also ensure that transport is as sustainable as possible. The sheet piles are transported from the factory in Luxembourg to the project site by inland waterway vessel.” ArcelorMittal has now supplied around 3,000 tonnes, with a further 1,500 tonnes due to be delivered this year. The entire project comprises 18,000 tonnes of EcoSheetPile™ Plus, mainly AZ24-700 sheet piles ranging from 12 to 18 metres in length. The remaining tonnage will be delivered and installed in phases up to 2025.
Depending on local conditions, the sheet piles are installed by vibration or pressing. The guiding principle is: vibrate where possible, press where necessary. “Not everything is decided in advance,” says Roel. “On certain sections of the route, the installation method is determined on site during construction. For these locations, we supply sheet piles that can be installed using either method. Another fine example of working together, smartly and to strengthen.”
Een zakelijke vraag aan ArcelorMittal Projects Europe B.V.? Get in touch
Wie aan Dijkversterking Tiel-Waardenburg werkte
- geo-data specialist
FugroMentioned in Geo-data specialist plays prominent role in sustainable dike reinforcement - construction consortiumMekante DiekMentioned in Geo-data specialist plays prominent role in sustainable dike reinforcement
- temporary bridge elements
Retro BridgeMentioned in Laad- en losplatform van tijdelijke RHB-brugelementen - conversion
Van den HeuvelMentioned in Gebr. De Koning installs 9 kilometres of sheet piling with zero emissions - constructionGebr. De KoningMentioned in Gebr. De Koning installs 9 kilometres of sheet piling with zero emissions
- construction consortiumBouwcombinatie Mekante DiekMentioned in Gebr. De Koning installs 9 kilometres of sheet piling with zero emissions
- electric drive systemeQuipMentioned in Gebr. De Koning installs 9 kilometres of sheet piling with zero emissions
- clay suppliesAannemingsbedrijf J. den BoerMentioned in 200,000 tonnes of high-quality clay for dykes
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDijkversterking Tiel-Waardenburg
- ThemeFlood protection and climate-resilient water management
- SubjectWater infrastructure
- CompanyArcelorMittal Projects Europe B.V.