Water infrastructure

200,000 tonnes of high-quality clay for dykes

Text Roel van GilsImage Aannemingsbedrijf J. den Boer

De dijkenklei die voor project Dijkversterking Tiel-Waardenburg wordt ingezet is afkomstig van projectgebied Geertjesgolf.
De dijkenklei die voor project Dijkversterking Tiel-Waardenburg wordt ingezet is afkomstig van projectgebied Geertjesgolf.

Large quantities of clay are usually needed to bring a dyke back up to standard as part of a reinforcement project. It is no surprise, then, that Aannemingsbedrijf J. den Boer, with several clay extraction concessions across the country, is called on for many dyke reinforcement projects. One such project is the reinforcement scheme between Tiel and Waardenburg, where the company is working for construction consortium Mekante Diek, comprising Ploegam, Dura Vermeer and Van Oord.

The Waal dike is familiar territory for Aannemingsbedrijf J. den Boer. “We’ve been supplying clay along the stretch between Gorinchem and Waardenburg for several years,” says director Ton Kuijs. “Contractors know they can count on us for high-quality clay for dykes, and that is needed on every reinforcement project. On the stretch between Tiel and Waardenburg, we’re not only supplying clay for dykes, but also deploying our BJ1 unloading pontoon so the clay can be transferred onto the right transport vehicles.”

Our tipper trucks have a steered rear axle, allowing them to turn and tip at a very tight angle, perpendicular to the dike.

Geertjesgolf

The clay for the Tiel-Waardenburg Dike Reinforcement project comes from the Geertjesgolf project area, a large sand extraction site between the Ewijk interchange (A50 and N322) and the villages of Deest and Winssen. “Clay, sand and gravel are extracted sustainably in this area for use as construction materials. The clay is of very high quality, making it suitable for use in dykes,” Ton explains. “The 200,000 tonnes of clay meet erosion class 1 requirements, are all clean soil and are being delivered in stages. We unload around 3,000 tonnes of clay a day using our crawler excavator with an extended boom. The clay is then transported further into the project area by the consortium’s trucks.”

Safe clay transport 

Through its sister company Reductum, J. den Boer is fully equipped to transport clay efficiently and safely. “Our tipper trucks have a steered rear axle, allowing them to turn and tip at a very tight angle, perpendicular to the dike,” Ton explains. “That makes things easier for the contractor and safer too, especially on dikes where there is usually little room on top. The truck is also hydraulically levelled before tipping, which improves safety. The plastic lining in the tipper body also helps, preventing clay from sticking to the headboard. Clay stuck to the headboard makes the truck top-heavy, with all the risks that entails. Fortunately, this is receiving more attention.” Ton also proudly explains that the first two electric trucks have been purchased and will eventually be deployed on dike reinforcement projects.

Tackling a project, including a dyke reinforcement scheme, safely and efficiently with high-quality equipment is what Aannemingsbedrijf J. den Boer and Transportbedrijf Reductum stand for, Ton concludes. “And we’ll be busy for some time yet. Geertjesgolf still has well over 1.5 million tonnes of clay for dykes, enough to supply several dyke reinforcement projects in the coming years.” 

Question about this story? Ask your question

Wie aan Dijkversterking Tiel-Waardenburg werkte

  1. geo-data specialistFugroMentioned in Geo-data specialist plays prominent role in sustainable dike reinforcement
  2. construction consortiumMekante DiekMentioned in Geo-data specialist plays prominent role in sustainable dike reinforcement
  3. soil consultancy firmDiseoMentioned in Diseo provides soil advice where land meets water
  4. adviserExplosive Clearance GroupMentioned in ECG is right at home on the flood defences
  5. temporary bridge elementsRetro BridgeMentioned in Laad- en losplatform van tijdelijke RHB-brugelementen
  6. conversionVan den HeuvelMentioned in Gebr. De Koning installs 9 kilometres of sheet piling with zero emissions
  7. constructionGebr. De KoningMentioned in Gebr. De Koning installs 9 kilometres of sheet piling with zero emissions
  8. construction consortiumBouwcombinatie Mekante DiekMentioned in Gebr. De Koning installs 9 kilometres of sheet piling with zero emissions
  9. electric drive systemeQuipMentioned in Gebr. De Koning installs 9 kilometres of sheet piling with zero emissions
  10. clay suppliesAannemingsbedrijf J. den BoerIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDijkversterking Tiel-Waardenburg
  • ThemeFlood protection and climate-resilient water management
  • SubjectWater infrastructure
  • CompanyAannemingsbedrijf J. den Boer
  • CompanyVan Oord
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.