The N241, better known as the A.C. de Graafweg, is set for a major overhaul in the coming years. Iv-Infra is playing a key role in the project. The engineering consultancy is responsible for the project’s full as-built survey and for updating and expanding the geographic information system (GIS). Michel Ham, project manager at Iv-Infra, is responsible for the as-built survey and for updating the asset data GIS database for the province of North Holland. The work will be carried out in two phases. Iv-Infra’s work will also take place after each of these phases.

An as-built survey is essentially a complete review, explains Ham: “We record every change in detail. For example, green areas, asphalt areas, and separate layers for culverts and manholes. In principle, each object has its own layer. The province of North Holland has defined the geometric and attribute requirements in advance. The province is actually a frontrunner in this area. The GIS database is very extensive.”

Iv-Infra follows several steps on this project. The new situation is mapped using its own advanced 3D scanning vehicle. This takes 360-degree photographs of the site and generates a point cloud. “We can use that to map the new situation. Cables, pipelines, structures, asphalt and green space data: all that information is collected first. In short, first the surveying, then the GIS work.”

Ham confirms that the Haarlem-based engineering consultancy was brought in for this project because of its specialist and extensive expertise. “We have an edge when it comes to automation and digitalisation. It’s up to us to maintain that lead.” The project manager is referring, among other things, to the use of Feature Manipulation Engine (FME) software. This is used to streamline all collected data between geometric and digital formats. The software is designed specifically for GIS systems and computer-aided design software, such as AutoCAD. 

Asset data: data on all existing objects, surfaces, green areas, asphalt, etc.

High standards

The complete review and data collection are carried out with great precision and thoroughness, meeting the client’s exacting requirements. The client, the Province, is responsible for managing the N241 and therefore also for the GIS database. 

These requirements go beyond those that apply to the process as a whole: the so-called BGT requirements. BGT stands for Basic Registration of Large-Scale Topography. All data holders, such as municipalities, water authorities, provinces and Rijkswaterstaat, can consult these maps, so they must always be up to date. Which section of road was built when? What does this green strip consist of, when was a particular culvert installed, and where do the cables for traffic signal installations run? The North Holland GIS database is even more detailed, thanks in part to Iv-Infra’s expertise. 

“For this kind of work, it’s important to ensure there are no gaps or overlaps between the areas,” Ham continues. “For example, there must be none in a paved area at a bypass. There must also be no gaps or overlaps between a hard shoulder and a verge. With the software mentioned above and the expertise of our GIS consultants, we can map, check and deliver this accurately.”

Iv-Infra’s work is still to get under way, although preparations are, of course, already in progress. The client has made it clear what needs to be done and which requirements must be met. 

Collaboration is crucial

“To meet these standards, we have to adapt our tools every year. That makes this work challenging too, because naturally we want to stay at the forefront,” says Ham. He sees the variety of the work as one of its most rewarding aspects. “It’s great to bring different disciplines together: surveying, working with GIS and meeting with Boskalis to provide data. Consultation and communication are crucial, both with Boskalis and with the Province. We depend on one another. That collaboration is rewarding.”

The reconstruction of the A.C. de Graafweg (N241) is a multi-year project. The drinking water transmission main is currently being relocated, and work on the cables and pipelines is starting. The provincial road is expected to be completed by mid-2025. The as-built survey and collection of the new GIS data are expected to begin in 2024.     

Have a business enquiry for Boskalis Nederland? Get in touch

Who worked on A.C. de Graafweg

  1. construction teamBoskalisMentioned in N241: awarded on the basis of collaboration
  2. clientProvince of North HollandMentioned in N241: awarded on the basis of collaboration
  3. clientPWNMentioned in N241: awarded on the basis of collaboration
  4. engineering consultancySwecoMentioned in N241: awarded on the basis of collaboration
  5. rerouting the pipelineVan Baarsen BuisleidingenMentioned in N241: awarded on the basis of collaboration
  6. clientProvinciaal Waterleidingbedrijf N.V. (PWN)Mentioned in Making a difference through collaboration
  7. asphalt millingAducoMentioned in Maximum efficiency through selective asphalt milling
  8. engineering consultancyIv-InfraIn this story
  9. temporary traffic measuresVisscher TrafficMentioned in A key role in temporary traffic management
  10. earthworksJimmink KolhornMentioned in Flexible approach to major earthworks
  11. geotechnical engineering consultancyIngenieursbureau BT GeoconsultMentioned in Dual role for geotechnical engineering firm
  12. directional drillingVan VulpenMentioned in Relocating and upgrading a drinking water transmission main
  13. full-service installerKo Hartog ElektrotechniekMentioned in Intelligent traffic signal systems and more
  14. signageTraffic Service NederlandMentioned in Improving safety and traffic flow through traffic management measures

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA.C. de Graafweg
  • ThemeDigitalisation from design to construction
  • SubjectRoad construction
  • CompanyIv-Infra
  • CompanyBoskalis Nederland
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.