Intelligent traffic signal systems and more

The redesign of the A.C. de Graafweg (N241) involves more than changes to the road layout: the public lighting and traffic signal systems are also being replaced. This work has been entrusted to Ko Hartog Elektrotechniek, an all-round specialist in electrical engineering for infrastructure. The company has also been familiar with the N241 for many years through its area maintenance contract with the Province of North Holland, covering the preventive and corrective maintenance of installations in the central and northern regions.

Given the complexity and phasing of the project, Ko Hartog Elektrotechniek is part of Boskalis’s construction team for the redesign of the A.C. de Graafweg. “Our scope includes installing the new public lighting, two intelligent traffic signal systems (i-VRIs) and modifying existing traffic signal systems,” says Bjørn Dielemans, director at Ko Hartog Elektrotechniek. “We are more than capable of designing a traffic signal system ourselves, but in this case the design had already been developed by an external party. For the public lighting, by contrast, we prepared the detailed design and carried out the cable calculations.”

All red
The project is being carried out in phases. To deliver the control systems and installations, Ko Hartog Elektrotechniek is following Boskalis’s programme. Work began this summer. “For the intelligent traffic signal systems we are installing, we are using a fibre-optic link between the i-VRIs for the first time,” says Lex van Dijk, estimator and work planner at Ko Hartog Elektrotechniek. “Fibre optics make it possible to transition in future to a ‘true’ i-VRI, with approaching vehicles effectively logging on to the traffic signal system. What’s more, the plan is for an i-VRI to receive advance information from route planners so it can adjust traffic flow accordingly.” Speaking of logging on, emergency service and public transport vehicles will be able to communicate with the i-VRIs via short-range radio to receive priority. The fire station will also be linked to the systems, allowing staff to set the i-VRIs to red using a physical button inside the station.

Masts
Along part of the A.C. de Graafweg route, the adjacent drinking water transmission main is being relocated. “This is a significant intervention in the cable and pipe corridor alongside the road,” says Van Dijk. “At several junctions, we are modifying the existing traffic signal systems to allow the water main to be moved without disrupting traffic and, of course, in accordance with the regulations. For example, we are moving the masts further out so that the stop lines and road layout can be retained.” Ko Hartog Elektrotechniek is also making space in the cable and pipe corridor for the cabling for the new public lighting. “We are supplying and installing a total of 137 masts with associated luminaires,” says Jibbe van Staveren, estimator and work planner at Ko Hartog Elektrotechniek, who is very positive about the collaboration on this project. “At the preparatory stage, Boskalis organised a meeting day for all the parties involved. Everyone understands each other’s role in the project, which is extremely valuable for coordinating disciplines and jointly working out the programme.”
As a full-service installer, Ko Hartog Elektrotechniek designs, installs and maintains electrical installations for infrastructure. “Our knowledge and expertise in systems, standards and legislation enable us to develop a plan from the very first idea that fits within the public realm,” Dielemans sums up. “We then have everything we need to install and maintain the systems in-house, with our own crane trucks, mobile elevating work platforms and excavators, and a focus on public lighting and traffic signal systems. We are also happy to include charging points and site lighting in our scope. In that respect, we cover a broad range.”
Have a business enquiry for Boskalis Nederland? Get in touch
Who worked on A.C. de Graafweg
- rerouting the pipelineVan Baarsen BuisleidingenMentioned in N241: awarded on the basis of collaboration
- clientProvinciaal Waterleidingbedrijf N.V. (PWN)Mentioned in Making a difference through collaboration
- geotechnical engineering consultancyIngenieursbureau BT GeoconsultMentioned in Dual role for geotechnical engineering firm
- directional drillingVan VulpenMentioned in Relocating and upgrading a drinking water transmission main
- full-service installerKo Hartog ElektrotechniekIn this story
- signageTraffic Service NederlandMentioned in Improving safety and traffic flow through traffic management measures
Keep following this
Get an email when a new story is published. No account needed.
- ProjectA.C. de Graafweg
- SubjectRoad construction
- CompanyKo Hartog Elektrotechniek
- CompanyBoskalis Nederland