Opdrachtgevers provincie Noord-Holland en het Provinciaal Waterleidingbedrijf N.V. (PWN) hebben het project ingestoken op samenwerking.
Opdrachtgevers provincie Noord-Holland en het Provinciaal Waterleidingbedrijf N.V. (PWN) hebben het project ingestoken op samenwerking.

The ‘A.C. de Graafweg (N241) reconstruction and relocation of the drinking water transmission main’ is an unusual project for Boskalis. Not so much in technical terms, but above all because of the complex phasing puzzle. This is also why the clients, the Province of North Holland and Provinciaal Waterleidingbedrijf N.V. (PWN), structured the project around collaboration. “Price and delivery schedule were not the main focus of the tender. The contract was awarded on the basis of our approach and collaboration skills. It was quite a change of approach for us as a contractor,” acknowledges Mark van der Star, project manager at Boskalis.

Two new roundabouts are also being built on the A.C. de Graafweg.

The A.C. de Graafweg (N241) in the province of North Holland connects the N242 with the A7, running from Verlaat to Wijzend via Opmeer and crossing three municipalities: Heerhugowaard (now Dijk en Waard), Opmeer and Medemblik. “The project involves 12 kilometres of provincial road being made safer by widening the road surface and central reservation, and relocating the cycle path,” explains Van der Star. “We are also building a number of navigable culverts and two roundabouts, installing two new traffic signal systems and replacing the street lighting. Most of the work involves reconstruction, with 1.5 kilometres of new road being built to eliminate the dangerous S-bend. The widening also requires the relocation of 8 kilometres of drinking water transmission main. All in all, these are substantial works, but they are not particularly complicated from a technical point of view.”

A complex phasing puzzle

The project stands out above all for the way it was tendered. “The spaghetti of cables and pipes beneath and alongside the road, combined with the limited options for setting up diversions, makes the phasing particularly complex. The province was therefore looking for a partner capable of solving this complex phasing puzzle,” says Van der Star. “The process requirements were divided into three so-called quality documents and a team assessment, with collaboration at the heart of it. We would normally work through a project in detail during the tender and submit a price. That was not the case here. First, our management team drew up a shortlist of potential candidates for the project’s future core team, including myself. They were interviewed by an internal coach and asked about their role and vision within the future core team. Based on the results and the profiles available for the province’s selected core team, we chose the right candidates for the project team and identified their respective strengths and weaknesses. This earned us the maximum score.”

The A.C. de Graafweg (N241) in the province of North Holland connects the N242 with the A7, running from Verlaat to Wijzend via Opmeer and crossing three municipalities.

Core team

On the basis of the ‘vision for collaboration’ quality document, the province narrowed its contractor selection down to three candidates. “In the next quality document, we had to explain how we would take the lead in the design. In other words, how we would develop the detailed design (DO) as an integrated whole, based on the reference designs and with input from all stakeholders, including permit applications, planning and phasing,” explains Van der Star. The aim was to jointly arrive at a D&C contract at the end of the process. Quality document 3 covered the financial plan. This was not about the figures, but once again about collaboration: how we would involve the client in the design and budget during the construction team phase. In other words, demonstrating how we would keep the books in order. Finally, quality document 4 focused on a team assessment. Under the watchful eye of two psychologists, the core team we had formed was assessed on its collaboration dynamics with the province’s core team. We came out on top and went on to join the construction team as part of the tender process.”

Steven Geurts and Mark van der Star from the N241 project team.

Two-phase contract

After the construction team was formed, the first three months were spent mainly getting to know one another, gathering information from the client, sharing expectations and then reviewing the reference design, Van der Star continues. “We then developed the design together, determined the planning and phasing, and drew up all the contract documents jointly. After more than a year, we reached agreement in mid-March 2022. It was a two-phase contract, with a clause giving the client the option to take the compiled documents to market after all. Fortunately, that was not necessary.” Boskalis was awarded the construction contract on 14 June 2022, under a traditional UAV-GC contract. “To meet the 2025 completion date, we had already started preparatory work in September 2021, alongside the design process. This included felling trees, placing preload and relocating part of the drinking water transmission main.”

The current position is that the detailed execution design (UO) is complete and the construction phase has begun. Boskalis is now working with the province to develop a number of sustainability measures, such as using sustainable surface layers and plastic sheet piling, and deploying an electric asphalt paver. “The project comprises 54 phases, mainly across three work zones. This means that each work zone requires 17 steps to reach the final result. Although we have returned to the traditional client-contractor relationship during construction, we have expressed our ambition to carry the construction team mindset forward. For example, we hold weekly core team meetings instead of progress meetings once every four weeks, and we also schedule a weekly lean session. It is simply much more effective. The enthusiasm of the team shows that too, as everyone is pulling together to reach the 2025 milestone.”     

Een zakelijke vraag aan Boskalis Nederland? Get in touch

Wie aan A.C. de Graafweg werkte

  1. construction teamBoskalisMentioned in N241: awarded on the basis of collaboration
  2. clientProvince of North HollandMentioned in N241: awarded on the basis of collaboration
  3. clientPWNMentioned in N241: awarded on the basis of collaboration
  4. engineering consultancySwecoMentioned in N241: awarded on the basis of collaboration
  5. rerouting the pipelineVan Baarsen BuisleidingenMentioned in N241: awarded on the basis of collaboration
  6. clientProvinciaal Waterleidingbedrijf N.V. (PWN)In this story
  7. asphalt millingAducoMentioned in Maximum efficiency through selective asphalt milling
  8. engineering consultancyIv-InfraMentioned in Smart tools and bright minds
  9. temporary traffic measuresVisscher TrafficMentioned in A key role in temporary traffic management
  10. earthworksJimmink KolhornMentioned in Flexible approach to major earthworks
  11. geotechnical engineering consultancyIngenieursbureau BT GeoconsultMentioned in Dual role for geotechnical engineering firm
  12. directional drillingVan VulpenMentioned in Relocating and upgrading a drinking water transmission main
  13. full-service installerKo Hartog ElektrotechniekMentioned in Intelligent traffic signal systems and more
  14. signageTraffic Service NederlandMentioned in Improving safety and traffic flow through traffic management measures

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectA.C. de Graafweg
  • ThemeViable projects and strong collaboration
  • SubjectSpecials
  • CompanyProvinciaal Waterleidingbedrijf N.V. (PWN)
  • CompanyBoskalis Nederland