A range of dewatering techniques keeps Herepoort combination ‘high and dry’ on Aanpak Ring Zuid

Text Roel van Gils Beeld Henk van Tongeren Water & Techniek

Een deel van de werkzaamheden speelt zich af beneden de grondwaterspiegel, waarvoor combinatie Herepoort dankbaar gebruik maakt van de expertise van Henk van Tongeren Water & Techniek.
Een deel van de werkzaamheden speelt zich af beneden de grondwaterspiegel, waarvoor combinatie Herepoort dankbaar gebruik maakt van de expertise van Henk van Tongeren Water & Techniek.

Aanpak Ring Zuid covers a 12-kilometre-long area and involves the large-scale reconstruction of Groningen’s southern ring road. The extensive project is divided into five sections, each with its own specific challenges. Using a range of dewatering techniques, Henk van Tongeren Water & Techniek is keeping the Herepoort combination dry as it delivers this landmark project.

The southern ring road runs right through the city of Groningen, roughly from Hoogkerk to Westerbroek. The road is important for traffic travelling to and from the city, as well as for traffic passing through Groningen. With the city growing rapidly, its main gateway is at risk of becoming congested. Aanpak Ring Zuid aims to improve the city’s accessibility, traffic flow, liveability and safety. Some of the work is taking place below the groundwater table, where the Herepoort combination is making good use of Henk van Tongeren Water & Techniek’s expertise.

Henk van Tongeren Water & Techniek is involved in, among other things, the construction of three major structures: the reconstruction of Vrijheidsplein and Julianaplein, and the construction of the sunken section.

81 deepwell pumps

“We are involved in, among other things, the construction of three major structures: the reconstruction of Vrijheidsplein and Julianaplein, and the construction of the sunken section,” begins Jens Dikken, project manager at Henk van Tongeren Water & Techniek. “Starting with the latter, the initial plan was to use wellpoint dewatering. In practice, the soil profile proved to be slightly different. As the phasing was then also completely revised and the tunnel was to be built in a different sequence, we switched to deepwell dewatering. In hindsight, it was the only right choice, as it resulted in well-drained, dry excavation pits. At peak capacity, 81 deepwells were pumping 140 m3 per hour. The groundwater was discharged into the Winschoterdiep via a main discharge pipeline. Dewatering began in October 2020 and ended in early July this year. The tunnel deck was also moved into place during this period. This was a tense moment, as the main discharge pipeline had to be modified without interrupting the dewatering process. We solved this by setting up a 120 m3 buffer on site and emptying it with tankers. The operation took 14 hours and went exactly to plan.”

Groundwater reinjection

At Julianaplein, Henk van Tongeren Water & Techniek ran 34 deepwells continuously from May 2022 to mid-June 2023. “They were arranged in a ring around the tunnel pit to lower the groundwater level. A second ring, with 35 return wells, was installed outside it. Of the 70 m3 pumped, around 25 m3 was returned to the ground, while the rest was discharged into the Noord-Willemskanaal,” Jens explains. A total of 2.5 kilometres of discharge pipelines were laid to carry the pumped groundwater to the return wells or the discharge point. Finally, at Vrijheidsplein, Henk van Tongeren Water & Techniek opted for a dewatering technique using 10-metre deep wellpoints and drainage. “This is a different and more cost-effective technique, made possible in part by the shallow excavation pit and the existing sheet pile wall. Unlike at Julianaplein, where dewatering was installed in phases, we were able to set up the system for the Vrijheidsplein excavation pit all at once. The system ran for about a year, from February 2022 to February 2023, with a capacity of around 50 m3 per hour. We also installed a section of groundwater reinjection here to prevent subsidence of a sewer that had been laid during an earlier phase.”

Henk van Tongeren Water & Techniek’s work on Aanpak Ring Zuid is now largely complete. The project is scheduled for completion in 2024. “It really is a great asset for the city and the province, not least because so much attention is being paid to improving liveability,” says Jens. “By Dutch standards, it is unique that you will soon be able to drive into the city through a park. It is great that we at Henk van Tongeren Water & Techniek have been able to contribute to that too.”     

Een zakelijke vraag aan Henk van Tongeren Water & Techniek? Get in touch

Who worked on Aanpak Ring Zuid

  1. dewateringHenk van Tongeren Water & TechniekMentioned in Keeping the site dry at Aanpak Ring Zuid
  2. independent oversightAbomaMentioned in Exceptional safety culture at Aanpak Ring Zuid
  3. clientalliantie van Rijkswaterstaat, de gemeente en de provincie GroningenMentioned in Exceptional safety culture at Aanpak Ring Zuid
  4. Renovation portalsBirkhoff StaalwerkenMentioned in Refurbished gantries and bespoke structures
  5. slipformed barriersBKB InfraMentioned in Slipformed barrier: large-scale 3D printing
  6. contractorKnol AkkrumMentioned in Tailor-made foundation solution with a special 452-pile pile mattress
  7. scaffolding contractorGjaltema GroepMentioned in Well informed, even underground
  8. engineering consultancyMUGMentioned in “Proud that we made no mistakes on a mega-project like this”
  9. construction consortiumHerepoortMentioned in 11,000 m3 of underwater concrete for Groningen ring road

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectAanpak Ring Zuid
  • SubjectRoad construction
  • CompanyHenk van Tongeren Water & Techniek
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.