Work on Nieuwe Sluis Terneuzen on schedule

Work on Nieuwe Sluis Terneuzen on schedule

A brief overview of the work involved in building Nieuwe Sluis Terneuzen: the lock heads, where the gates and bridges will be installed, the lock chamber (the middle section of the lock), the levelling channel (for filling and emptying the lock), the lock platform (the area on either side of the chamber) and the front walls (the front faces of the lock.) 

Work is currently progressing apace on the various walls of the lock. Area manager Harm Verbeek explains: “This year, we will first build the lock head on the Westerschelde side. This is the outer head. In June, we will use 260,000 cubic metres of sand to create an artificial island, held in place by dredging screens. After a few weeks for the sand to settle, we can continue with construction.”

Goessekade extension progressing well
Goessekade is being extended. The quay is being anchored from a pontoon, now that the vibration work has been completed. “Although we are working from the water, there is no disruption to passing shipping,” says Verbeek. “Until work on the quay is completed at the end of this year, Goessekade will be closed from the new business park to the emergency quay.” A new quay has been built on Schependijk. “Most of the old quay has been demolished, and excavation is currently under way as far as the new quay, using several vessels and cranes. To ensure that ships have enough room to reach Oostsluis and, until mid-2021, Middensluis, part of Schependijk is being excavated. Shipping has been using the temporary navigation channel (Kapitein Rooiboskanaal) to reach Middensluis since early May.”

Sluishoofden

Eastern lock chamber wall, tubular piles in the water.


Lock chamber walls and lock platforms
The first diaphragm wall for the western lock chamber wall was started earlier this year. This wall consists of two parallel walls that together form the levelling channel. “The levelling channel is directly alongside the lock and is wide enough for a lorry to drive through,” Verbeek explains. “The anchor wall for this wall has now also been installed alongside the first diaphragm wall. Work on the second wall will start early next year. Behind these walls is the western lock platform, on existing ground within the Zeevaartweg construction site.”

Work has now begun on vibrating in the combi wall for the eastern lock chamber wall. Verbeek says: “Once work on Schependijk is complete, we will start piling and vibrating in the new quay wall for Nieuwe Sluis. We will then pump in soil. Both the sheet piling and the soil will be placed in the water towards Oostsluis. We will excavate Schependijk to a point where ships can continue to reach Oostsluis. Middensluis will then be removed, and the area will become the outer harbour.”

Front Wall Northwest is complete, and work is under way on the other front walls. The front walls form the front face of the lock platform, the area associated with the lock. Front Wall Northwest is complete and forms part of the primary flood defence. Front Wall Northeast is part of the outer head. “Last year, we built an earthwork for Front Wall Southwest, into which the diaphragm wall will be installed to form the front face on the canal side. The same will be done for Front Wall Southeast when work on the inner head begins,” Verbeek concludes.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFlood protection and climate-resilient water management
  • SubjectWater infrastructure
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.