Work begins on the service harbour at the Nieuwe Sluis Terneuzen

On Wednesday 11 December 2019, the sound of an old ship’s bell rang out in Terneuzen. The bell, from a former buoy-laying vessel from Terneuzen, officially marked the start of work on the service harbour. It was a celebratory occasion, attended by all the parties involved.

Wilbur van Beijnen, water engineering discipline lead and member of the technical team at the Vlaams Nederlandse Scheldecommissie (VNSC).
Before the start was marked, project director Eric Marteijn welcomed everyone. He then handed over to the chair and co-chair of the steering committee, Freddy Aerts, head of the Maritime Access division at the Department of Mobility and Public Works, and Theo van de Gazelle, chief engineer-director at Rijkswaterstaat Zee en Delta. Leendert Muller, CEO of Muller Maritime Holding, spoke on behalf of all the parties that will have a base in the service harbour. It was then time to symbolically mark the start of work.

Installing the tubular piles.
Piling work gets under way
Following the official start signal, piling work on the service harbour could begin. If all goes according to plan, the service harbour will be completed by the end of 2021. The brand-new service harbour and building in Buitenhaven West will then be 385 metres long and 90 metres wide at its widest point. We speak to Wilbur van Beijnen, water engineering discipline lead and member of the technical team at the Vlaams Nederlandse Scheldecommissie (VNSC). “I mainly work on quay structures, mooring facilities, seabed protection and flood safety in general,” says Van Beijnen, opening the conversation. “I am project manager for the work on the service harbour. Preparations for the service harbour are under way. The construction site has been set up on the long Middenhavendam, earth has been moved and the access road has been modified. This means construction traffic heading to the site cannot cross paths with the traffic controllers travelling to the traffic control centre, which is also on this dam.”

Delivery of sheet piles.
That same week, work began on vibratory driving the new combined wall, made up of steel tubular piles with sheet piles in between. “We started with one piling rig, and so far vibratory driving has been sufficient: we have not yet needed to use impact piling,” explains Van Beijnen. “Work is progressing from north to south, and piling should be complete by mid-April this year. Cofferdams are being built at the northern and southern ends. In the second quarter of 2020, we will place around 100,000 m3 of sand for them. This will be done in stages. The combined wall must be anchored with strand anchors approximately 50m long. At the Service Building, these anchors interfere with the building’s foundation piles, so precision is essential.”

Delivery of tubular piles and sheet piles.
Who will use the service harbour?
The service harbour will be used by the tugboat operators Multraship and Boluda, by Rijkswaterstaat, and by a police boat and a customs boat. Van Beijnen concludes: “The service harbour will therefore be used by maritime service providers with a direct connection to the Terneuzen lock complex. The new location is well placed in relation to the Nieuwe Sluis once it is complete. A service building and the surrounding roads will also be built alongside the service harbour. The building will house the Royal Netherlands Marechaussee, Boluda (formerly Kotug) and Muller Maritime Holding. Their boats will be berthed in the service harbour. Rijkswaterstaat’s Nautische Centrale Terneuzen is located on the same spit of land.”
Question about this story? Ask your question
Who worked on Dienstenhaven
- contractorVan Driessche & De KosterMentioned in Control building and harbour services building taking shape
- contractors' joint ventureSassevaartMentioned in Control building and harbour services building taking shape
- contractors' joint ventureTriconMentioned in Control building and harbour services building taking shape
- contractors' joint ventureBouwbedrijf VrolijkMentioned in Control building and harbour services building taking shape
Keep following this
Get an email when a new story is published. No account needed.
- ProjectDienstenhaven
- ThemeMaterials and techniques for infrastructure
- SubjectWater infrastructure