Wet excavation of a cofferdam to 10.1 metres below NAP
Text Roel van GilsImage Bonneveld

Groningen’s station area is undergoing a major transformation. More tracks and platforms are being added, along with tunnels for pedestrians, cyclists and buses. A new underground cycle parking facility is also under construction. In two phases, Bonneveld built and dewatered a vast cofferdam for main contractor Strukton Civiel. Project manager Stefan Albers looks back.
Bonneveld specialises in constructing cofferdams in the wet. “Where required, we can take care of the whole process, from excavation, placing the gravel, installing culverts and underwater concreting through to handing over the cofferdam clean and dry,” says Stefan. “We have been involved in the Groningen Spoorzone project in this capacity since the tender stage. The cofferdam was built in two phases. Phase one took place in 2021, after which train services were diverted across the new cofferdam, and we completed the second section this year. In total, we excavated 75,000 m3 of soil, cleaned 1,200 GEWI anchors and placed more than 7,000 m3 of underwater concrete.”

Excavating and suction dredging
The cofferdam is 66 metres wide, 130 metres long and 12 metres deep, reaching 10.1 metres below NAP. “We tackled both phases in almost exactly the same way,” says Erik Rigter, site supervisor at Bonneveld. “We excavated the first section dry. We then flooded the cofferdam with water from the canal and began excavating in the wet from a pontoon. In the first phase, we used two 50-tonne crawler cranes; in the second, one crawler crane, as the cofferdam was smaller. The cranes enabled us to excavate down to around 8 metres below NAP. Beneath that are harder clay and loam layers, typical of the ground conditions in Groningen. We used water jets to break up the bottom layers down to the final level of 10.1 metres below NAP, then sucked up the soil-water mixture with our DOP pumps and transported it to a dewatering depot 400 metres away. A 50-tonne Bonneveld crane was also stationed there to clear out the depot.”
The complete package
Disposal of the excavated soil was not included in Bonneveld’s scope this time. “Our client chose to handle this in-house and use the soil on another project,” Stefan explains. “We did take care of everything else, including the diving work, placing the underwater concrete floor and handing over the cofferdam clean. That is one of our strengths: we can provide the complete package.” After the first phase, Strukton began construction inside the cofferdam, allowing train services to be diverted across it. This enabled Bonneveld to excavate the second phase, located directly between the railway tracks. The only access to the cofferdam was via a temporary bridge. “Access was quite a challenge, both for transport and for positioning the concrete pumps, but in the end everything went smoothly and was completed on schedule. We also have Strukton Civiel to thank for the excellent cooperation.”
A business enquiry for Bonneveld BV? Get in touch
Who worked on it
Groningen Spoorzone in Groningen
- wet cofferdams
Bonneveld - main contractor
Strukton Civiel
Keep following this
Get an email when a new story is published. No account needed.
- ProjectGroningen Spoorzone
- ThemeUnderground construction
- SubjectWater infrastructure
- CompanyBonneveld BV
- CompanyStrukton Civiel