Dijkversterking Arcen

Future-proof pressure main route in a new dike structure

Text Roel van Gils Images GW Leidingtechniek

De nieuwe leiding is aanzienlijk sterker en heeft een verwachte levensduur van vijftig jaar.
De nieuwe leiding is aanzienlijk sterker en heeft een verwachte levensduur van vijftig jaar.

Strengthening a dike when a crucial wastewater pressure main runs right through the planned dike structure calls for a carefully considered solution. If the pipe is left in place, future maintenance will be virtually impossible without breaking open the flood defence. Rerouting it is therefore unavoidable. During the dike reinforcement in Arcen, Waterschap Limburg, Dijkzone Alliantie Arcen (DZA) and GW Leidingtechniek jointly found a solution that was also delivered largely emissions-free.

GW Leidingtechniek is one of Waterschap Limburg’s three regular contractors for pipe replacement. “We have also been working with Ploegam, one of the partners in DZA, for many years. Our collaboration took shape on earlier dike reinforcement projects, including in Nieuw-Bergen and Steyl,” says Dirk Aerts of GW Leidingtechniek. “We were also brought in at an early stage for the dike reinforcement in Arcen. Together, we determined the optimum route for the new pressure main, so that any repairs or replacement work in the future can be carried out without breaking open the flood defence.”

From PVC to HDPE

Most of the new pressure main was laid on the landward side, between the Maas and the flood defence. “We replaced the approximately 450-metre-long PVC pressure main in two phases. This allowed our work and that of Dijkzone Alliantie Arcen to be coordinated as effectively as possible,” Dirk explains. “To ensure wastewater could continue to be discharged during the work, a temporary pipe installation (TLI) was set up. The existing PVC pipe was then removed and replaced with an HDPE 400 SDR11 pressure main.” The new pipe is considerably stronger and, according to Dirk, has an expected service life of fifty years. “Waterschap Limburg will not have to worry about it for at least the first 10 to 20 years.”

The work took around five months, with high water disrupting progress several times.

Steel casing pipes

The pressure main carries all the sewage from Arcen to the Arcen pumping station. From there, the wastewater is pumped to the Blerick wastewater treatment plant. Only the section of pipe within the dike reinforcement work area was renewed and connected to the existing PVC pipe outside the area. “Where the new pipe crosses the Maas flood defence, we installed it inside steel casing pipes. This means the pressure main can be replaced or repaired in the future without breaking open the flood defence. The pipe will only need to be excavated on either side of the defence, after which a new section can easily be fed through,” says Dirk.

The work took around five months, with high water disrupting progress several times. “Whenever the Maas rose by more than a metre, work had to stop. Even so, the schedule remained manageable thanks to good coordination between all the parties involved,” says Dirk. He adds that GW Leidingtechniek made extensive use of emissions-free equipment and battery packs supplied by DZA. “The project gave us valuable experience of working emissions-free in a complex environment. I will take this knowledge and experience with me into the projects that GW Leidingtechniek will deliver emissions-free in the future.”

Een zakelijke vraag aan GW Leidingtechniek BV? Get in touch

Who worked on Dijkversterking Arcen

  1. geotechnical specialistFugroMentioned in The added value of geotechnical investigations in the Arcen dike reinforcement project
  2. grass and herb seed mixesDSV ZadenMentioned in Strong dikes start with strong grass
  3. combinantPloegamMentioned in Strong dikes start with strong grass
  4. regular contractorGW LeidingtechniekIn this story
  5. foundation specialistHakkers FunderingstechniekMentioned in Grouted anchors provide stability on the banks of the Meuse
  6. three vertical pumpsPentairMentioned in Compactly designed pumps for low and high water levels at Arcen

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectDijkversterking Arcen
  • ThemeFlood protection and climate-resilient water management
  • SubjectDijkversterking Arcen
  • CompanyGW Leidingtechniek BV
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.